In: Finance
You just finished calculating the NPV of project A and found it to be $49,242. A concurrent project, which will use the same resources as project A is now before you as well. This is project B, which will require a $2M investment in an asset that will have a $1M salvage value at the end of the project. A total of $170,000 was invested in the consulting and research leading to the marketability of the product. Project B will generate annual sales of $1.5M and total costs of $1.1M. The firm’s cost of capital is 7.5%, its tax rate is 30%, and the CCA depreciation for this asset is 20%. Project B will trigger a net change in working capital of $130,000. The project will last 6 years. Calculate the NPV of this project and say clearly whether you would accept it. You must show your work to get full points. 12 points.
Project B would not accept because it gives negative NPV from the project which is calculated below.
Calculation of NPV of Project B:
NPV = sum of discounted cash flow = -$2,300,000.00+$325,756.04+$292,644.46+$264,490.14+$240,272.80 +$219,241.48+$842,050.23 = -$115,544.84
Sl No | Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 |
i | Sales (given) | $1,500,000 | $1,500,000 | $1,500,000 | $1,500,000 | $1,500,000 | $1,500,000 | |
ii | Total costs (given) | $1,100,000 | $1,100,000 | $1,100,000 | $1,100,000 | $1,100,000 | $1,100,000 | |
iii |
Consulting & research expenses (Assumption 1) |
$34,000 | $34,000 | $34,000 | $34,000 | $34,000 | ||
iv | EBITDA (i-ii-iii) | $366,000 | $366,000 | $366,000 | $366,000 | $366,000 | $400,000 | |
v | Depreciation (refer Wno 1) | $200,000 | $160,000 | $128,000 | $102,400 | $81,920 | $65,536 | |
vi | EBIT (iv-v) | $166,000 | $206,000 | $238,000 | $263,600 | $284,080 | $334,464 | |
vii | Tax @ 30% (vi*0.3) | $49,800 | $61,800 | $71,400 | $79,080 | $85,224 | $100,339 | |
viii | PAT (vi-vii) | $116,200 | $144,200 | $166,600 | $184,520 | $198,856 | $234,125 | |
ix |
Consulting & research expenses (iii) |
$34,000 | $34,000 | $34,000 | $34,000 | $34,000 | ||
x | Depreciation (v) | $200,000 | $160,000 | $128,000 | $102,400 | $81,920 | $65,536 | |
xi |
Operating cashflow (viii+ix+x) |
$350,200 | $338,200 | $328,600 | $320,920 | $314,776 | $299,661 | |
xii | Investment in asset (given) | -$2,000,000 | $1,000,000 | |||||
xiii | Investment in consulting & research (given) | -$170,000 | ||||||
xiv | Net change in working capital (given) (Assumption 2) | -$130,000 | ||||||
xv | Total cashflow (xi+xii+xiii+xiv) | -$2,300,000 | $350,200 | $338,200 | $328,600 | $320,920 | $314,776 | $1,299,661 |
xvi | Present value factor @ 7.5% | 1.0000 | 1/1.075 = 0.9302 | 1/(1.075^2) = 0.8653 | 1/(1.075^3) = 0.8049 | 1/(1.075^4) = 0.7487 | 1/(1.075^5) = 0.6965 | 1/(1.075^6) = 0.6479 |
xvii | Discounted cashflow (xv*xvi) | -$2,300,000 | $325,756.04 | $292,644.46 | $264,490.14 | $240,272.80 | $219,241.48 | $842,050.23 |
Assumption 1 = Investment in consulting & research is allowed as deduction for tax purpose for 5 years. $170,000/5 = $34,000. Again assumed total costs exclude consulting & research expenses.
Assumption 2 = Net change in working capital in invested now. Assumed it will not be realised at the end of the project.
Wno 1:
Depreciation for year 1 =(Investment-salvage value)*20% = (2,000,000-1,000,000)*20% = 1,000,000*20% = 200,000
Depreciation for year 2 = (Investment-salvage value-depreciation for year 1)*20% = (2,000,000-1,000,000-200,000)*20% = 800,000*20% = 160,000
Depreciation for year 3 = (Investment-salvage value-accumulated depreciation)*20% = (2,000,000-1,000,000-200,000-160,000)*20% = 640,000*20% = 128,000
Depreciation for year 4 = (Investment-salvage value-accumulated depreciation)*20% = (2,000,000-1,000,000-200,000-160,000-128,000)*20% = 512,000*20% = 102,400
Depreciation for year 5 = (Investment-salvage value-accumulated depreciation)*20% = (2,000,000-1,000,000-200,000-160,000-128,000-102,400)*20% = 409,600*20% = 81,920
Depreciation for year 6 = (Investment-salvage value-accumulated depreciation)*20% = (2,000,000-1,000,000-200,000-160,000-128,000-102,400-81,920)*20% = 327,680*20% = 65,536