Question

In: Civil Engineering

During and after the commissioning and turn-over process, the design and construction team need to provide...

  1. During and after the commissioning and turn-over process, the design and construction team need to provide the owner with many important documents for the operation of the building. These include all of the following, except:

    A list of things that the contractor secretly left out of the building to save costs.

    Operations and maintenance manuals for installed equipment

    Final construction drawings, typically called "As Built" drawings. These incorporate any minor changes made during construction.

    Design calculations for building systems.

    Warranty, test-and-balance, and inspection documents.

    Building Information Modeling (BIM) data, if included in the contract.

    Samples and inventories of spare parts and materials used in the construction, to facilitate repairs.

Solutions

Expert Solution

Explanation:

Project commissioning is the process of assuring that all systems and components of a building or industrial plant are designed, installed, tested, operated, and maintained according to the operational requirements of the owner or final client.

Construction team submit documents regarding equipment cut-sheets, schematics, in-progress record drawings, manufacturers installation-operation-maintenance manuals, startup reports, etc. to assist the Commissioning Authority in execution of the Construction process. Design team and Construction team also Furnish a copy of all construction documents, addenda, change orders, Requests for Information (RFIs), approved submittals, shop drawings, and IOMs, related to commissioned systems and equipment to the Commissioning Authority.

They also Submit test results for tests required by the Contract Documents, including (but not limited to) duct leakage tests, hydronic system pressure tests, plumbing system disinfection certification, generator tests, smoke evacuation system tests, fire pump tests, fire alarm tests, etc. as applicable to the commissioning scope.

The Commissioning Authority will not authorize or approve construction cost amendments, changes to the construction schedule, or changes to the contract documents.

Hence, construction and design team wil submit,

Operations and maintenance manuals for installed equipment.

Final construction drawings, typically called "As Built" drawings. These incorporate any minor changes made during construction.

Design calculations for building systems.

Warranty, test-and-balance, and inspection documents.

Building Information Modeling (BIM) data, if included in the contract.

Samples and inventories of spare parts and materials used in the construction, to facilitate repairs.

But they will not submit the list of things that the contractor secretly left out of the building to save costs.

Note: For any queries please ask in comment.


Related Solutions

Why concrete mix proportions need to be designed? After completing the design mix process, explain what...
Why concrete mix proportions need to be designed? After completing the design mix process, explain what are the next steps to be done? If the same concrete mix proportions calculated in (a) is to be used for application near marine environment or in heavy industrial area, suggest with justification the possible modification that can be done.         
Crossland Construction’s design/build department allows their clients (owners) to select the design and construction team based...
Crossland Construction’s design/build department allows their clients (owners) to select the design and construction team based on their combined experience and track-record. Design/build firms typically have a cash flow problem since they tend to be paid in lump sums when projects are completed or hit milestones. However, their expenses, such as payroll, must be paid regularly. So, such firms need bank lines of credit to finance their initial costs, but in the past year, lines of credit were difficult to...
Crossland Construction’s design/build department allows their clients (owners) to select the design and construction team based...
Crossland Construction’s design/build department allows their clients (owners) to select the design and construction team based on their combined experience and track-record. Design/build firms typically have a cash flow problem since they tend to be paid in lump sums when projects are completed or hit milestones. However, their expenses, such as payroll, must be paid regularly. So, such firms need bank lines of credit to finance their initial costs, but in the past year, lines of credit were difficult to...
The process design team at a manufacturer has broken an assembly process into eight basic steps,...
The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. They work a 7 hour day and want to produce at a rate of 360 units per day. What should their cycle time be? Task Time (sec) Predecessor A 45 -- B 50 A C 40 A D 55 B, C E 40 D F 65 D G 25 E H 35...
The economy has expanded rapidly over the last two years. Provide an explanation for this turn...
The economy has expanded rapidly over the last two years. Provide an explanation for this turn of events and show how it is an INUS explanation.
COURSE : IT System Integration “The software design/development team and test engineers need to develop a...
COURSE : IT System Integration “The software design/development team and test engineers need to develop a strategy for planning, design, execution, data collection, and test evaluation”. Discuss this statement. note: NEED A UNIQUE ANSWER AND NO HANDWRITING PLEASE.. THANK YOU
Provide an executive summary to your team on how to credential providers. You will need to...
Provide an executive summary to your team on how to credential providers. You will need to consider the following: Type of provider being credentialed Steps they will go thru to be credentialed Educational background needed Does this provider have an NPI number? State the provider will work in Is there a standard application? Is an onsite visit needed; why or why not Who gets credentialed (list at least 5 specialties) Are all facilities credentialed?
There are several steps need to be considered to fulfill the structural design process. Describe the...
There are several steps need to be considered to fulfill the structural design process. Describe the design process which involves building form and structural arrangement.
What parties to the building design and construction process—in addition to architects, mechanical engineers, and electrical...
What parties to the building design and construction process—in addition to architects, mechanical engineers, and electrical engineers—will play a substantive role in establishing the success of fire protection systems? For each party that is identified, briefly outline the role they can/should play.
Whole Life Costing (WLC) is an evaluation process that needs to be undertaking during the design...
Whole Life Costing (WLC) is an evaluation process that needs to be undertaking during the design phase. However implementation of (WLC) often faces two major problems. Explain these two problems and how they have been addressed. Please don’t write for hand because i can’t read your handstyle and thank you :)
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT