Question

In: Accounting

Complete the problems below on process costing and variance analysis. Part 1: You must prepare two...

Complete the problems below on process costing and variance analysis.

Part 1: You must prepare two process costing cost reports – one using the weighted average method and one using the fifo method.  
Morgan Clay Products manufactures clay molded pottery on an assembly line. Its standard costing system uses two cost categories, direct materials and conversion costs. Each product must pass through the Molding Department and the Finishing Department. Direct materials are added at the beginning of the production process. Conversion costs are allocated evenly throughout production.

Data for the Assembly Department for August 2017 are:
Work in process, beginning inventory: 2600 units
Direct materials (100% complete)
Conversion costs (35% complete)

Units started during August 715 units

Work in process, ending inventory: 520 units
Direct materials (100% complete)
Conversion costs (55% complete)

Costs for August:
Standard costs for Assembly:
Direct materials $18 per unit
Conversion costs $35.50 per unit

Work in process, beginning inventory:
Direct materials $12,600
Conversion costs $8250

Part 2A: Variance Problem
Castleton Corporation manufactured 36,000 units during March. The following fixed overhead data relates to March:
Actual Static Budget
Production 36,000 units 34,000 units
Machine-hours 6,960 hours 6,800 hours
Fixed overhead costs for March $164,700 $156,400
Compute the fixed overhead variances.

Part 2B: Variance Problem
Russo Corporation manufactured 21,000 air conditioners during November. The overhead cost-allocation base is $34.50 per machine-hour. The following variable overhead data pertain to November:

Actual Budgeted
Production 21,000 units 23,000 units
Machine-hours 12,700 hours 13,800 hours
Variable overhead cost per machine-hour:
$34.00 $34.50
Compute the variable overhead variances.

Solutions

Expert Solution

Dear student, we cannot able to post solution more than one question as per our policy.
Step for solution
Step 1 Equivalent Units of production = Physical units multiplied by % of competition
Step 2 Calculate total cost to be accounted for
Step 3 Cost per Equivalent Unit = Cost incurred during Month / Equivalent Units of production
Step 4 Cost assigned to units transferred out = Cost in beginning WIP + Cost incurred for complete beginning WIP + Cost of units in Started and completed
Step 5 Cost assigned to units ending work in progress = equivalent units in ending WIP inventory * Cost per Equivalent Unit
For direct material 100% unit completed in the previous period. It means remaining 0% completed in this month.
For conversion cost 35% unit completed in the previous period. It means the remaining 65% completed in this month.
Direct material Conversion Cost
Cost per Equivalent Unit for month of August $          18.00 $          35.50
Multiply: Equivalent Units of production under FIFO Method 715 2171
Cost incurred during Month $ 12,870.00 $ 77,070.50
Morgan Clay
Assembly Department production Report
First in First out (FIFO) Method
Month ended August 31, 2017
Summary of Physical units
Units in beginning WIP inventory 2600
Units started during month 715
Total unit to be accounted for 3315
Units completed and transferred out (3315-520) 2795
Units in ending WIP inventory 520
Total unit accounted for 3315
Equivalent Units of production
Particulars Physical units Direct material Conversion Cost
% units % units
units in beginning WIP inventory 2600 0% 0 65% 1690
Units in Started and completed (2795-2600) 195 100% 195 100% 195
units in ending WIP inventory 520 100% 520 55% 286
Equivalent Units of production 715 2171
Summary of cost to be accounted
Direct material Conversion Cost Total
Cost in beginning WIP $   12,600.00 $      8,250.00 $    20,850.00
Cost incurred during Month (Add) $   12,870.00 $    77,070.50 $    89,940.50
total cost to be accounted for $   25,470.00 $    85,320.50 $ 110,790.50
cost per Equivalent Unit
Cost incurred during Month 12870 77070.5
Equivalent Units of production 715 2171
Cost per Equivalent Unit 18.00 35.50 53.50
Assign costs to units transferred out and units in ending WIP inventory
cost assigned to units transferred out
Direct material $   12,600.00
Conversion Cost $      8,250.00
Cost in beginning WIP $    20,850.00
Direct material (0*18) $                   -  
Conversion Cost (1690*35.5) $   59,995.00
Cost incurred for complete beginning WIP $    59,995.00
Direct material (195*18) $      3,510.00
Conversion Cost (195*35.5) $      6,922.50
Cost of units in Started and completed $    10,432.50
cost assigned to units transferred out $    91,277.50
cost assigned to units ending work in progress
Direct material (520*18) $      9,360.00
Conversion Cost (286*35.5) $   10,153.00
cost assigned to units ending work in progress $    19,513.00
Total cost assigned $ 110,790.50
Step for solution
Step 1 Equivalent Units of production = Physical units multiplied by % of competition
Step 2 Calculate total cost to be accounted for
Step 3 Cost per Equivalent Unit = total cost to be accounted for / Equivalent Units of production
Step 4 Cost assigned to units transferred out = units completed and transferred out * Cost per Equivalent Unit
Step 5 Cost assigned to units ending work in progress = equivalent units in ending WIP inventory * Cost per Equivalent Unit
Morgan Clay
Assembly Department production Report
Weighted average Method
Month ended August 31, 2017
Summary of Physical units
Units in beginning WIP inventory 2600
Units started during month 715
Total unit to be accounted for 3315
Units completed and transferred out (3315-520) 2795
Units in ending WIP inventory 520
Total unit accounted for 3315
Equivalent Units of production
Particulars Physical units Direct material Conversion Cost
% units % units
units in beginning WIP inventory 2600 100% 2600 100% 2600
Units in Started and completed (2795-2600) 195 100% 195 100% 195
units in ending WIP inventory 520 100% 520 35% 182
Equivalent Units of production 3315 2977
Summary of cost to be accounted
Direct material Conversion Cost Total
Cost in beginning WIP $    12,600.00 $      8,250.00 $       20,850.00
Cost incurred during Month (Add) $    12,870.00 $    77,070.50 $       89,940.50
Total cost to be accounted for $    25,470.00 $    85,320.50 $    110,790.50
cost per Equivalent Unit
total cost to be accounted for 25470 85320.5
Divided by: Equivalent Units of production 3315 2977
Cost per Equivalent Unit $          7.6833 $        28.6599 $          36.3432
Assign costs to units transferred out and units in ending WIP inventory
cost assigned to units transferred out
units completed and transferred out 2795 2795
Cost per Equivalent Unit $          7.6833 $        28.6599
cost assigned to units transferred out $    21,474.71 $    80,104.40 $    101,579.11
cost assigned to units ending work in progress
equivalent units in ending WIP inventory 520 182
Cost per Equivalent Unit $          7.6833 $        28.6599
cost assigned to units ending work in progress $      3,995.29 $      5,216.10 $         9,211.39
Total cost assigned $    110,790.50

Related Solutions

Complete the problems below on variance analysis. Morgan Clay Products manufactures clay molded pottery on an...
Complete the problems below on variance analysis. Morgan Clay Products manufactures clay molded pottery on an assembly line. Its standard costing system uses two cost categories, direct materials and conversion costs. Each product must pass through the Molding Department and the Finishing Department. Direct materials are added at the beginning of the production process. Conversion costs are allocated evenly throughout production. Data for the Assembly Department for August 2017 are: Work in process, beginning inventory: 2600 units Direct materials (100%...
How did the managerial accounting process of standard costing and variance analysis improve the analysis of...
How did the managerial accounting process of standard costing and variance analysis improve the analysis of the operations of the firm? What would be your reaction, as a manager, now that all the β€œnew” information has reached your desk? Direct Labor Variances Direct Materials Variance Overhead Variance
Determining the reasons for variances is an important part of the overall process of variance analysis....
Determining the reasons for variances is an important part of the overall process of variance analysis. Certain causes are commonly attributed to specific variances. Match each reason on the left with the variance(s) it commonly creates. Each numbered item has one or more correct answer(s). Each lettered item may be used once, more than once, or not at all. A change in the quality of materials purchased A new supplier contract Error in the accounting records Change in proportion of...
Complete the following questions. In addition to answering the items below, you must submit an analysis...
Complete the following questions. In addition to answering the items below, you must submit an analysis of the assignment. Analyze the specific outcomes and write an analysis directed toward the management team at Smart Company describing what the numbers mean and how they relate to the business. Submit journal entries in an Excel file and written segments in an MS Word document. For written answers, please make sure your responses are well-written, formatted per CSU-Global Guide to Writing and APA...
Complete the following questions. In addition to answering the items below, you must submit an analysis...
Complete the following questions. In addition to answering the items below, you must submit an analysis of the assignment. Analyze the specific outcomes and write an analysis directed toward the team at Coco Inc. describing what the numbers mean and how they relate to the business. Submit journal entries in an Excel file and written segments in an MS Word document. For written answers, please make sure your responses are well-written, formatted per CSU-Global Guide to Writing and APA and...
Complete the following questions. In addition to answering the items below, you must submit an analysis...
Complete the following questions. In addition to answering the items below, you must submit an analysis of the assignment. Analyze the specific outcomes and analysis directed toward the management team at Smart Company describing what the numbers mean and how they relate to the business. Submit journal entries in an Excel file and written segments in an MS Word document. For written answers, please make sure your responses are well-written, formatted per CSU-Global Guide to Writing and APA and have...
Complete the following questions. In addition to answering the items below, you must submit an analysis...
Complete the following questions. In addition to answering the items below, you must submit an analysis of the assignment. Analyze the specific outcomes and write an analysis directed toward the management team at Smart Company describing what the numbers mean and how they relate to the business. Submit journal entries in an Excel file and written segments in an MS Word document. For written answers, please make sure your responses are well-written, formatted per CSU-Global Guide to Writing and APA...
Complete the following questions. In addition to answering the items below, you must submit an analysis...
Complete the following questions. In addition to answering the items below, you must submit an analysis of the assignment. Analyze the specific outcomes and write an analysis directed toward the management team at Smart Company describing what the numbers mean and how they relate to the business. Submit journal entries in an Excel file and written segments in an MS Word document. For written answers, please make sure your responses are well-written, formatted per CSU-Global Guide to Writing and APA...
Complete the following questions. In addition to answering the items below, you must submit an analysis...
Complete the following questions. In addition to answering the items below, you must submit an analysis of the assignment. Analyze the specific outcomes and write an analysis directed toward the management team at Smart Company describing what the numbers mean and how they relate to the business. Submit journal entries in an Excel file and written segments in an MS Word document. For written answers, please make sure your responses are well-written, formatted per CSU-Global Guide to Writing and APA...
Complete the following questions. In addition to answering the items below, you must submit an analysis...
Complete the following questions. In addition to answering the items below, you must submit an analysis of the assignment. Analyze the specific outcomes and write an analysis directed toward the team at Coco Inc. describing what the numbers mean and how they relate to the business. Submit journal entries in an Excel file and written segments in an MS Word document. For written answers, please make sure your responses are well-written, formatted per CSU-Global Guide to Writing and APA and...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT