Question

In: Finance

You just finished a capital budgeting investment analysis on a ​$209 million project. The​ project's life...

You just finished a capital budgeting investment analysis on a ​$209 million project. The​ project's life is 10 years and it will generate equal annual​ after-tax cash operating cash flows of ​$37.61 million. You assumed a ​$68 million salvage​ value, but the​ project's adjusted tax basis at termination will be ​$93 million. The project would have no effect on net working capital. With a 27​% marginal tax​ rate, the resulting NPV is ​$80.93 million. What cost of capital did you use for the​ analysis? ​ (Percent with​ 1decimal)

Solutions

Expert Solution

IF YOU NEED SOLUTION WITH FINANCIAL CALCULATOR, WILL DO THAT ALSO. THIS IS EASY QUESTION, ONLY TRICK IS THAT NPV = 0 WHEN WE ADD NPV TO COST, THEN FIND IRR


Related Solutions

Exercise Example - Capital Budgeting Project Analysis - Chapter 5 As director of capital budgeting, you...
Exercise Example - Capital Budgeting Project Analysis - Chapter 5 As director of capital budgeting, you are reviewing three potential investment projects with the following cost and cash flow projections.   Cash Flow Project A Project B Project C Investment Cost ($500,000) ($375,000) ($475,000) Year One Cash Flow $200,000 $175,000 $250,000 Year Two Cash Flow $180,000 $50,000 $200,000 Year Three Cash Flow $100,000 $50,000 $75,000 Year Four Cash Flow $80,000 $50,000 $30,000 Year Five Cash Flow $140,000 $300,000 $30,000 Calculate the...
You just finished analyzing a capital investment that will produce equal annual cash flows of $25...
You just finished analyzing a capital investment that will produce equal annual cash flows of $25 million of over its 5-year life. The resulting NPV is $4 million and the profitability index is 1.05. You assumed a $30 million salvage value, $20 million above its adjusted tax basis, and a 35% marginal tax rate. What discount rate did you use to value this investment? please show steps, no excel.
You just finished analyzing a capital investment that will produce equal annual cash flows of $25...
You just finished analyzing a capital investment that will produce equal annual cash flows of $25 million of over its 5-year life. The resulting NPV is $8 million and the IRR is 15.13%. You assumed a $30 million salvage value, $20 million above its adjusted tax basis, and a 35% marginal tax rate. What discount rate did you use to value this investment? please show the answer step by step and do not use excel
You are analyzing a project with 5-year life. The project requires a capital investment of $10000...
You are analyzing a project with 5-year life. The project requires a capital investment of $10000 now, and it will generate uniform annual revenue of $6000 at the end of each year. Further, the project will have a salvage value of $2500 at the end of the fifth year and it will require $3000 each year for the operation. What is the net value of the project using year 1 as the basis, considering a 10% annual interest rate._________(round your...
Explain the project evaluation project in relation to capital budgeting and the purpose of investment projects....
Explain the project evaluation project in relation to capital budgeting and the purpose of investment projects. Purposes were categorized into 6 categories: replacement, renewal, expansion, cost-reduction, conforming, and all other projects.
You just finished calculating the NPV of project A and found it to be $49,242. A...
You just finished calculating the NPV of project A and found it to be $49,242. A concurrent project, which will use the same resources as project A is now before you as well. This is project B, which will require a $2M investment in an asset that will have a $1M salvage value at the end of the project. A total of $170,000 was invested in the consulting and research leading to the marketability of the product. Project B will...
You just finished calculating the NPV of project A and found it to be $49,242. A...
You just finished calculating the NPV of project A and found it to be $49,242. A concurrent project, which will use the same resources as project A is now before you as well. This is project B, which will require a $2M investment in an asset that will have a $1M salvage value at the end of the project. A total of $170,000 was invested in the consulting and research leading to the marketability of the product. Project B will...
You just finished calculating the NPV of project A and found it to be $49,242. A...
You just finished calculating the NPV of project A and found it to be $49,242. A concurrent project, which will use the same resources as project A is now before you as well. This is project B, which will require a $2M investment in an asset that will have a $1M salvage value at the end of the project. A total of $170,000 was invested in the consulting and research leading to the marketability of the product. Project B will...
As you know, investment analysis/capital budgeting is a two step process. Assume the first part of...
As you know, investment analysis/capital budgeting is a two step process. Assume the first part of an investment analysis results in the second part being conducted. The second part returns an unfavorable answer. What are three things that you can do that would result in the investment being made?
Using capital budgeting, recommend a capital investment project and discuss what value will it add to...
Using capital budgeting, recommend a capital investment project and discuss what value will it add to the firm and should the organisation take up the project or not? the firm can be an educational institue or pharmaceutical company or any defined business.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT