Question

In: Accounting

On January 1, 2018, the Marjlee Company began construction of an office building to be used...

On January 1, 2018, the Marjlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in 2019. Construction expenditures for 2018, which were incurred evenly throughout the year, totaled $7,200,000. Marjlee had the following debt obligations which were outstanding during all of 2018:

Construction loan, 10% $ 1,800,000
Long-term note, 9% 2,400,000
Long-term note, 6% 4,800,000


Required:
Calculate the amount of interest capitalized in 2018 for the building using the specific interest method.
  

Solutions

Expert Solution

Ans:

Interest to be capitalized in 2018 for the building

Average expenditure = 7,200,000/2 = 3,600,000

Weighted average rate:

2,400,000@9%                        = $216,000

4,800,000@6%                         = $288,000

$7,200,000                                = $504,000

504,000/7,200,000                    = 7%

interest capiralised

1,800,000 @ 10%                 = $180,000

1,800,000 @7%                 =     126,000

Interest capitalised              = $306,000

Hope this helped ! Let me know in case of any queries.


Related Solutions

On January 1, 2018, the Marjlee Company began construction of an office building to be used...
On January 1, 2018, the Marjlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in 2019. Construction expenditures for 2018, which were incurred evenly throughout the year, totaled $7,200,000. Marjlee had the following debt obligations which were outstanding during all of 2018: Construction loan, 11% $ 1,800,000 Long-term note, 10% 2,400,000 Long-term note, 7% 4,800,000 Calculate the amount of interest capitalized in 2018 for the building using the specific...
On January 1, 2018, the Marjlee Company began construction of an office building to be used...
On January 1, 2018, the Marjlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in 2019. Construction expenditures for 2018, which were incurred evenly throughout the year, totaled $9,900,000. Marjlee had the following debt obligations which were outstanding during all of 2018: Construction loan, 10% $ 2,475,000 Long-term note, 9% 3,300,000 Long-term note, 6% 6,600,000 Required: Calculate the amount of interest capitalized in 2018 for the building using the...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 2,020,000 March 1, 2018 1,740,000 June 30, 2018 1,940,000 October 1, 2018 1,740,000 January 31, 2019 441,000 April 30, 2019 774,000 August 31, 2019 1,071,000 On January 1, 2018, the company obtained a $4,900,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,710,000 March 1, 2018 1,320,000 June 30, 2018 1,520,000 October 1, 2018 1,320,000 January 31, 2019 378,000 April 30, 2019 711,000 August 31, 2019 1,008,000 On January 1, 2018, the company obtained a $4,200,000 construction loan with a 16% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,180,000 March 1, 2018 660,000 June 30, 2018 860,000 October 1, 2018 660,000 January 31, 2019 279,000 April 30, 2019 612,000 August 31, 2019 909,000 On January 1, 2018, the company obtained a $3,100,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,050,000 March 1, 2018 870,000 June 30, 2018 390,000 October 1, 2018 690,000 January 31, 2019 675,000 April 30, 2019 990,000 August 31, 2019 1,710,000 On January 1, 2018, the company obtained a $3 million construction loan with a 14% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,200,000 March 1, 2018 900,000 June 30, 2018 1,100,000 October 1, 2018 900,000 January 31, 2019 315,000 April 30, 2019 648,000 August 31, 2019 945,000 On January 1, 2018, the company obtained a $3,500,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,420,000 March 1, 2018 1,140,000 June 30, 2018 1,340,000 October 1, 2018 1,140,000 January 31, 2019 351,000 April 30, 2019 684,000 August 31, 2019 981,000 On January 1, 2018, the company obtained a $3,900,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,070,000 March 1, 2018 840,000 June 30, 2018 380,000 October 1, 2018 710,000 January 31, 2019 1,170,000 April 30, 2019 1,485,000 August 31, 2019 2,700,000 On January 1, 2018, the company obtained a $3 million construction loan with a 14% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,300,000 March 1, 2018 720,000 June 30, 2018 340,000 October 1, 2018 640,000 January 31, 2019 450,000 April 30, 2019 765,000 August 31, 2019 1,260,000 On January 1, 2018, the company obtained a $3 million construction loan with a 10% interest...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT