Problem 10.35
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent. Costs and cash flows for each project are given in the following table.
Year | Project 1 | Project 2 | ||
0 | -$1,308,961 | -$1,198,212 | ||
1 | 257,000 | 344,000 | ||
2 | 363,000 | 344,000 | ||
3 | 425,000 | 344,000 | ||
4 | 520,000 | 344,000 | ||
5 | 761,000 | 344,000 |
Calculate NPV and IRR of two projects. (Enter negative
amounts using negative sign, e.g. -45.25. Do not round discount
factors. Round other intermediate calculations and final answer to
0 decimal places, e.g. 1,525. Round IRR answers to 2 decimal
places, e.g. 15.25 or 12.25%.)
NPV of project 1 is | $ | ||
NPV of project 2 is | $ | ||
IRR of project 1 is | % | ||
IRR of project 2 is | % |
Which project should be accepted?
Crane Corp. should accept
project 2project 1neither project |