Question

In: Statistics and Probability

You are the construction manager of a company that build standard shopping centres across the world....

You are the construction manager of a company that build standard shopping centres across the world. You meet a supplier who promises you material that allows builders to build significantly quicker than what the existing material allows, without compromising the quality, safety etc of the structures. The CEo asks you to assess during the year and give a report at the end of the year with a recommendation of whether to buy the new material or not. You take a sample of projects from around the world and use new materials from some and old materials from others. This is the information gathered:

Material New (experiment) Existing/Old
Sample size of projects nx = 12 ny = 8
Avg time taken to complete a building x = 6 months y = 8 months
Standard deviation sx = 3 months sy =2 months

Use the p value method to determine if the suppliers claim is valid to decide whether to continue using the existing material or adopt the new method post the 1 year of experimentation.

1) Decision criteria

Ho

H1

You need to perform a _____ tailed test

2) Assumption:

3) Degrees of freedom

4) Choice of distribution and motivation

5) Test statistic (show formula and all workings)

6) P-value (all workings and analysis of p-value)

7) Decision

8) Interpretation and conclusion

9) what would your decison be if

p-value < x

p-value > x

Solutions

Expert Solution

n1 = 12

= 6

s1 = 3

n2 = 8

= 8

s2 = 2

1) The null and alternative hypothesis is

We need to perform the 2 sample t (independent) test.

For doing this test first we have to check the two groups have population variances are equal or not.

The null and alternative hypothesis is

Test statistic is

F = largest sample variance / Smallest sample variances

F = 9 / 4 = 2.25

Degrees of freedom => n1 - 1 , n2 - 1 => 12 - 1 , 8 - 1 => 11 , 7

Critical value = 3.603 ( Using f table)

Critical value > test statistic so we fail to reject null hypothesis.

Conclusion: The population variances are equal.

So we have to use here pooled variance.

2) Assumption: The population variances are equal and population distribution follows the normal distribution.

3) Degrees of freedom = n1 + n2 - 2 = 12 + 8 - 2 = 18

4) T distritution.

5) Test statistic is

Degrees of freedom = n1 + n2 - 2 = 12 + 8 - 2 = 18

6) P-value = 2*P(T< - 1.65) = 2*0.0581 = 0.1163

7) P-value > 0.05 we fail to reject the null hypothesis.

8) Conclusion: There is sufficient evidence to support the supplier's claim is valid to decide whether to continue using the existing material or adopt the new method post the 1 year of experimentation.


Related Solutions

You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project involving the construction of a multi-screen cinema and retail complex. You have had safety concerns in relation to the appointed scaffolding company, over a three weeks period. The issues raising concern include scaffolds being handed over in an unsafe state (missing toe boards, inadequate bracing and ties), scaffold workers operating at height not being tied-off, poor housekeeping and storage of materials on-site. Outline your...
Problem 1 The manager of a construction company must decide whether to build single family homes,...
Problem 1 The manager of a construction company must decide whether to build single family homes, apartments, or condominiums. Profits (in thousands of dollars) are given in the following table and depend on various possible population trends. The probability of a declining population is 0.3, the probability for a stable population is 0.5 and the probability of a growing population is 0.2 Payoff table (in thousands of dollars): Population Declining Stable Growing Single Family Homes 220 80 75 Apartments 85...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,700,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 486500 $1,000,000 Estimated costs to complete 903,500 0 Billings during the year 455,000 1,245,000 Cash collections during the year 355,000 1,345,000 ) Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,820,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 518,000 $ 1,120,000 Estimated costs to complete 962,000 0 Billings during the year 410,000 1,410,000 Cash collections during the year 310,000 1,510,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,730,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 476,000 $ 1,030,000 Estimated costs to complete 884,000 0 Billings during the year 470,000 1,260,000 Cash collections during the year 370,000 1,360,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,900,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 420,000 $ 1,200,000 Estimated costs to complete 980,000 0 Billings during the year 450,000 1,450,000 Cash collections during the year 350,000 1,550,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,730,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 476,000 $ 1,030,000 Estimated costs to complete 884,000 0 Billings during the year 470,000 1,260,000 Cash collections during the year 370,000 1,360,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,760,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2015 2016   Costs incurred during the year $ 399,000 $1,060,000      Estimated costs to complete 931,000 0      Billings during the year 485,000 1,330,000      Cash collections during the year 385,000 1,430,000    Required information Assume that Beavis recognizes revenue on this contract over time...
Beavis Construction Company was the low bidder on a construction project to build an office building...
Beavis Construction Company was the low bidder on a construction project to build an office building for $8,000,000. The project was begun in 2017 and completed in 2019. Cost and other data are presented below: 2017 2018 2019 Costs incurred during the year $ 1,500,000 $4,500,000 $1,550,000 Estimated costs to complete 4,500,000 1,500,000 -0- Billings during the year 1,400,000 5,200,000 1,400,000 Cash collections during the year 1,000,000 4,000,000 3,000,000 Assume that Beavis recognizes revenue on this contract over time according...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2012 and completed in 2013. Cost and other data are presented below:                                                                                     2012                           2013 Costs incurred during the year                               $450,000                $ 1.100,000 Estimated costs to complete 1,050,000                      0 Billings during the year                                            400,000                    1,400,000 Cash collections during the year                             300,000                     1,500,000 Assume that Beavis uses the percentage- of- completion method for...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT