In: Finance
You are considering the following three projects. A & B are mutually exclusive while C is independent.
Question: On one graph, plot the NPV profile for Both projects, A&B.
please show how on excel
Following are their expected cash flows
year |
project A |
Project B |
Project C |
0 |
-60,000.00 |
-40,000.00 |
-20,000.00 |
1 |
0 |
40,000.00 |
35,000.00 |
2 |
82,000.00 |
40,000.00 |
30,000.00 |
3 |
60,000.00 |
20,000.00 |
2,000.00 |
4 |
20,000.00 |
10,000.00 |
-40,000.00 |
Here in question ask for NPV graphs for project A&B only. So i don't take project C cash flows in answer.