In: Operations Management
Period |
Actual |
Forecast |
1 |
13 |
|
2 |
25 |
|
3 |
35 |
|
4 |
46 |
|
5 |
66 |
|
6 |
71 |
|
7 |
80 |
|
8 |
88 |
|
9 |
95 |
|
10 |
? |
PERIOD (X) |
DEMAND (Y) |
X |
Y |
X * Y |
X^2 |
1 |
13 |
1 |
13 |
13 |
1 |
2 |
25 |
2 |
25 |
50 |
4 |
3 |
35 |
3 |
35 |
105 |
9 |
4 |
46 |
4 |
46 |
184 |
16 |
5 |
66 |
5 |
66 |
330 |
25 |
6 |
71 |
6 |
71 |
426 |
36 |
7 |
80 |
7 |
80 |
560 |
49 |
8 |
88 |
8 |
88 |
704 |
64 |
9 |
95 |
9 |
95 |
855 |
81 |
SIGMA |
45 |
519 |
3227 |
285 |
INTERCEPT = (SIGMA(Y) * SIGMA(X^2) - SIGMA(X) * SIGMA(XY)) / (N * SIGMA(X^2) - SIGMA(X)^2)
INTERCEPT = (519 * 285) - (45 * 3227) / ((9 * 285) - 45^2) = 5
SLOPE = ((N * SIGMA(XY)) - (SIGMA(X) * SIGMA(Y))) - (N * SIGMA(X^2) - SIGMA(X)^2)
SLOPE = ((9 * 3227) - (45 * 519) / ((9 * 285) - 45^2) = 10.533
Y = A + B(X), WHERE A IS THE INTERCEPT, B IS THE SLOPE, X IS THE PERIOD = 5 + (10.533 * X)
FOR THE VALUE OF X = 10 FORECAST = 5 + (10.533 * 10) = 110.33