Question

In: Advanced Math

John’s Construction has three projects under way. Each project requires a regular supply of gravel, which...

John’s Construction has three projects under way. Each project requires a regular supply of gravel, which can be obtained from three quarries. Shipping costs differ from location to location, and are summarized in the table.

From: Job 1 Job 2 Job 3 Tonnage allowance
Quarry A $9 $8 $7 1500
Quarry B $7 $11 $6 1750
Quarry C $4 $3 $12 2750
Job Requirements (tonnes) 2000 3000 1000 6000

Formulate a transportation model (but do not attempt to solve it) which could be used to determine the amount of gravel to be shipped from each quarry to the various job sites.

Solutions

Expert Solution

Let the amount of gravel from Quarry A to Job 1 (In tonnes) =

Let the amount of gravel from Quarry A to Job 2 (In tonnes) =

Let the amount of gravel from Quarry A to Job 3 (In tonnes) = ​​​​​​​

Let the amount of gravel from Quarry B to Job 1 (In tonnes) =

Let the amount of gravel from Quarry B to Job 2 (In tonnes) = ​​​​​​​

Let the amount of gravel from Quarry B to Job 3 (In tonnes) = ​​​​​​​

Let the amount of gravel from Quarry C to Job 1 (In tonnes) =

Let the amount of gravel from Quarry C to Job 2 (In tonnes) = ​​​​​​​

Let the amount of gravel from Quarry C to Job 3 (In tonnes) =

Our objective is to minimise the shipping costs

Therefore we can formulate the objective as

Minimise

Subject to the constraints

(Tonnage allowance in quaary A)

(Tonnage allowance in quaary B)

​​​​​​​ (Tonnage allowance in quaary C)

(Job requirement in job 1)

(Job requirement in job 2)

(Job requirement in job 3)

​​​​​​​ (Non negativity)


Related Solutions

Marc Hernandez’s construction firm currently has three projects in progress. Each requires a specific supply of...
Marc Hernandez’s construction firm currently has three projects in progress. Each requires a specific supply of gravel. There are three gravel pits available to provide for Hernandez’s needs, but shipping costs differ from location to location. To From Job 1 Job 2 Job 3 Tonnage Allowance Central pit $9   $ 8    $ 7             3,000 Rock pit    $7   $11    $ 6            4,000 Acme pit   $4   $ 3     $12           6,000 Job requirements (tons) (Job1) 2,500 (Job 2) 3,750 (Job 3) 4,850 A....
Nokia has two Projects. Project A and Project B. Which project should be accepted under each...
Nokia has two Projects. Project A and Project B. Which project should be accepted under each measurement. Project A Project B NPV ($) 2578 3842 IRR ($) 12 14 MIRR (%) 10 11 PI 1.2 1.5 Payback Period (years) 3 3.8 Discounted Payback Pd (Years) 4.2 4.8 Nokia's cost of capital is 8%. Its critical payback period is 2 years and the critical discount payback period is 3 years NPV - (Project A be accepted, Project B be accepted, or...
Walsh Company is considering three independent projects, each of which requires a $6 million investment. The...
Walsh Company is considering three independent projects, each of which requires a $6 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented below: Project H (High risk): Cost of capital = 16% IRR = 21% Project M (Medium risk): Cost of capital = 14% IRR = 11% Project L (Low risk): Cost of capital = 7% IRR = 9% Note that the projects' costs of capital vary because the projects have...
Lane Industries is considering three independent projects, each of which requires a $2.5 million investment. The...
Lane Industries is considering three independent projects, each of which requires a $2.5 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 15% IRR = 17% Project M (medium risk): Cost of capital = 10% IRR = 8% Project L (low risk): Cost of capital = 7% IRR = 8% Note that the projects' costs of capital vary because the projects have...
Lane Industries is considering three independent projects, each of which requires a $2.5 million investment. The...
Lane Industries is considering three independent projects, each of which requires a $2.5 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 13% IRR = 15% Project M (medium risk): Cost of capital = 10% IRR = 8% Project L (low risk): Cost of capital = 8% IRR = 9% Note that the projects' costs of capital vary because the projects have...
Lane Industries is considering three independent projects, each of which requires a $2.5 million investment. The...
Lane Industries is considering three independent projects, each of which requires a $2.5 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 13% IRR = 15% Project M (medium risk): Cost of capital = 10% IRR = 8% Project L (low risk): Cost of capital = 8% IRR = 9% Note that the projects' costs of capital vary because the projects have...
Calculating Project NPV Down Under Boomerang, Inc., is considering a new three-year expansion project that requires...
Calculating Project NPV Down Under Boomerang, Inc., is considering a new three-year expansion project that requires an initial fixed asset investment of $3,950,000. The fixed asset will be depreciated straight-line to zero over its three -year tax life, after which time it will be worthless. The project is estimated to generate $3,175,000 in annual sales, with costs of $1,455,000. The tax rate is 35 percent and the required return is 10 percent. What is the Project's NPV?
draft a simple contract for a small construction project (remodeling a kitchen for instance) under which...
draft a simple contract for a small construction project (remodeling a kitchen for instance) under which the homeowner hires a independent contractor to do the work. Consider three points of view, the homeowner, the contractor, and the subcontractor. What clauses would each party want in his/her contract to assure satisfactory performance by the others? What recourse would each party have if the others did not perform?
Leeds Company has an opportunity to invest in one or two new projects. Project A requires...
Leeds Company has an opportunity to invest in one or two new projects. Project A requires a $350,000 investment for new machinery with a four-year life and no salvage value. Project B requires a $350,000 investment for new machinery with a three-year life and a $10,000 salvage value. The two projects yield the following predicted annual results. The company uses straight-line depreciation and cash flows occur evenly throughout each year. Project A Sales $350,000 Expenses: Direct materials 49,000 Direct labor...
Down Under Boomerang, Inc., is considering a new three-yearexpansion project that requires an initial fixed...
Down Under Boomerang, Inc., is considering a new three-year expansion project that requires an initial fixed asset investment of $2.97 million. The fixed asset falls into the three-year MACRS class. The project is estimated to generate $2,170,000 in annual sales, with costs of $847,000. The project requires an initial investment in net working capital of $390,000, and the fixed asset will have a market value of $255,000 at the end of the project.a. If the tax rate is 24 percent,...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT