Question

In: Operations Management

Product A is the end item and is made from 3 units of component B and...

Product A is the end item and is made from 3 units of component B and 4 units of component C.

Component B is made from 2 units of component D and 2 units of component E. Component C is made from 2 units of component F. Lead times are as follows: A = 1 weeks, B = 2 weeks, D = 1 week, and E = 1 week.

A) Draw the bill of materials for Product A. (2 points)

B) Develop the MRP schedule for Product A and components B, D, and E only, given the gross requirement of product A. Currently, there are 50 units of B and 70 units of D on hand. No safety stock requirement.

Product A (3 points)

L4L

1 2 3 4 5 6 7 8 9 10
Gross requirement 60 200
Scheduled receipts
Available inventory                       
Net requirement
Planned order receipts
Planned order releases

Component B (3 points)

L4L

1 2 3 4 5 6 7 8 9 10
Gross requirement
Scheduled receipts
Available inventory                       50
Net requirement
Planned order receipts
Planned order releases

Component D (3 points)

FOQ = 50

1 2 3 4 5 6 7 8 9 10
Gross requirement
Scheduled receipts
Available inventory                   70
Net requirement
Planned order receipts
Planned order releases

Component E (3 points)

L4L

1 2 3 4 5 6 7 8 9 10
Gross requirement
Scheduled receipts
Available inventory
Net requirement
Planned order receipts
Planned order releases

Solutions

Expert Solution

(a)

(b)

Note: I have assumed that the 'Available Inventory' figures are ending inventory. However, if the required assumption is beginning inventory, then the entire row of 'Available Inventory' will shift towards the right by one week. So, check the assumption before making entry.


Related Solutions

Product A is an end item and is made from two units of B and three...
Product A is an end item and is made from two units of B and three of C. B is made of four units of D and two of E. C is made of two units of F and two of E.    A has a lead time of one week. B, C, and E have lead times of two weeks, and D and F have lead times of three weeks. b. If 100 units of A are required in Week...
Assume that Product Z is made of two units of A and three units of B....
Assume that Product Z is made of two units of A and three units of B. A is made of three units of C and four of D. D is made of two units of E      Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks.      Fifty two units of Product Z are required in Period 10. (Assume that...
Assume that Product Z is made of two units of A and four units of B....
Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E. Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty eight units OF Product Z are required in Period 10. (Assume that...
Assume that Product Z is made of two units of A and three units of B....
Assume that Product Z is made of two units of A and three units of B. A is made of three units of C and four of D. D is made of two units of E. Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty five units OF Product Z are required in Period 10. (Assume that...
A. The expected demand for a regular component is 2000 units per year. The item can...
A. The expected demand for a regular component is 2000 units per year. The item can be purchased from Bonjo Limited. Their lists are shown in the table below. The ordering cost is $200 and the carrying cost per unit is 75%. The cost is $20. BONJO LIMITED QUANTITY DISCOUNT 1 - 199 0% 200 - 499 2% 500 - more 5% You have just been promoted as the operations manager for this firm. Advise the purchasing manager in making...
One unit of A is made of two units of B, three units of C, and...
One unit of A is made of two units of B, three units of C, and two units of D. B is composed of one unit of E and two units of F. C is made of two units of F and one unit of D. E is made of two units of D. Items A, C, D, and F have one-week lead times; B and E have lead times of two weeks. Lot-for-lot (L4L) lot sizing is used for...
One unit of A is made of two units of B, three units of C, and...
One unit of A is made of two units of B, three units of C, and two units of D. B is composed of one unit of E and two units of F. C is made of two units of F and one unit of D. E is made of two units of D. Items A, C, D, and F have one-week lead times; B and E have lead times of two weeks. Lot-for-lot (L4L) lot sizing is used for...
Webster Company produces 40,000 units of product A, 30,000 units of product B, and 15,000 units...
Webster Company produces 40,000 units of product A, 30,000 units of product B, and 15,000 units of product C from the same manufacturing process at a cost of $390,000. A and B are joint products, and C is regarded as a by-product. The unit selling prices of the products are $40 for A, $30 for B, and $1 for C. None of the products requires separable processing. Of the units produced, Webster Company sells 33,000 units of A, 29,000 units...
Webster Company produces 25,000 units of product A, 20,000 units of product B, and 10,000 units...
Webster Company produces 25,000 units of product A, 20,000 units of product B, and 10,000 units of product C from the same manufacturing process at a cost of $340,000. A and B are joint products, and C is regarded as a by-product. The unit selling prices of the products are $30 for A, $25 for B, and $1 for C. None of the products require separable processing. Of the units produced, Webster Company sells 18,000 units of A, 19,000 units...
Webster Company produces 35,000 units of product A, 30,000 units of product B, and 14,500 units...
Webster Company produces 35,000 units of product A, 30,000 units of product B, and 14,500 units of product C from the same manufacturing process at a cost of $385,000. A and B are joint products, and C is regarded as a by-product. The unit selling prices of the products are $40 for A, $20 for B, and $2 for C. None of the products requires separable processing. Of the units produced, Webster Company sells 28,000 units of A, 29,000 units...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT