T. Crews, Inc. has been contracted to make Foolio. The recipe calls for 100 milligrams of taurine in each 16-ounce bottle. To make sure that they are in compliance, T. Crews has pulled eight bottles of Foolio from its last eleven batches and tested them for taurine content. The data from these tests is below.

Use this data for questions 8 – 14.

Mg taurine per bottle

Batch

Bottle 1

Bottle 2

Bottle 3

Bottle 4

Bottle 5

Bottle 6

Bottle 7

Bottle 8

1

103.37

104.15

105.02

105.90

105.45

107.15

109.02

109.50

2

101.00

99.42

96.72

98.50

95.13

96.15

98.83

93.30

3

103.30

100.11

101.96

102.40

100.37

100.22

106.50

101.20

4

101.00

99.73

108.31

103.75

109.70

100.35

108.00

95.93

5

101.35

104.62

108.12

103.10

99.69

103.83

97.16

104.11

6

98.05

98.58

97.35

100.25

101.39

100.55

101.34

109.07

7

96.65

98.96

92.61

107.28

97.08

99.75

107.35

104.48

8

107.00

103.56

101.39

97.65

103.65

102.62

98.26

100.67

9

100.97

103.42

101.98

99.36

112.08

103.18

100.75

104.36

10

107.15

98.30

98.25

105.33

97.45

99.12

103.95

103.71

11

107.02

104.07

106.00

101.89

102.51

103.06

102.48

97.87

  1. What is UCLX-bar?

a. Less than 100.00

b. Between 100.00 and 102.00

c. Between 102.01 and 104.00

d. Between 104.01 and 106.00

e. Greater than 106.00

  1. What is LCLX-bar?

  a. Less than 96.00

b. Between 96.00 and 97.00

c. Between 97.01 and 98.00

d. Between 98.01 and 99.00

e. Greater than 99.00

  1. All points on the X-bar chart are within the control limits.

True

False

  1. Is this process considered in control?

a. Yes, because all points on the r-chart are within the control limits

b. Yes, because all points on the r-chart and x-bar chart are within the control limits

c. No, because points on the r-chart or x-bar chart are not within the control limits

d. No, because points on R chart are too close to average

  1. When an activity has two precedent activities, its early start time is equal to:

a) The later of the two precedent activities’ “Early Start” times

b) The activity’s start time minus its duration

c) The earlier of the two precedent activities’ “Early Finish” times

d) The later of the two precedent activities’ “Early Finish” times

  1. An obstacle to supply chain integration is

a) information sharing between partners

b) limited supply chain visibility

c) considering the capabilities of partners when creating new processes

d) joint investment between firms in a supply chain

Solutions

Expert Solution

Find A2,D3 and D4 from the table of control chart constants for sample size m=9

X-bar Chart:

R-chart

Q1: What is UCL of X-bar Chart ?

d. Between 104.01 and 106.00

Q2. What is LCLX-bar?

d. Between 98.01 and 99.00

Q3.All points on the X-bar chart are within the control limits.

False (Batch 1 and Batch 2 value of X-bar is outside the UCL and LCL)

Q4.Is this process considered in control?

c. No, because points on the r-chart or x-bar chart are not within the control limits. ((Batch 1 and Batch 2 value of X-bar is outside the UCL and LCL)

Q5.When an activity has two precedent activities, its early start time is equal to:

d) The later of the two precedent activities’ “Early Finish” times

Q6.An obstacle to supply chain integration is

b) limited supply chain visibility


Related Solutions

What are statistical process control methods?
What are statistical process control methods?
a process in statistical control has a mean of .3119 and specification limit of .307 to...
a process in statistical control has a mean of .3119 and specification limit of .307 to .317. if the standard deviation of the process is .0013, what percent of the process output is expected to be below the specification limit?
In quality control, statistical process control (SPC ) is often employed to analyze the process capability...
In quality control, statistical process control (SPC ) is often employed to analyze the process capability in manufacturing or service operations. Explain the following with an example each : What is a p chart  ? What is a c chart ? There are 3 machines in your factory which can produce a ruler. The rulers as produced has a spread in length between 12.5 thru 12.4 inch. The standard deviation of the 3 machines are * 0.15 * 0.09 * 0.13...
In quality control, statistical process control (SPC ) is often employed to analyze the process capability...
In quality control, statistical process control (SPC ) is often employed to analyze the process capability in manufacturing or service operations. Explain the following with an example each : What is a p chart  ? What is a c chart ? There are 3 machines in your factory which can produce a ruler. The rulers as produced has a spread in length between 12.5 thru 12.4 inch. Given the standard deviation of the 3 machines are as follows, calculate the process...
Eight samples (m=8) have been collected from a manufacturing process that is in statistical control, and...
Eight samples (m=8) have been collected from a manufacturing process that is in statistical control, and the dimension of interest has been measured for each part. It is desired to determine the values of the center, LCL, and UCL for ?̅ and R charts. The calculated ?̅ values (units are in mm) are 2.723, 1.993, 2.008, 1.723, 1.999, 2.001, 1.995 and 2.723 The calculated R values (mm) are 0.015, 0.021, 0.020, 0.023, 0.723, 0.723, 0.014 and 0.011. Also plot the...
A process is in statistical control with   and The control chart uses a sample size of n...
A process is in statistical control with   and The control chart uses a sample size of n = 3. Specifications are at 42 ± 4. The quality characteristic is normally distributed. What conditions should we check to ensure that conclusions from a capability analysis are correct? Estimate the potential capability of the process. Estimate the actual capability of the process. How much improvement in ppm could be made in process performance if the mean could be centered at the nominal value?
Assume you know that a process is in statistical control. Is it a capable process? Give...
Assume you know that a process is in statistical control. Is it a capable process? Give an explanation for your answer
What is Statistical process control (SPC) key element?
What is Statistical process control (SPC) key element?
Statistical Process Control is a critical part of tracking performance, and evaluation of process capability is...
Statistical Process Control is a critical part of tracking performance, and evaluation of process capability is an important element to track the need to closely monitor. Using the table below and the attached X-bar, S charts, determine the process capability indices for the process (Cp, Cpk), and evaluate whether the process is capable for average surface roughness (Ra) for the inner diameter of tubing. If not, what change(s) should be made next to get Cpk ≥ 1.33? The specification requires...
Explain the difference between process capability and statistical control. Suppose that a process with a normally...
Explain the difference between process capability and statistical control. Suppose that a process with a normally distributed output has a mean of 50.0 cm. and a variance of 3.61 cm. If the specifications are 51.0 +/- 3.75 cm., a. Compute Cp and Cpk b. What are your conclusions about this process?