What methods are available to determine flow and flow
in rivers.
Explain with a paragraph.
Describe the three methods you will choose from these methods by
explaining and exemplifying them in detail.
In: Civil Engineering
To meet the tolerance required for a surveying project, it is necessary to use a total station. An obstacle makes it impossible to obtain a direct line of sight. Explain one technique that you would use to establish the line of sight past the obstacle. Use a sketch if necessary (0.5 marks)
In: Civil Engineering
Assume that a two-lane small road crosses a two-lane main road at a right angle making a four-leg intersection where the traffic on the small road controlled by a yield sign. A shopping mall is located 108.24 ft from the centerline of the outside lane of the main road and 12 m from the centerline of the nearest lane of the minor road. Determine the maximum velocity (in km/h) that can be allowed on the small road if the speed limit on the main road is 39.77 mph. Grades of both the roads are leveled.
In: Civil Engineering
Assume you are conducting a parking study in your University. You need to explain the processes/tasks that you will undertake to complete this study. You need to explain how you will do different tasks and how you will present the collected data.
In: Civil Engineering
In: Civil Engineering
You are the Engineer In Charge for a large paving project in New York City. There is some additional paving work being added to the mainline expressway job involving approximately 25,000 metric tons of asphalt. The additional work involves paving nine (9) ramps along the mainline expressway. Due to the Maintenance and Protection of Traffic requirements, the ramps will each be paved on their own night. The total estimated quantity is 400 Metric Tons of Superpave Top Asphalt and 500 Metric Tons of Superpave Binder Asphalt. The Contractor states that it will cost him $90.00 per metric ton to place the asphalt, which is far above his $65.00 per metric ton bid price.
In: Civil Engineering
In: Civil Engineering
During and after the commissioning and turn-over process, the design and construction team need to provide the owner with many important documents for the operation of the building. These include all of the following, except:
A list of things that the contractor secretly left out of the building to save costs. |
||
Operations and maintenance manuals for installed equipment |
||
Final construction drawings, typically called "As Built" drawings. These incorporate any minor changes made during construction. |
||
Design calculations for building systems. |
||
Warranty, test-and-balance, and inspection documents. |
||
Building Information Modeling (BIM) data, if included in the contract. |
||
Samples and inventories of spare parts and materials used in the construction, to facilitate repairs. |
In: Civil Engineering
In: Civil Engineering
In: Civil Engineering
In: Civil Engineering
a. A symmetrical rectangle box section prestressed concrete beam of external width of 300 mm and external depth of 600 mm with a uniform thickness of 40 mm is prestressed with 7 numbers straight steel wires of 7 mm diameter located at a distance of 15 mm from the bottom of the soffit and 5 number of 5mm diameter of the steel wires located at the 575 mm from the bottom of the beam . The wires were initially tensioned on the prestressing bed with an initial prestress of 1500 N/mm2 . The beam is subjected to point load of 48 + 0.2 (54) kN at the center of the beam and a uniformly distributed load of 20 kN/m entire length of the beam with a length of 10 m. Calculate the resultant stresses at the end and mid span section with neat stress distribution diagram. Assume the density of the concrete is 24 kN/m3 . Use BS8110 code
b. In the above problem, how to control the resultant stresses such that they do not exceed 25 N/mm2 at mid span section.
In: Civil Engineering
a. An unsymmetrical I section prestressed concrete beam of top flange (350 X 40 mm) in size, bottom flange of (200 X 40 mm), 30mm thickness of web and overall depth of 400 mm is prestressed with 19 numbers straight steel wires of 7 mm diameter located at a distance of 15 mm from the bottom of the soffit and 9 numbers of straight steel wires of 6 mm diameter located at a distance of 15 mm from the top of the beam. The wires were initially tensioned on the prestressing bed with an initial prestress of 1.2 + 0.01 (54) GPa. The length of the beam is 10 m. Calculate the total percentage loss of stress in the wires at top and bottom. Assume the beam is post tensioned beam and all the wires stressed simultaneously by using the following data: Relaxation of steel stress= 4.5% of initial stress -6 Shrinkage strain in concrete for post tensioning = 200 x 10 Creep Coefficient ΙΈ=1.6 Friction coefficient for wave effect=0.0015 + 0.001 (54) per meter Slip at anchorage= 1.5 mm Modulus of elasticity for steel = 210 GPa Modulus of elasticity for concrete= 35 GPa
b. What are the measures that are suggested to be taken to reduce the losses in prestressed concrete members for the above problem?
In: Civil Engineering
prestressed road bridge of span 16.74 m consists of
a
concrete slab of 420 mm thick with parallel post-tensioned cables,
in each of which the force
at transfer is 440 kN. If the bridge is required to support a
uniformly distributed applied load
of 43.37kN/m2
, with tensile stress in the concrete not exceeding
0.85 N/mm2
at any time. Calculate the maximum horizontal spacing of the
cables, their
distance from the soffit of the slab at mid-span and their lowest
possible position at
supports. Assume 15 % loss of prestress after transfer. Also
calculate the number of steel
wires used in each cable with the permissible stress of 1200
N/mm2
for 7 mm diameter steel
wire. Assume the density of the concrete is 24 kN/m3
.
In: Civil Engineering
. A symmetrical rectangle box section prestressed
concrete beam of external width of 300
mm and external depth of 600 mm with a uniform thickness of 40 mm
is prestressed with 7
numbers straight steel wires of 7 mm diameter located at a distance
of 15 mm from the bottom
of the soffit and 5 number of 5mm diameter of the steel wires
located at the 575 mm from the
bottom of the beam . The wires were initially tensioned on the
prestressing bed with an initial
prestress of 1500 N/mm2
. The beam is subjected to point load of 55.4 kN at the center of
the beam and a uniformly distributed load of 20 kN/m entire
length
of the beam with a length of 10 m. Calculate the resultant stresses
at the end and mid span
section with neat stress distribution diagram. Assume the density
of the concrete is 24
kN/m3
.
b. In the above problem, how to control the resultant
stresses such that they do not exceed
25 N/mm2 at mid span section.
In: Civil Engineering