Question

In: Finance

Case 2 Geo Tech Cash Flow Template (Base Case) Year 0 1 2 3 4 5...

Case 2 Geo Tech Cash Flow Template (Base Case)

Year 0 1 2 3 4 5
$600,000.00 $1,080,000.00 $1,050,000.00 $750,000.00 $570,000.00
Revenues

Cash Costs

Set up

$280,000.00 $420,000.00 $280,000.00 $140,000.00 $140,000.00

Other operating

$240,000.00 $240,000.00 $360,000.00 $360,000.00 $240,000.00

Depreciation

$280,000.00 $280,000.00 $280,000.00
EBIT -$200,000.00 $140,000.00 $130,000.00 $250,000.00 $190,000.00
Taxes -$70,000.00 $49,000.00 $45,500.00 $87,500.00 $66,500.00

Net Operating Income After Taxes

-$130,000.00 $91,000.00 $84,500.00 $162,500.00 $123,500.00

Add Depreciation

$280,000.00 $280,000.00 $280,000.00

Net Operating Cash Flows

$150,000.00 $371,000.00 $364,500.00 $162,500.00 $123,500.00

Recovery of Capital Assets (AT)

$65,000.00

Project Cost

-$840,000.00

Total Cash Flow (CAD)

-$840,000.00 $150,000.00 $371,000.00 $364,500.00 $162,500.00 $188,500.00

Exchange Rate

0.860 0.860 0.860 0.860 0.860 0.860

Total Cash Flow (USD)

-$722,400.000 $129,000.000 $319,060.000 $313,470.000 $139,750.000 $162,110.000

Adjust with below FX rates and inflation, calculate NPV and IRR with FX rates and inflation. Note the base case has been solved. Just looking for adjustments to the last 3 rows with below inflation and FX rates. Show on Excel.

FX Forecast
Project Year 0 1 2 3 4 5
Calendar Year 2014 2015 2016 2017 2018 2019
FX Rate 0.860 0.825 0.805 0.790 0.780 0.775
US Inflation 1.50%
CAD Inflation 1.75%

Solutions

Expert Solution

NPV of cash-flows involving two countries can be computed using two approaches:

Approach 1 : Home currency approach (considering US as home country):

The net present value under this approach is calculated by (a) converting the foreign-currency cash flows of the project to the domestic currency based on the expected forward exchange rates, and (b) discounting the resultant cash flows based on the domestic currency cost of capital.

I will start the calculations from Total cash-flow (CAD) since the others have already been computed in the question.

Particulares Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Workings
Total Cash flow (CAD) (840,000)    150,000    371,000    364,500    162,500    188,500 (A)
FX rates          0.860        0.825        0.805        0.790        0.780        0.775 (B)
Cash flows in USD (722,400)    123,750    298,655    287,955    126,750    146,088 (C) = (A)*(B)
Discount factor of USD at 1.5% inflation rate 1           0.99           0.97           0.96           0.94           0.93 (D) = refer working note 1 below
Present value of cash flow in USD (722,400)    121,921    289,893    275,376    119,422    135,607 (E) =(C)*(D)
Net Present Value (USD)     219,820 Sum of all Present value of cash flow in USD

IRR is the internal rate of return at which rate NPV will be zero. We can do multiple sensitivity by changing the discount factor from 1.5% to a higher rate , stopping at a rate when NPV becomes zero. Here, IRR = 11.689%

Steps:

First , the CAD cash flows are converted to USD based on the forward exchange rates and then the USD cashflows are discounted using the USD inflation rate.

Working note 1:

Discount factor of USD inflation rate of 1.5%

Year 1 = 1/(100%+1.5%)^1=0.985

Year 2 = 1/(100%+1.5%)^2=0.971

Year 3 = 1/(100%+1.5%)^3=0.956

Year 4 = 1/(100%+1.5%)^4=0.942

Year 5 = 1/(100%+1.5%)^5=0.928

Approach 2 : Foreign currency approach (considering Canada as foreign country):

The net present value under this approach is calculated by (a) discounting the foreign currency cash flows basis foreign currency cost of capital and (b) converting the resultant present value of foreign-currency cash flows of the project to the domestic currency based on the expected forward exchange rates

I will start the calculations from Total cash-flow (CAD) since the others have already been computed in the question.

Particulares Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Workings
Total Cash flow (CAD) (840,000)    150,000    371,000    364,500    162,500    188,500 (A)
Discount factor of CAD at 1.75% inflation rate          1.000        0.983        0.966        0.949        0.933        0.917 (B) = refer working note 1 below
Cash flows in CAD (840,000)    147,420    358,348    346,014    151,606    172,838 (C) = (A)*(B)
FX rates          0.860        0.825        0.805        0.790        0.780        0.775 (D)
Present value of cash flow in USD (722,400)    121,622    288,470    273,351    118,252    133,949 (E) =(C)*(D)
Net Present Value (USD)     213,245 Sum of all Present value of cash flow in USD

IRR is the internal rate of return at which rate NPV will be zero. We can do multiple sensitivity by changing the discount factor from 1.75% to a higher rate , stopping at a rate when NPV becomes zero. Here, IRR = 11.69%

Working note 1:

Discount factor of CAD inflation rate of 1.75%

Year 1 = 1/(100%+1.75%)^1=0.983

Year 2 = 1/(100%+1.75%)^2=0.966

Year 3 = 1/(100%+1.75%)^3=0.949

Year 4 = 1/(100%+1.75%)^4=0.933

Year 5 = 1/(100%+1.75%)^5=0.917

Conclusion:

As can be seen, NPV under both the approaches are almost the same and so as IRR. This is because, the expected foreign exchange of future years reflects the inflation rates of each of the countries.


Related Solutions

Consider the cash flow for projects A and B Year: 0, 1, 2, 3, 4, 5...
Consider the cash flow for projects A and B Year: 0, 1, 2, 3, 4, 5 Project A: ($1000), 100, 600, 700, 900, 300 Project B: ($1000), 900, 700, 500, 300, 300 The cost of capital for both projects is 10% 1. Find NPV, IRR and profitability index (PI) of projects A and B. 2. If projects A and B are mutually exclusive, which project would you select 3. Find the crossover rate for projects A and B
Consider the cash flow for projects A and B Year: 0, 1, 2, 3, 4, 5
  Consider the cash flow for projects A and B Year: 0, 1, 2, 3, 4, 5 Project A: ($1000), 100, 600, 700, 900, 300 Project B: ($1000), 900, 700, 500, 300, 300 The cost of capital for both projects is 10% 1. Find NPV, IRR and profitability index (PI) of projects A and B. 2. If projects A and B are mutually exclusive, which project would you select 3. Find the crossover rate for projects A and B
Consider the following cash flows: Year 0 1 2 3 4 5 6 Cash Flow -$10,000...
Consider the following cash flows: Year 0 1 2 3 4 5 6 Cash Flow -$10,000 $2,200 $3,300 $2,500 $2,500 $2,300 $2,100 A. Payback The company requires all projects to payback within 3 years. Calculate the payback period. Should it be accepted or rejected? B. Discounted Payback Calculate the discounted payback using a discount rate of 10%. Should it be accepted or rejected? C. IRR Calculate the IRR for this project. Should it be accepted or rejected? D. NPV Calculate...
Year Cash Flow 0 –$ 15,900 1 7,930 2 9,490 3 8,970 4 7,210 5 –...
Year Cash Flow 0 –$ 15,900 1 7,930 2 9,490 3 8,970 4 7,210 5 – 3,580 Required: The company uses an interest rate of 12 percent on all of its projects. Calculate the MIRR of the project using all three methods. (Do not round intermediate calculations. Round your answers to 2 decimal places (e.g., 32.16).) MIRR Discounting approach % Reinvestment approach % Combination approach %
Year Cash Flow 0 $0 1 $250 2 $400 3 $500 4 $600 5 $600 What...
Year Cash Flow 0 $0 1 $250 2 $400 3 $500 4 $600 5 $600 What is the present (Year 0) value if the opportunity cost (discount) rate is 10 percent? Add an outflow (or cost) of $1,000 at Year 0. What is the present value (or net present value) of the stream?
Investment A: Year: 0 1 2 3 4 5 Cash flow: -$14,000 $6,000 $6,000 $6,000 $6,000...
Investment A: Year: 0 1 2 3 4 5 Cash flow: -$14,000 $6,000 $6,000 $6,000 $6,000 $6,000 Investment B: Year: 0 1 2 3 4 5 Cash flow: -$15,000 $7,000 $7,000 $7,000 $7,000 $7,000 Investment C: Year: 0 1 2 3 4 5 Cash flow: -$18,000 $12,000 $4,000 $4,000 $4,000 $4,000 The cash flows for three projects are shown above. The cost of capital is 7.5%. If an investor decided to take projects with a payback period two years or...
Year Cash flow (€) 0 - Investment -? 1 150,000 2 150,000 3 4 150,000 ?...
Year Cash flow (€) 0 - Investment -? 1 150,000 2 150,000 3 4 150,000 ? Some years ago X AG paid €15’000 for a vacant lot with planning permission. The plot could easily be sold today for 10 times that amount. X AG has however a project in mind that would occupy the plot and require investment of €200,000 but generate positive cash flows of €150,000 for the next 4 years. X AG will be able to sell the...
Discounted Cash Flow: Year (n) 0 1 2 3 4 Undiscounted cash flow -$600,000 $200,000 $200,000...
Discounted Cash Flow: Year (n) 0 1 2 3 4 Undiscounted cash flow -$600,000 $200,000 $200,000 $200,000 $200,000 DCF @ 11% ∑DCF @11% DCF @ 13% ∑DCF @13% DCF @ 15% ∑DCF @15% Notes: DCF = Discounted Cash Flow ∑DCF = Cumulative Discounted Cash Flow Refer to the following video on how to calculate IRR with Excel. Provide your completed spreadsheet in the space below. Alternatively, do the exercise in Excel and enter the values back into the table above....
TABLE 4 Project Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Cash...
TABLE 4 Project Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow A -15000 6000 7000 6000 6000 6000 B -15000 7000 7000 7000 7000 7000 C -18000 12000 2000 2000 2000 2000 "Consider the cash flow of the three projects depicted in Table 4. The cost of capital is 7.5%. If an investor decided to take projects with a payback period of 2 years...
Determine the rate of return for this project. Year 0 1 2 3 4 5 Cash...
Determine the rate of return for this project. Year 0 1 2 3 4 5 Cash flow -$12,300 $4000 $4000 $3000 $3000 $3000 14.21% 12.75% 13.11% 13.85%
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT