Question

In: Finance

The NPV method and the IRR method will always produce the same decision when a. All...

The NPV method and the IRR method will always produce the same decision when

a.

All of the answers are correct.

b.

mutually exclusive projects are evaluated.

c.

a single project is evaluated.

d.

a limited number of projects must be selected from a large number of opportunities.

Solutions

Expert Solution

The correct answer to the question is option (c). NPV method and IRR method will always produce the same decision when a single project is evaluated.

Now, let's look at the options one by one.

Option (b)
Two projects are said to be mutually exclusive if a firm can undertake only one of them. In the case of mutually exclusive projects, the NPV method and the IRR method could produce different decisions. For instance, consider the following two projects with a discount rate of say 10%:

Cash flow in Year 0 Cash flow in Year 1 NPV IRR
Project A (10,000) 30,000      17,273 200%
Project B (25,000) 50,000      20,455 100%

While project A is better if the IRR of the projects are considered, project B is better if the NPV is considered. The decisions are not the same. So option (b) is wrong.

Option (c)
If the above mentioned projects are evaluated individually, both the NPV method and the IRR method produce the same decision (to accept) for each project (at a discount rate of 10%).

Option (d)
For option (d) too, the rationale applied for option (b) can be applied. If there are a number of projects to choose from and both NPV and IRR methods are applied to the projects, the NPV method and the IRR method might produce different decisions. So option (d) is wrong.

Since, option (c) is the only correct answer, option (a) is wrong.


Related Solutions

Under what circumstances will the IRR and NPV rules lead to the same decision (accept/reject)? When...
Under what circumstances will the IRR and NPV rules lead to the same decision (accept/reject)? When might they conflict? (It is important to explain your answers with details or demonstrate your understanding by applying examples.) please this answer should not be from text book.
14. (Toolkit – Decision Rules – PBAK, IRR, NPV) Calculating NPV & IRR: Your next project...
14. (Toolkit – Decision Rules – PBAK, IRR, NPV) Calculating NPV & IRR: Your next project provides an annual cash flow of $15,400 for nine years and costs $67,000 today. Is this a good project at 8% required return? How about 20%? Question 14 options: Yes, Yes Yes, No No, Yes No, No
When NPV and IRR rules result in a conflicting decision regarding acceptance of a project managers...
When NPV and IRR rules result in a conflicting decision regarding acceptance of a project managers could use the MIRR. It assumes reinvestment of projects' cash flows at the WACC, so it produces results consistent with NPV method. Let's try to find the MIRR for the project with the following cash flows: Initial cost of -800 at time zero, CF1 = 400, CF 2 = 570, CF3 = -130. Here we have two negative cash flows and two positive cash...
NPV always gives you correct decision for accepting the project. If NPV always gives us the...
NPV always gives you correct decision for accepting the project. If NPV always gives us the correct decision why should we pay attention to profitability ratios or IRR? Provide an example where one of these other ratios might change your decision on a project.
1) What are the main differences between the NPV method and the IRR? 2) When does...
1) What are the main differences between the NPV method and the IRR? 2) When does IRR give you the wrong answer? 3) How does the MIRR avoid the IRR shortcomings? Please answer all sections with 5-7 sentences for each question.
NPV & IRR: Find the NPV (assume 8% just to calculate NPV initially) & IRR of...
NPV & IRR: Find the NPV (assume 8% just to calculate NPV initially) & IRR of these projects. When would you choose one over the other (i.e. what is the crossover rate)? Draw the NPV profile using 11 intervals of interest rates ranging from (and including) 0% to 100%. Place all data, ratios, calculations, findings, etc. in the first Excel sheet with references to the information in other sheets. Time A CF B CF 0 -10000 -10000 1 12000 9000...
Describe the decision rules for NPV and IRR. How do changes in the WACC affect the...
Describe the decision rules for NPV and IRR. How do changes in the WACC affect the outcome of these decisions? (There are 4 parts to this question. 1-2 sentences each) NPV decision rule: Impact of changes in WACC on NPV rule: IRR decision rule: Impact of changes in WACC on IRR rule:
a) Is it possible for conflicts to exist between the NPV and the IRR when independent...
a) Is it possible for conflicts to exist between the NPV and the IRR when independent projects are being evaluated? Explain your answer. (150 words) b) If the payback was the only method a firm used to accept or reject projects, what payback should it choose as the cutoff point, that is, reject projects if their paybacks are not below the chosen cutoff? Is your selected cutoff based on some economic criteria, or is it more or less arbitrary? Are...
What is the correction that is made to the IRR method when using the Modified IRR...
What is the correction that is made to the IRR method when using the Modified IRR method?
What are the pros and cons of the various capital budgeting decision methods (NPV, IRR, MIRR,...
What are the pros and cons of the various capital budgeting decision methods (NPV, IRR, MIRR, PB, DPB)? If you had to pick one method to use for all project valuation situations, which one would you pick, and why? Please explain your answer! I am trying to understand the concept.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT