Question

In: Finance

1) What are the main differences between the NPV method and the IRR? 2) When does...

1) What are the main differences between the NPV method and the IRR?

2) When does IRR give you the wrong answer?

3) How does the MIRR avoid the IRR shortcomings?

Please answer all sections with 5-7 sentences for each question.

Solutions

Expert Solution

1) NPV method refers to Net present value of cash inflows and outflows, it is calculated by reducing the present value of cash outflow from present value of cash inflow at the cost of capital of the project. A positive NPV means the project can be undertaken as inflows are more than outflows in terms of present value. IRR is the internal rate of return it is the rate where the Net Present value of a project is zero. It is the base rate, any return above IRR is considered to be profitable for the project.

2) In case where there is single outflow at the start of the year, there would be one single IRR but when the project has multiple cash outflows at different stages than the project will not have one single IRR there would be multiple IRR for a project, In that case we would not be able to decision whether to accept or reject the project based on the IRR

3) Where a project has multiple outflows IRR would not give us correct decision. Hence in that case project manager can use the MIRR method for decision making which would overcome the shortcomings of multiple IRR.


Related Solutions

1)the major differences between the NPV and IRR method for capital budgeting analysis. Also, explain the...
1)the major differences between the NPV and IRR method for capital budgeting analysis. Also, explain the pros and cons of the IRR technique in the capital budgeting analysis. 2)What should be used as an appropriate discount rate for the project analysis of a division whose risk level is different from that of the company as a whole. Explain why.
1. Describe the relationship between the IRR and the discount rate when NPV=0. 2. Given the...
1. Describe the relationship between the IRR and the discount rate when NPV=0. 2. Given the following information, should a company invest in a given capital? Initial Investment $675,000 Annual Cash Inflow $158,000 Salvage Value $80,000 Years of life of the equipment and project: 6 Minimum required rate of return: 10% Depreciation $99,167 Payback Period in Years 4.3 Accounting Rate of Return 8.72% NPV $27,553.5 IRR 11.32%
a) Is it possible for conflicts to exist between the NPV and the IRR when independent...
a) Is it possible for conflicts to exist between the NPV and the IRR when independent projects are being evaluated? Explain your answer. (150 words) b) If the payback was the only method a firm used to accept or reject projects, what payback should it choose as the cutoff point, that is, reject projects if their paybacks are not below the chosen cutoff? Is your selected cutoff based on some economic criteria, or is it more or less arbitrary? Are...
​(1) In​ general, if NPV​ = 0, then what IRR would be equal​ to? ​(2) In​...
​(1) In​ general, if NPV​ = 0, then what IRR would be equal​ to? ​(2) In​ general, if NPV​ > 0, then what PI​ (Profitability Index) would be equal​ to?
What are main differences between the Finite Difference Method and Finite Elements Method? How are the...
What are main differences between the Finite Difference Method and Finite Elements Method? How are the boundary and interior values of the finite element solution obtained?
1. What in an antigen? 2. What are the main differences between innate and adaptive immunity?...
1. What in an antigen? 2. What are the main differences between innate and adaptive immunity? 3. What are the three lines of defense? State their function and give examples of each one. 4. What is humoral immunity? Which cells are involved in humoral immunity? 5. What is an antibody? Which cell produces it? 6. What is cell-mediated immunity?
1. What is the reinvestment rate assumption and how does it affect the NPV vs. IRR...
1. What is the reinvestment rate assumption and how does it affect the NPV vs. IRR conflicts? 2. What is the rationale behind the MIRR method? 3. ​​​​​​​Would the MIRR change if the required rate of return changed?
What is the correction that is made to the IRR method when using the Modified IRR...
What is the correction that is made to the IRR method when using the Modified IRR method?
Question 1: What does the following code print to the console when the main method is...
Question 1: What does the following code print to the console when the main method is run? public static void referenceMystery(int x, int[] a) { x = 3; a[0] = 4; System.out.println(x+" "+a[0]); } public static void main(String[] args) { int x = 1, y = 2; int[] a = new int[1]; int[] b = new int[1]; referenceMystery(y, b); } 1. x a[0] 2. 1 3. 2 0 4. 3 4 Question 2: What does the following code print out...
Explain FIVE conflicts between NPV and IRR
Explain FIVE conflicts between NPV and IRR
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT