In: Finance
You just finished calculating the NPV of project A and found it to be $49,242. A concurrent project, which will use the same resources as project A is now before you as well. This is project B, which will require a $2M investment in an asset that will have a $1M salvage value at the end of the project. A total of $170,000 was invested in the consulting and research leading to the marketability of the product. Project B will generate annual sales of $1.5M and total costs of $1.1M. The firm’s cost of capital is 7.5%, its tax rate is 30%, and the CCA depreciation for this asset is 20%. Project B will trigger a net change in working capital of $130,000. The project will last 6 years. Calculate the NPV of this project and say clearly whether you would accept it. You must show your work to get full points. 12 points.
Based on the given data, pls find below workings;
Consulting cost is not considered in the working as the same is already expensed out and is a sunk cost.
Book Value (Cost - Accumulated Depreciation) is calculated at end of Year 6, to calculate capital gains/(Loss) as compared to the salvage value and thus tax on the capital gains/ (loss).
Computation of Net Present Value (NPV) based on the Discounted Cash flows; The Discounting factor is computed based on the formula: For year 0, the discounting factor is 1; For Year 1, it is computed as = Year 0 factor /(1+discounting factor%) ; Year 2 = Year 1 factor/(1+discounting factor %) and so on;
Next, the cashflows need to be multiplied with the respective years' discounting factor, to arrive at the discounting cash flows;
The total of all the discounted cash flows is equal to its respective Project NPV of the Cash Flows;
Based on these workings, the NPV of the Project B is $ 50617.43; This project is feasible to accept and also having higher NPV than that of Project A.