In: Accounting
Complete the problems below on variance analysis.
Morgan Clay Products manufactures clay molded pottery on an
assembly line. Its standard costing system uses two cost
categories, direct materials and conversion costs. Each product
must pass through the Molding Department and the Finishing
Department. Direct materials are added at the beginning of the
production process. Conversion costs are allocated evenly
throughout production.
Data for the Assembly Department for August 2017 are:
Work in process, beginning inventory: 2600 units
Direct materials (100% complete)
Conversion costs (35% complete)
Units started during August 715 units
Work in process, ending inventory: 520 units
Direct materials (100% complete)
Conversion costs (55% complete)
Costs for August:
Standard costs for Assembly:
Direct materials $18 per unit
Conversion costs $35.50 per unit
Work in process, beginning inventory:
Direct materials $12,600
Conversion costs $8250
Part 2A: Variance Problem
Castleton Corporation manufactured 36,000 units during March. The
following fixed overhead data relates to March:
Actual Static Budget
Production 36,000 units 34,000 units
Machine-hours 6,960 hours 6,800 hours
Fixed overhead costs for March $164,700 $156,400
Compute the fixed overhead variances.
Part 2B: Variance Problem
Russo Corporation manufactured 21,000 air conditioners during
November. The overhead cost-allocation base is $34.50 per
machine-hour. The following variable overhead data pertain to
November:
Actual Budgeted
Production 21,000 units 23,000 units
Machine-hours 12,700 hours 13,800 hours
Variable overhead cost per machine-hour:
$34.00 $34.50
Compute the variable overhead variances.
Fixed overhead | ||
Fixed OH Volume Variance | $ 9,200.00 | Favorable |
Fixed OH Budget Variance | $ 8,300.00 | Unfavorable |
Fixed OH Cost Variance | $ 900.00 | Favorable |
Fixed Overhead Volume Variance = (Actual Activity – Normal Activity) × Budgeted Fixed Overhead Rate | |
Minus sign indicate Favorable variance. | |
Budgeted Fixed Overheads | 156,400 |
Actual Fixed Overheads | 164,700 |
Budgeted units | 34,000 |
Actual units | 36,000 |
Overhead rate =( Budgeted Fixed Overheads / Budgeted units) | |
Applied Fixed Overhead = (Budgeted Fixed Overhead Rate * Actual units) | |
Budgeted Fixed Overhead Rate (156400/34000) | $ 4.60 |
Budgeted Fixed Overheads | 156400 |
Less: Applied Fixed Overhead (4.6*36000) | -165600 |
Fixed OH Volume Variance | $ (9,200) |
Indicate | Favorable |
Actual Fixed Overheads | 164700 |
Less: Budgeted Fixed Overheads | -156400 |
Fixed OH Budget Variance | $ 8,300 |
Indicate | Unfavorable |
Fixed OH Cost Variance (Total of both variance) | $ (900) |
Indicate | Favorable |
Variable Overhead | ||
Variable OH Rate Variance | $ 6,350.00 | Favorable |
Variable OH Efficiency Variance | $ 3,450.00 | Unfavorable |
Variable OH Cost Variance | $ 2,900.00 | Favorable |
Standard machine hours per units (13800/23000) | 0.60 | |
Minus sign indicate Favorable variance. | ||
Measure | Machine Hour | |
Standard variable overhead rate per Machine Hour | $ 34.50 | |
Actual variable overhead rate per Machine Hour | $ 34.00 | |
21000*0.60 | Standard Machine Hours | 12,600 |
Actual Machine Hours | 12,700 | |
Actual variable overhead rate per Machine Hour | 34.00 | |
Less | Standard variable overhead rate per Machine Hour | -34.50 |
Difference | -0.50 | |
Multiply | Actual Machine Hours | 12700 |
Variable OH Rate Variance | $ (6,350.00) | |
Indicate | Favorable | |
Actual Machine Hours | 12700 | |
Less | Standard Machine Hours | -12600 |
Difference | 100 | |
Multiply | Standard variable overhead rate per Machine Hour | 34.50 |
Variable OH Efficiency Variance | $ 3,450.00 | |
Indicate | Unfavorable | |
Variable OH Cost Variance (Total of both variance) | $ (2,900.00) | |
Indicate | Favorable |