In: Computer Science
A plant manager is considering buying additional stamping machines to accommodate increasing demand. The alternatives are to buy 1 machine, 2 machines, or 3 machines. The profits realized under each alternative are a function of whether their bid for a recent defense contract is accepted or not. The payoff table below illustrates the profits realized (in $000's) based on the different scenarios faced by the manager.
Alternative Bid Accepted Bid Rejected
Buy 1 machine $10 $5
Buy 2 machines $30 $4
Buy 3 machines $40 $2
Refer to the information above. Assume that based on historical bids with the defense contractor, the plant manager believes that there is a 65% chance that the bid will be accepted and a 35% chance that the bid will be rejected.
a. Which alternative should be chosen using the expected monetary value (EMV) criterion?
b. What is the expected value under certainty?
c. What is the expected value under perfect information (EVPI)?
(I need an Excel Spreadsheet)
a. Which alternative should be chosen using the expected monetary value (EMV) criterion?
b. What is the expected value under certainty?
ACTUALLY I WILL DO PAPER WORK THAT ALSO I CAN SHARE THEN YOU CAN EASILY UNDERSTOOD
A B C
Alternative Bid accepted Bid rejected
Machine 1 10 5
Machine 2 30 4
Machine 3 40 2
=MAX(B2:B4) =MAX(C2:C4)
Probabilities 0.65 0.35 7
certainty =(B6*B5)+(C6*C5)
Alternative Bid accepted Bid rejected Expected payoff under risk 1
Machine 1 10 5 =SUMPRODUCT(B11:C11,$B$15:$C$15)
Machine 2 30 4 =SUMPRODUCT(B12:C12,$B$15:$C$15)
Machine 3 40 2 =SUMPRODUCT(B13:C13,$B$15:$C$15)
Probabilities 0.65 0.35
Expected value under risk =MAX(D11:D13) 18
Expected value of perfect information = Expected value under 20 uncertainty - Expected value under risk
=C7-D17
=E19*1000
A B C
Alternative Bid accepted Bid rejected
Machine 1 $10 $5
Machine 2 $30 $4
Machine 3 $40 $2
$40 $5
Probabilities 0.65 0.35
Expected value under certainity $27.75
Alternative Bid accepted Bid rejected Expected payoff under risk
Machine 1 $10 $5 8.25
Machine 2 $30 $4 20.9
Machine 3 $40 $2 26.7
Probabilities 0.65 0.35
Expected value under risk 26.7
Expected value of perfect information = Expected value $1.05 20 under uncertainity - Expected value under risk I $1,050.00
c. What is the expected value under perfect information (EVPI)?
b.