Use the following for Questions 1 - 5:
You are considering two mutually exclusive projects, A and
B.
Project A costs $60,000 and generates cash flows of $9,000 for
10 years.
Project B costs $60,000 and generates cash flows of $2,000 for
seven years and then cash flows of $27,000 for three years.
Report rates in percentage form to two decimal places i.e.
10.03% not 10%
Question 1 (3 points)
Calculate what discount rate would make you indifferent
between choosing one project or another. i.e. what discount rate
produces the same NPV for both projects?
Question 1 options:
Question 2 (1 point)
Which project would you ACCEPT if your discount rate was
1%?
Question 2 options:
A)
Project A
B)
Project B
C)
Both Project A and B
D)
Neither Project A or B
Question 3 (1 point)
Which project would you ACCEPT if your discount rate was
5%?
Question 3 options:
A)
Project A
B)
Project B
C)
Both Project A and B
D)
Neither Project A or B
Question 4 (1 point)
Which project would you ACCEPT if your discount rate was
10%?
Question 4 options:
A)
Project A
B)
Project B
C)
Both Project A and B
D)
Neither Project A or B
Question 5 (2 points)
What is the highest discount rate in which you can still
produce a non-negative NPV for at least one project?