Question

In: Finance

​(1) In​ general, if NPV​ = 0, then what IRR would be equal​ to? ​(2) In​...

​(1) In​ general, if NPV​ = 0, then what IRR would be equal​ to?

​(2) In​ general, if NPV​ > 0, then what PI​ (Profitability Index) would be equal​ to?

Solutions

Expert Solution

1. If NPV = 0, Then the IRR would be equal to the Weighted average cost of capital (WACC) Which is also termed as Discount rate.

The Net present value is the Present worth of the project, it is calculated by discounting the cash flows of the project which is the Wacc and then subtracted from the intiial investment of the project, and the internal rate of return is the return at which the present value of cash flows if discounted comes equal to the initial investment, so when the NPV = 0 then the IRR will be equal to the WACC.

2. If NPV >0 , then the PI would be Greater than

If the NPV is more than 1, then it means that the present value of cash flows is greater than the initial investment and the Profitbaility index is claculated by dividing the sum of present value of cash flows by the initial invesment, so of the Net present value is more than 1, the Profitbality index would result in Greater than 1.0.


Related Solutions

1(a). When NPV=0, then: Select one: a. IRR less than 0 b. IRR=required return c. IRR...
1(a). When NPV=0, then: Select one: a. IRR less than 0 b. IRR=required return c. IRR greater than 0 d. IRR greater than required return e. IRR=0 1(b). The relationship between NPV of a project and the required rate of return is: Select one: a. positive b. random c. negative d. determined by the relationship of NPV to IRR e. none of the answers is correct
1. Describe the relationship between the IRR and the discount rate when NPV=0. 2. Given the...
1. Describe the relationship between the IRR and the discount rate when NPV=0. 2. Given the following information, should a company invest in a given capital? Initial Investment $675,000 Annual Cash Inflow $158,000 Salvage Value $80,000 Years of life of the equipment and project: 6 Minimum required rate of return: 10% Depreciation $99,167 Payback Period in Years 4.3 Accounting Rate of Return 8.72% NPV $27,553.5 IRR 11.32%
If you earn the WACC on a project, (IRR = WACC) or NPV = 0, what...
If you earn the WACC on a project, (IRR = WACC) or NPV = 0, what have you accomplished for your shareholders? 1A. A semiannual bond pays a 4.5 % coupon for the next 27 years. If investors want a 7.3% return, what are they willing to pay for the bond?
If the IRR for a project is 20%, then the project's NPV would be:
If the IRR for a project is 20%, then the project's NPV would be:
1) What are the main differences between the NPV method and the IRR? 2) When does...
1) What are the main differences between the NPV method and the IRR? 2) When does IRR give you the wrong answer? 3) How does the MIRR avoid the IRR shortcomings? Please answer all sections with 5-7 sentences for each question.
NPV & IRR: Find the NPV (assume 8% just to calculate NPV initially) & IRR of...
NPV & IRR: Find the NPV (assume 8% just to calculate NPV initially) & IRR of these projects. When would you choose one over the other (i.e. what is the crossover rate)? Draw the NPV profile using 11 intervals of interest rates ranging from (and including) 0% to 100%. Place all data, ratios, calculations, findings, etc. in the first Excel sheet with references to the information in other sheets. Time A CF B CF 0 -10000 -10000 1 12000 9000...
Period   0 1 2 3 4 5 6 7 8 9 10 11 PBP NPV IRR...
Period   0 1 2 3 4 5 6 7 8 9 10 11 PBP NPV IRR Project A $                       (1,000,000) $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 400,000 Project B $                       (1,000,000) $ 500,000 $ 500,000 $ 500,000 Project C $                             (80,000) $      1,040 $      9,456 $    11,405 $    18,567 $    47,453 $      6,394 $    45,727 $    51,933 $    85,625 Project D $                           (400,000) $      4,161...
Period   0 1 2 3 4 5 6 7 8 9 10 11 PBP NPV IRR...
Period   0 1 2 3 4 5 6 7 8 9 10 11 PBP NPV IRR Project A $                       (1,000,000) $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 400,000 Project B $                       (1,000,000) $ 500,000 $ 500,000 $ 500,000 Project C $                             (80,000) $      1,040 $      9,456 $    11,405 $    18,567 $    47,453 $      6,394 $    45,727 $    51,933 $    85,625 Project D $                           (400,000) $      4,161...
In an essay, discuss the advantages and disadvantages of using (1) NPV analysis and (2) IRR...
In an essay, discuss the advantages and disadvantages of using (1) NPV analysis and (2) IRR analysis to evaluate projects.
What is the difference between NPV and IRR? Which one would you choose for evaluating a...
What is the difference between NPV and IRR? Which one would you choose for evaluating a potential investment and why? Be sure to support your reasoning with evidence
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT