Question

In: Finance

You are given the following information on the best guess of related outcomes for a project....

You are given the following information on the best guess of related outcomes for a project. The initial cash outlay for developing and market testing the product over the next year IS $70M. Following the test, the company will spend another $400M to put the productive capabilities in place at the END of the year. If the test is successful, which is expected to have a probability of 0.8, the expected annual cash flows will be $150M for five years. If the test fails, the expected annual cash flows will be $50M for five years. The discount rate is 12%. (a) Compute the NPV of this project at time 0 assuming that the project will be implemented regardless of the outcome of the test. Given that the value at the END of the testing year of the 5-year $150M annuity is $540.72M, and that of the 5-year $50M annuity is $180.24M. ( b) Say, you are given the option to upgrade by building a better production facility at a cost of $500M if the test fails. The upgraded facility is expected to generate annual cash flows of $100M for five years. Note that the base facility and cash flows estimates will apply if the test is successful. Compute the value of the option to upgrade at time 0.

Solutions

Expert Solution

Expected cash inflow when project gets started= 0.8*150+0.2*50=$130 million

Below is the cash flow schedule and NPV of the project:

Year Cash flow Present Value of cash flow
(Cash flow/1.12^year)
1      (470.00)                                   (419.64)
2        130.00                                     103.64
3        130.00                                       92.53
4        130.00                                       82.62
5        130.00                                       73.77
6        130.00                                       65.86
Total (NPV)                                       (1.23)

As the NPV of the project is $-1.23 million i.e. negative, the project should not be accepted.

In case of facility upgrade, Initial outlay at the end of year 1= 70+500=570 and expected annual cash flow =150*0.8+0.2*100=140

Hence, NPV calculation is given below:

Year Cash flow Present Value of cash flow
(Cash flow/1.12^year)
1      (570.00)                                   (508.93)
2        140.00                                     111.61
3        140.00                                       99.65
4        140.00                                       88.97
5        140.00                                       79.44
6        140.00                                       70.93
Total (NPV)                                     (58.33)

So, value of the upgrade option is (-58.33+1.23)=-$57.1 million


Related Solutions

You are given the following information about Project Y and Project Z. **Show Formulas Used in...
You are given the following information about Project Y and Project Z. **Show Formulas Used in Excel** Year Project Y Project Z 0 ($225,000) ($225,000) 1 210,000 95,000 2 98,000 88,000 3 --- 73,000 4 --- 87,500 The projects provide a necessary service, so whichever one is selected is expected to be repeated into the foreseeable future. Both projects have an 9% cost of capital. a. What is each project’s initial NPV without replication? Which project will you choose? b....
Given the following information, you are to determine the following Project network. Early, late and slack...
Given the following information, you are to determine the following Project network. Early, late and slack activity times. Project duration. Critical path Task Predecessor Duration A None 5 B A 8 C A 15 D A 10 E A 10 F B 10 G C, D 12 H E, 15 I G, H 7 J F,G,I 10 K J 12
1. You are considering investing in a project with the following possible outcomes:                             &n
1. You are considering investing in a project with the following possible outcomes:                                          Probability of     Investment States                                  Occurrence          Returns State 1: Economic boom         18%                  20% State 2: Economic growth       42%                  16% State 3: Economic decline      30%                   3% State 4: Depression                 10%                 -25% Calculate the expected rate of return and standard deviation of returns for this investment, respectively. A) 8.72%, 12.99% B) 7.35%, 12.99% C) 3.50%, 1.69% D) 2.18%, 1.69% 1. You are considering investing in a project with the...
You are given the following information about Project Y and Project Z. Year Proj Y Proj...
You are given the following information about Project Y and Project Z. Year Proj Y Proj Z 0 ($225,000) ($225,000) 1 210,000 95,000 2 98,000 88,000 3 — 73,000 4 — 87,500 The projects provide a necessary service, so whichever one is selected is expected to be repeated into the foreseeable future. Both projects have an 9% cost of capital. a.      What is each project’s initial NPV without replication? Which project will you choose? b.     What is the IRR of...
You are given the following information about Project Y and Project Z. Year Proj Y Proj...
You are given the following information about Project Y and Project Z. Year Proj Y Proj Z 0 ($225,000) ($225,000) 1 210,000 95,000 2 98,000 88,000 3 — 73,000 4 — 87,500                                                                                                                         The projects provide a necessary service, so whichever one is selected is expected to be repeated into the foreseeable future. Both projects have an 9% cost of capital. What is each project’s initial NPV without replication? Which project will you choose? What is the IRR of...
You are given the following information about Project Y and Project Z. Year Proj Y Proj...
You are given the following information about Project Y and Project Z. Year Proj Y Proj Z 0 ($225,000) ($225,000) 1 210,000 95,000 2 98,000 88,000 3 — 73,000 4 — 87,500 The projects provide a necessary service, so whichever one is selected is expected to be repeated into the foreseeable future. Both projects have an 9% cost of capital. a. What is each project’s initial NPV without replication? Which project will you choose? b. What is the IRR of...
You are given the following information: Project A Project B Investment $125,000 $100,000 CF-1 $12,500 $15,000...
You are given the following information: Project A Project B Investment $125,000 $100,000 CF-1 $12,500 $15,000 CF-2 $15,000 $25,000 CF-3 $25,000 $20,000 CF-4 $40,000 $10,000 CF-5 $60,000 $15,000 CF-6 $70,000 $35,000 Required rate of return 10% 10% Compute the following: a) MIRR for Project A b) MIRR for Project B c) Profitability Index for Project A d) Profitability Index for Project B
You are considering investing in a project with the following possible outcomes:      Probability of Investment States...
You are considering investing in a project with the following possible outcomes:      Probability of Investment States    Occurrence Returns State 1: Economic boom 20% 16% State 2: Economic growth       40% 12% State 3: Economic decline       20% 5% State 4: Depression        20% -5% Calculate the standard deviation of returns for this investment. Round to the nearset hundredth percent. Answer in the percent format. Do not include % sign in your answer (i.e. If your answer is 4.33%, type...
The following table contains information related to the major activities of a research project. Use the...
The following table contains information related to the major activities of a research project. Use the information to do the following: a. Compute the expected duration, variance, and standard deviation for each activity b. What is the probability that the project finishes in less than 60 days? Activity Predecessor To Tm Tp A - 3 7 12 B A 8 11 17 C B 7 13 16 D B 7 10 13 E C 14 17 23 F D 12...
You are given the following information                                     Sto
You are given the following information                                     Stock 1            Stock 2               Expected Return         30%                 15% Standard Deviation     20%                 12% Assume that the correlation coefficient between stock 1 and stock 2 returns is 10%. Compute the portfolio expected return and standard deviation if you invest 10% of your wealth in stock 1.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT