Question

In: Accounting

The budgeted and actual results for June 2020 are as follows: Budget Actual Production (units) 150,000...

The budgeted and actual results for June 2020 are as follows:

Budget

Actual

Production (units)

150,000

150,500

Direct material A

300,000m2

£675,000

316,050m2

£695,310

Direct material B

900,000

£18,000

1,053,500

£21,070

Direct labour

37,500 hours

£318,750

37,625 hours

£323,575

Fixed overheads

£287,500

£300,623.75

You are required to:

  1. Calculate all possible variances from the information provided above for June and use the variances to reconcile the actual cost of production with the standard cost of production.
  1. Evaluate the variances calculated in terms of what might have caused them and what, if anything, could be put done to bring them back under control.

Solutions

Expert Solution

a. Calculation of all possible variances from the information provided for June:

Budgeted cost data for production of 150,000 units

Budgeted quantity or hours Budgeted Price or Rate Budgeted Cost
Direct materials A 300,000 m2 £1.25 £375,000
Direct materials B 900,000 £0.02 £18,000
Direct labor 37,500 hours £8.50 £318,750
Budgeted fixed overhead £287,500
Budgeted cost of 150,000 units £999,250

Budgeted direct material A price per unit = £375,000 / 300,000 = £1.25

Budgeted direct material B price per unit = £18,000 / 900,000 = £0.02

Budgeted direct labor rate per unit = £318,750 / 37,500 = £8.50

Standard cost data allowed for production of 150,500 units will be:

Standard quantity or hours Standard Price or Rate Standard Cost
Direct materials A 301,000 m2 (300,000 / 150,000) x 150,500 £1.25 £376,250
Direct materials B 903,000 (900,000 / 150,000) x 150,500 £0.02 £18,060
Direct labor 37,625 hours (37,500 / 150,000) x 150,500 £8.50 £319,812.50
Standard fixed overhead [(£287,500 / 150,000) x 150,500] £288,458.33
Standard cost of 150,500 units £1,002,580.83

Actual cost data for production of 150,500 units is:

Actual quantity or hours Actual Price or Rate Actual Cost
Direct materials A 316,050 m2 £2.20 £695,310
Direct materials B 1,053,500 £0.02 £21,070
Direct labor 37,625 hours £8.60 £323,575
Actual fixed overhead £300,623.75
Actual cost of 150,500 units £1,340,578.75

Actual direct material A price per unit = £695,310 / 316,050 = £2.20

Actual direct material B price per unit = £21,070 / 1,053,500 = £0.02

Actual direct labor rate per unit = £323,575 / 37,625 = £8.60

1. Direct material Price variance = (Standard price - Actual price) x Actual Quantity of material

Direct material Price variance of  Direct materials A = (£1.25 - £2.20) x 316,050 = £300,247.50 (U) Unfavorable

Direct material Price variance of  Direct materials B = No effect (since both the standard price and actual price of direct material B is same)

2. Direct material quantity variances = (Standard quantity - Actual quantity) x Standard price per material

Direct material quantity variance of  Direct materials A = (301,000 - 316,050) x £1.25 = £18,812.50 (U) Unfavorable

Direct material quantity variance of  Direct materials B = (903,000 - 1,053,500) x £0.02 = £3,010 (U) Unfavorable

3. Direct labor rate vairance = (Standard rate - Actual rate) x Actual labour hours = (£8.50 - £8.60) x 37,625 = £3,762.50 (U) Unfavorable

4. Direct labor efficiency variance = (Standard labour hours - Actual labour hours) * Standard rate per labour hour

= No effect (since both the standard labor hours and the actual labor hurs are same).

5. Fixed overhead spending varaince = Budgeted fixed overhead - Actual fixed overhead

= £287,500 - £300,623.75 = £13,123.75 (U) Unfavorable

6. Fixed overhead volume variance = Standard fixed overhead - Budgeted fixed overhead

= £288,458.33 - £287,500 = £958.33 (F) Favorable

Reconciliation statement showing the actual cost of production with the standard cost of production:

Item £ £
Standard cost of 150,500 units £1,002,580.83
Adjustments:
Direct materials Price variances:
Direct materials A £300,247.50
Direct materials B £0 £300,247.50
Direct materials Quantity variances:
Direct materials A £18,812.50
Direct materials B £3,010 £21,822.50
Direct labor rate variance £3,762.50
Direct labor efficiency variance £0
Fixed overhead spending varaince £13,123.75
Fixed overhead volume variance -£958.33
Actual cost of 150,500 units 13,40,578.75

b. Actions to be taken to bring them back under control are:

Direct material price variance for direct materials A is unfavorable since the actual material price is higher than the standard material price, the company should instruct the purchase manager to purchase the material at the budgeted price to bring the price under control and thus it will helps to control the cost.

Direct material quantity variance for direct materials A is unfavorable since the actual material used is higher than the standard material allowed. The Company's production manager should focus on the usage of the material to bring down the usage of material and thus the company can reduce the costs.

Direct material quantity variance for direct materials B is unfavorable since the actual material used is higher than the standard material allowed. The Company's production manager should focus on the usage of the material to bring down the usage of material and thus the company can reduce the costs.

Direct labor rate variance is unfavorable since the hiring manager has hired the labor above the standard labor rate per labor hour. The Company's hiring manager should bring the labor at the estimated rate to reduce the labor cost.

Direct labor efficiency variance has no effect since the standard labor hours allowed and actual labor hours worked are same.

Fixed overhead spending variance is unfavorable since the company has spent more fixed expenses during the period than budgeted. The company should reduce the fixed cost.


Related Solutions

The following information is for X Company for 2017: Master    Actual     Budget    Results    Production 10,900 units...
The following information is for X Company for 2017: Master    Actual     Budget    Results    Production 10,900 units 12,000 units Total variable costs $99,190    $108,226    Total fixed costs $197,300    $201,669    1. What was the 2017 master (static) budget for total costs? 2. What was the 2017 flexible budget for total costs?
The following data are given for Harry Company: Budgeted production 1,056 units Actual production   900 units...
The following data are given for Harry Company: Budgeted production 1,056 units Actual production   900 units Materials:     Standard price per ounce $1.758     Standard ounces per completed unit 11     Actual ounces purchased and used in production 10,197     Actual price paid for materials $20,904 Labor:     Standard hourly labor rate $14.09 per hour     Standard hours allowed per completed unit 4.4     Actual labor hours worked 4,635     Actual total labor costs $75,319 Overhead:     Actual and budgeted fixed overhead $1,054,000     Standard variable overhead rate $24.00 per...
The following data are given for Stringer Company: Budgeted production 959 units Actual production   1,063 units...
The following data are given for Stringer Company: Budgeted production 959 units Actual production   1,063 units Materials:     Standard price per ounce $1.9     Standard ounces per completed unit 10     Actual ounces purchased and used in production 10,949     Actual price paid for materials $22,445 Labor:     Standard hourly labor rate $14.96 per hour     Standard hours allowed per completed unit 4.6     Actual labor hours worked 5,474.45     Actual total labor costs $83,485 Overhead:     Actual and budgeted fixed overhead $1,186,000     Standard variable overhead rate $27.00 per...
The following data is given for the Stringer Company: Budgeted production 954 units Actual production 1,030...
The following data is given for the Stringer Company: Budgeted production 954 units Actual production 1,030 units Materials: Standard price per ounce $1.92 Standard ounces per completed unit 12 Actual ounces purchased and used in production 12,731 Actual price paid for materials $26,099 Labor: Standard hourly labor rate $14.49 per hour Standard hours allowed per completed unit 4.8 Actual labor hours worked 5,304.5 Actual total labor costs $80,894 Overhead: Actual and budgeted fixed overhead $1,031,000 Standard variable overhead rate $25.00...
Pacific company provides the following information about its budgeted and actual results for June 2019. Although...
Pacific company provides the following information about its budgeted and actual results for June 2019. Although the expected June volume was 25, 000 units produced and sold, the company actually produced and sold 27, 000 units as detailed here: Budgeted (25, 000 units) Actual (27, 000 units) Selling price $5.00 per unit $5.23 per unit Variable costs (per unit): Direct materials 1.24 per unit 1.12 per unit Direct labour 1.50 per unit 1.40 per unit Manufacturing supplies* 0.25 per unit...
16.The following data is given for the Stringer Company: Budgeted production 906 units Actual production   1,059...
16.The following data is given for the Stringer Company: Budgeted production 906 units Actual production   1,059 units Materials:     Standard price per ounce $1.84     Standard ounces per completed unit 10     Actual ounces purchased and used in production 10,908     Actual price paid for materials $22,361 Labor:     Standard hourly labor rate $14.81 per hour     Standard hours allowed per completed unit 4.1     Actual labor hours worked 5,453.85     Actual total labor costs $83,171 Overhead:     Actual and budgeted fixed overhead $1,002,000     Standard variable overhead rate $25.00...
A budget variance occurs when the actual results of your financial activity differ from your budgeted...
A budget variance occurs when the actual results of your financial activity differ from your budgeted projections. Please identify what might be causing you budget variances at the moment. What are some microeconomic factors that could be causing this outcome? What are some macroeconomic factors that could be sources of the variance? What might you change in your financial behaviour, budget, or goals to your improve outcomes?
Prepare a flexible income statement budget for three production levels of Crow Co. Production: 150,000 units;...
Prepare a flexible income statement budget for three production levels of Crow Co. Production: 150,000 units; 180,000 units, 200,000 units. Price per unit: $120 Costs: Direct Material: 10% of total revenues, Direct Labor: 15% of total revenues, Factory Overhead: 5% of total revenues. Fixed Costs = $78,000 Expenses: Administrative Expenses: 15% of Gross Profit, Selling Expenses: 10% of Gross Profit Crow Co. Flexible Income Statement, Dec/31/20XY Production Level 150,000 180,000 200,000 Revenues
The following are budgeted data: Sales (units )Production (units) April 15,000 18,000 May 20,000 19,000 June...
The following are budgeted data: Sales (units )Production (units) April 15,000 18,000 May 20,000 19,000 June 18,000 16,000 Two pounds of material are required for each finished unit. The inventory of materials at the end of each month should equal 20% of the following month's production needs. Purchases of raw materials for May should be: 36,800 pounds 39,200 pounds 52,000 pounds 38,000 pounds
Using the following budgeted information for production of 9,000 and 14,000 units, prepare a flexible budget...
Using the following budgeted information for production of 9,000 and 14,000 units, prepare a flexible budget for 19,000 units. Lens Junction sells lenses for $45 each and is estimating sales of 16,000 units in January and 19,000 in February. Each lens consists of 2 pounds of silicon costing $2.50 per pound, 3 oz of solution costing $3 per ounce, and 30 minutes of direct labor at a labor rate of $20 per hour. Desired inventory levels are: Jan. 31 Feb....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT