In: Finance
Problem 11-6
NPV
Your division is considering two projects with the following cash flows (in millions):
0 | 1 | 2 | 3 |
Project A | -$17 | $8 | $8 | $3 |
Project B | -$26 | $13 | $10 | $9 |
What are the projects' NPVs assuming the WACC is 5%? Round your
answer to two decimal places. (fill in the blank space)
Project A $____ million
Project B $____ million
What are the projects' NPVs assuming the WACC is 10%? Round your
answer to two decimal places.
Project A $____ million
Project B $____ million
What are the projects' NPVs assuming the WACC is 15%? Round your
answer to two decimal places.
Project A $____ million
Project B $____ million
What are the projects' IRRs assuming the WACC is 5%? Round your
answer to two decimal places.
Project A ____%
Project B ____%
What are the projects' IRRs assuming the WACC is 10%? Round your
answer to two decimal places.
Project A ____%
Project B ____%
What are the projects' IRRs assuming the WACC is 15%? Round your
answer to two decimal places.
Project A ____%
Project B ____%
If the WACC were 5% and A and B were mutually exclusive, which
would you choose? (Hint: The crossover rate is 20.19%.)
(select multiple choice)
a.Project A
b.Project B
b.Neither A, nor B
If the WACC were 10% and A and B were mutually exclusive, which would you choose? (Hint: The crossover rate is 20.19%.) (select multiple choice)
a.Project A
b.Project B
b.Neither A, nor B
If the WACC were 15% and A and B were mutually exclusive, which would you choose? (Hint: The crossover rate is 20.19%.) (select multiple choice)
a.Project A
b.Project B
b.Neither A, nor B
1) | ||||||||||
At WACC 5% | ||||||||||
Project A | $ 0.47 | million | ||||||||
project B | $ 3.23 | million | ||||||||
Working: | ||||||||||
Project A | Project B | |||||||||
Year | Discount factor | Cash flows | Present Value | Cash flows | Present Value | |||||
a | b=1.05^-a | c | d=b*c | e | f=b*e | |||||
0 | 1.0000 | $ -17 | $ -17.00 | $ -26 | $ -26.00 | |||||
1 | 0.9524 | $ 8 | $ 7.62 | $ 13 | $ 12.38 | |||||
2 | 0.9070 | $ 8 | $ 7.26 | $ 10 | $ 9.07 | |||||
3 | 0.8638 | $ 3 | $ 2.59 | $ 9 | $ 7.77 | |||||
$ 0.47 | $ 3.23 | |||||||||
2) | ||||||||||
At WACC 10% | ||||||||||
Project A | $ -0.86 | million | ||||||||
project B | $ 0.84 | million | ||||||||
Working: | ||||||||||
Project A | Project B | |||||||||
Year | Discount factor | Cash flows | Present Value | Cash flows | Present Value | |||||
a | b=1.10^-a | c | d=b*c | e | f=b*e | |||||
0 | 1.0000 | $ -17 | $ -17.00 | $ -26 | $ -26.00 | |||||
1 | 0.9091 | $ 8 | $ 7.27 | $ 13 | $ 11.82 | |||||
2 | 0.8264 | $ 8 | $ 6.61 | $ 10 | $ 8.26 | |||||
3 | 0.7513 | $ 3 | $ 2.25 | $ 9 | $ 6.76 | |||||
$ -0.86 | $ 0.84 | |||||||||
3) | ||||||||||
At WACC 15% | ||||||||||
Project A | $ -2.02 | million | ||||||||
project B | $ -1.22 | million | ||||||||
Working: | ||||||||||
Project A | Project B | |||||||||
Year | Discount factor | Cash flows | Present Value | Cash flows | Present Value | |||||
a | b=1.15^-a | c | d=b*c | e | f=b*e | |||||
0 | 1.0000 | $ -17 | $ -17.00 | $ -26 | $ -26.00 | |||||
1 | 0.8696 | $ 8 | $ 6.96 | $ 13 | $ 11.30 | |||||
2 | 0.7561 | $ 8 | $ 6.05 | $ 10 | $ 7.56 | |||||
3 | 0.6575 | $ 3 | $ 1.97 | $ 9 | $ 5.92 | |||||
$ -2.02 | $ -1.22 | |||||||||
4) | At 5% WACC | |||||||||
IRR | ||||||||||
Project A | 6.77% | |||||||||
project B | 12.26% | |||||||||
Working: | ||||||||||
IRR is the rate at which NPV is zero. | ||||||||||
Project A: | ||||||||||
NPV | ||||||||||
At 5% | $ 0.47 | |||||||||
At 10% | $ -0.86 | |||||||||
IRR | = | 5%+(10%-5%)*(0.47/(0.47+0.86)) | ||||||||
= | 6.77% | |||||||||
Project B: | ||||||||||
NPV | ||||||||||
At 5% | $ 3.23 | |||||||||
At 15% | $ -1.22 | |||||||||
IRR | = | 5%+(15%-5%)*(3.23/(3.23+1.22)) | ||||||||
= | 12.26% | |||||||||