In: Finance
Your division is considering two investment projects, each of which requires an up-front expenditure of $23 million. You estimate that the investments will produce the following net cash flows:
Year | Project A | Project B | ||
1 | $ 4,000,000 | $20,000,000 | ||
2 | 10,000,000 | 10,000,000 | ||
3 | 20,000,000 | 8,000,000 |
What are the two projects' net present values, assuming the cost of capital is 5%? Do not round intermediate calculations. Round your answers to the nearest dollar.
Project A: $
Project B: $
What are the two projects' net present values, assuming the cost of capital is 10%? Do not round intermediate calculations. Round your answers to the nearest dollar.
Project A: $
Project B: $
What are the two projects' net present values, assuming the cost of capital is 15%? Do not round intermediate calculations. Round your answers to the nearest dollar.
Project A: $
Project B: $
What are the two projects' IRRs at these same costs of capital? Do not round intermediate calculations. Round your answers to two decimal places.
Project A: %
Project B: %
a.i.Project A
Net present value is calculated using a financial calculator by inputting the below:
The net present value of cash flows is $7,156,570.57 $7,156,571.
Project B
Net present value is calculated using a financial calculator by inputting the below:
The net present value of cash flows is $12,028,614.62 $12,028,615.
a.ii. Project A
Net present value is calculated using a financial calculator by inputting the below:
The net present value of cash flows is $3,927,122.46 $3,927,122.
Project B
Net present value is calculated using a financial calculator by inputting the below:
The net present value of cash flows is $9,456,799.40 $9,456,799.
a.iii. Project A
Net present value is calculated using a financial calculator by inputting the below:
The net present value of cash flows is $1,190,022.19 $1,190,022.
Project B
Net present value is calculated using a financial calculator by inputting the below:
The net present value of cash flows is $7,212,870.88 $7,212,871.
b.i.Project A
Internal rate of return is calculated using a financial calculator by inputting the below:
The IRR of project is 17.45%.
Project B
Internal rate of return is calculated using a financial calculator by inputting the below:
The IRR of project is 37.15%.
In case of any query, kindly comment on the solution.