Questions
A very wide embankment with height of 3m and the soil unit weight 19 kn/m3 to...

A very wide embankment with height of 3m and the soil unit weight 19 kn/m3 to be constructed. Calculate the normal stress, water pressure and effective stress at two positions: At the middle of clay, the depth = 5 m and the saturated unit weight = 27 kn/m3, and at the middle of sand, the depth = 5 and the saturated unit weight = 21 kn/m3.

For two cases

- Before constructing embankment

-Instantly after constructing the embankment

In: Civil Engineering

describe the methods for determining road-way conditions

describe the methods for determining road-way conditions

In: Civil Engineering

1. describe the methods for determining roadway condition

1. describe the methods for determining roadway condition

In: Civil Engineering

1. describe how the driver and vehicle characteristics influence the geometric design of the highway 2....

1. describe how the driver and vehicle characteristics influence the geometric design of the highway

2. describe design standards for major parts of highway

In: Civil Engineering

The particle has a mass of 0.6 kg and is confined to move along the smooth...

The particle has a mass of 0.6 kg and is confined to move along the smooth horizontal slot due to the rotation of the arm OA. Assume the particle contacts only one side of the slot at any instant. The arm has an angular acceleration of θ¨ = 3 rad/s2 when θ˙ = 2 rad/s at θ = 30∘. (Figure 1) Part A Determine the magnitude of the force of the rod on the particle when θ = 30∘. Express your answer to three significant figures and include the appropriate units. F F = nothing nothing Request Answer Part B Determine the magnitude of the normal force of the slot on the particle when θ = 30∘. Express your answer to three significant figures and include the appropriate units. N N = nothing nothing Request Answer Provide Feedback Figure

In: Civil Engineering

1. how to select suitable soil as the subgrade material 2.describe the different types of islands...

1. how to select suitable soil as the subgrade material

2.describe the different types of islands used in channelizing at grade intersections indicating the principal function of each type

In: Civil Engineering

If you are asked to conduct geologic survey of rocks for potential sites of tunnels in...

If you are asked to conduct geologic survey of rocks for
potential sites of tunnels in Himalayas, summarize the
activities as per geologic investigation.

In: Civil Engineering

geologic investigation of rocks for potential sites of tunnels in Himalayas

geologic investigation of rocks for potential sites of tunnels in Himalayas

In: Civil Engineering

The sales and finance team of a car company is evaluating a new proposed luxury model...

The sales and finance team of a car company is evaluating a new proposed luxury model of its brand that will require an investment of $1Billion in a new machine for car interior decoration. Demand for the company’s car is expected to begin at 100,000 units in year 1, with 10% annual growth thereafter. Production cost will be $40,000 per unit in the first year, and increase by a rateof either 3% or 5% per year as a result of wage increase. Selling price will start at $35,000 and increase by 5% of the production cost. The model will be phased out at the end of year 10. In addition, 0.3%, 2% and 1% of before tax profit per year will be spent on social corporate responsibility, commercial (including promotions) and recalls respectively. Assume taxes will be 30% of yearly profit and that inflation will remain at 0% per year throughout the 10 year of production. Also assume interest rate is expected to be 3% per year in the first 5 years and 5% in the last 5 years.
a. Based on present worth analysis, is the proposed investment profitable if production cost increases by a rate of 3% per year as a result of wage increase? Justify your answer.
b. Based on present worth analysis, is the proposed investment profitable if production cost increases by a rate of 5% per year as a result of wage increase? Justify your answer.

In: Civil Engineering

Activities, predecessors and duration for a School Building Project Activity Description Immediate predecessor Duration (days) A...

Activities, predecessors and duration for a School Building Project

Activity

Description

Immediate predecessor

Duration (days)

A

Clear Site and mobilize labour and equipment

None

5

B

Excavate foundation

A

15

C

Procure materials (sand, cement, chippings etc.)

A

10

D

Pour foundation concrete

B, C

5

E

Mould sandcrete blocks (substructure)

C

5

F

Construct substructure block work

D, E

15

G

Construct superstructure block work

F, H

30

H

Make doors and window frames

I

10

I

Procure and preserve roof timber

C

10

J

Roofing, plastering and painting

G, I

25

K

Fabricate roof trusses

I

15

L

Mould sandcrete blocks (superstructure)

C

10

  1. Draw the network diagram.
  2. What is the critical path of the above project?
  3. Calculate the total and free floats for the activities.

In: Civil Engineering

Find the magnitude and the direction of the resultant force that acts upon the elbow which...

Find the magnitude and the direction of the resultant force that acts upon the elbow which is located on the horizontal plane. Diameter of pipe at section (1) is D1=10 cm, pressure is P1=150000 Pa , the diameter at section (2) is D2= 5 cm and the discharge is Q=0.025 m3/s.(pwater= 1000 kg/m3) Use Formula: ∑f equal to pQv2-pQv1

In: Civil Engineering

Explain the relationship between metallurgical and materials engineering and other engineering disciplines.

Explain the relationship between metallurgical and materials engineering and other engineering disciplines.

In: Civil Engineering

Starting from the point (x0, y0) = (2,3) of the function f (x) = 4x ^...

Starting from the point (x0, y0) = (2,3) of the function f (x) = 4x ^ 2 - 4xy + 2y ^ 2, it is to choose to proceed according to the Steep Descent Method (x2, y2).

In: Civil Engineering

A cantilevered one way slab of effective span 1.5 m has an effective depth of 100...

A cantilevered one way slab of effective span 1.5 m has an effective depth of 100 mm. The slab is provided with 10 mm dia. main reinforcement at 150 mm c/c spacing. Check the slab for deflection if, Ast required is 522.02 mm2. The grade of concrete is M20 and grade of steel is Fe 415.

In: Civil Engineering

Q82: How are the claddings connected with main structure?

Q82: How are the claddings connected with main structure?

In: Civil Engineering