Question

In: Finance

Swenson's is considering two mutually exclusive projects, Projects A and B, and has determined that the...

Swenson's is considering two mutually exclusive projects, Projects A and B, and has determined that the crossover rate for these projects is 11.7 percent and the required return for both projects is 9 percent. Given this you know that:

Multiple Choice

  • both projects have a zero NPV at a discount rate of 11.7 percent.

  • neither project will be accepted if the discount rate is less than 11.7 percent.

  • the project that is acceptable at a discount rate of 11 percent should be rejected at a discount rate of 12 percent.

  • both projects have a negative NPV at discount rates greater than 11.7 percent.

  • both projects provide an internal rate of return of 11.7 percent.

Solutions

Expert Solution

Crossover rate is the rate at which the NPV of the two projects is equal. For rates lower than this, one project is better than the other and for rate higher than this the other projects becomes better till the time NPV remains positive.

At the crossover rate, the investor is indifrrent between the two projects if the NPV is positive for both the projects.

Having understood this let's look at the options:

  • Both project might have 0 NPV at the crossover rate but it is not always true and is not being implied by the given information or the definition of the crossover rate. So this option is incorrect.

  • If any one project has a positive NPV at the rate lower than the crossover rate, it can be selected if this NPV is higher than that of the other project. So this option is also incorrect.

  • As explained in the definition, one project is acceptable at rates below the crossover rate and the other project is accepted at a rate higher than the crossover rate. So if the crossover rate is 11.7% then one project will have a higher NPV at 11% and the other will have a highe NPV at 12% so this statement is correct

  • This is not at all implied by the crossover rate. It only implies that the NPV is equal. So this option is incorrect.

  • Even this is not implied by the crossover rate, IRR is the rate at which the NPV = 0, it is not the rate at which the NPV becomes equal for both the projects. So this option is incorrect.


Related Solutions

Heller Airlines is considering two mutually exclusive projects, A and B. The projects have the same...
Heller Airlines is considering two mutually exclusive projects, A and B. The projects have the same risk. Below are the cash flows from each project: Project A Project B Year Cash Flow Cash Flow 0 -$2,000 -$10,000 1 6,000 15,000 a. Graph the NPV profile of each investment. b. Indicate the crossover point and calculate the crossover rate. c. If the cost of capital is 8%, which project should be chosen and why?
KORONA Manufacturing is considering investing in either of two mutually exclusive projects, A and B. The...
KORONA Manufacturing is considering investing in either of two mutually exclusive projects, A and B. The firm has a 14 percent cost of capital, and the risk-free rate is currently 9 percent. The initial investment, expected cash inflows, and certainty equivalent factors associated with each of the projects are shown in the following table. Project A Project B Initial investment (II) $ 40,000 $ 56,000 Year (t) Cash inflows (CFt) Certainty equivalent factors (αt) Cash inflows (CFt) Certainty equivalent factors...
Good old XYZ Corp. is considering two mutually exclusive projects, A & B in order to...
Good old XYZ Corp. is considering two mutually exclusive projects, A & B in order to expand their product line. The cost accountants determined the following: A’s initial investment must be $42,400, while project B will cost $60,000. Project A has projected cash flows of $23,000 a year, and project B of $24,000 a year. The project should last 3 years.   In addition, the following rates has been given: the prime = 7%; Labor = 6%; the firm’s cost of...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates cash flows of $10,000 for 10 years. Project B costs $80,000 and generates cash flows of $2,000 for six years and then cash flows of $28,000 for four years. Report rates in percentage form to two decimal places i.e. 10.03% not 10% At what discount rate would make you indifferent between choosing one project or another? What is the highest discount rate in which...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates cash flows of $12,000 for 10 years. Project B costs $60,000 and generates cash flows of $2,000 for six years and then cash flows of $29,000 for four years. Which project would you accept if your discount rate was 10%? Which project would you accept if your discount rate was 5%?
Considering two mutually exclusive projects. The crossover rate between these two projects is ___ percent and...
Considering two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is less than the crossover rate. Year Project A Project B 0 −$27,000 −$27,000 1 10,000 18,100 2 10,000 8,000 3 18,000 10,120 11.75%; A 11.75%; B 17.19%; B 18.64%; A 17.19%; A
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0&
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0                  -$35,000                  -$35,000     1                     22,000                     13,000     2                     20,000                     21,000     3                     13,000                     22,000 What is the internal rate of return of PROJECT A?
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0&
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0                  -$35,000                  -$35,000     1                     22,000                     13,000     2                     20,000                     21,000     3                     13,000                     22,000 What is the crossover point?
You are considering the following two mutually exclusive projects. The crossover rate between these two projects...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is greater than the crossover rate. Year Project A Project B 0 −$26,000 −$26,000 1 9,500 17,590 2 9,500 7,500 3 17,500 9,610 rev: 05_02_2019_QC_CS-167236, 05_09_2019_QC_CS-168369, 09_24_2019_QC_CS-182411 Multiple Choice 18.39%; A 11.89%; B 16.97%; B 11.89%; A 16.97%; A
You are considering the following two mutually exclusive projects. The crossover rate between these two projects...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is greaterthan the crossover rate. Year Project A Project B 0 −$30,000 −$30,000 1 11,500 19,630 2 11,500 9,500 3 19,500 11,650
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT