In: Accounting
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow:
| Direct Labor-Hours per Unit  | 
Annual Production  | 
||
| Hubs | 0.60 | 30,000 | units | 
| Sprockets | 0.20 | 46,000 | units | 
Additional information about the company follows:
Hubs require $26 in direct materials per unit, and Sprockets require $14.
The direct labor wage rate is $13 per hour.
Hubs require special equipment and are more complex to manufacture than Sprockets.
The ABC system has the following activity cost pools:
| Estimated | Activity | ||||
| Activity Cost Pool (Activity Measure) | Overhead Cost | Hubs | Sprockets | Total | |
| Machine setups (number of setups) | $ | 31,590 | 130 | 104 | 234 | 
| Special processing (machine-hours) | $ | 117,500 | 4,700 | 0 | 4,700 | 
| General factory (organization-sustaining) | $ | 82,400 | NA | NA | NA | 
Required:
1. Compute the activity rate for each activity cost pool.
2. Determine the unit product cost of each product according to the ABC system.
Answer:
| 
 Activity Cost Pool  | 
 Overhead cost  | 
 Total cost drivers  | 
 Activity Rate = ANSWER  | 
|
| 
 Machine Setup  | 
 $ 31590  | 
 234  | 
 $ 135  | 
 per setup  | 
| 
 Special Processing  | 
 $ 117500  | 
 4700  | 
 $ 25  | 
 per MH  | 
Working #1
| 
 Activity Cost Pool  | 
 Hubs  | 
 Sprockets  | 
| 
 Machine Setup  | 
 $ 17550 [130 x $135]  | 
 $ 14040 [104 x $135]  | 
| 
 Special Processing  | 
 $ 117500 [ 4700 x $25]  | 
 $ -  | 
| 
 Total Overhead cost allocated  | 
 $ 135050  | 
 $ 14040  | 
| 
 Total units  | 
 30000  | 
46000 | 
| 
 Overhead cost per unit  | 
 $ 4.50  | 
 $ 0.31  | 
Working #2
| 
 Working  | 
 Hubs  | 
 Sprockets  | 
|
| 
 A  | 
 Direct labor hours per unit  | 
 0.60  | 
0.20 | 
| 
 B  | 
 Wage rate per hout  | 
 $ 13  | 
13 | 
| 
 C= A x B  | 
 Direct labor cost per unit  | 
 $ 7.8  | 
 $ 2.6  | 
---Answer
| 
 Working  | 
 Hubs  | 
 Sprockets  | 
|
| 
 A  | 
 Direct Materials  | 
 $ 26  | 
 $ 14  | 
| 
 B [Working #2]  | 
 Direct Labor  | 
 $ 7.8  | 
 $ 2.6  | 
| 
 C [Working #1]  | 
 Overhead  | 
 $ 4.50  | 
 $ 0.31  | 
| 
 D = A+B+C  | 
 Unit Cost  | 
 $ 38.3  | 
 $ 16.91  |