In: Finance
Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 8 percent.
Time: | 0 | 1 | 2 | 3 | 4 | 5 | 6 |
Cash flow: | –$8,600 | $1,080 | $2,280 | $1,480 | $1,480 | $1,280 | $1,080 |
Use the IRR decision rule to evaluate this project. (Negative amount should be indicated by a minus sign. Round your answer to 2 decimal places.)
IRR%=
Should it be accepted or rejected?
IRR :
IRR is the Rate at which PV of Cash Inflows are equal to PV of Cash
Outflows.
IRR = Rate at which least +ve NPV + [ NPV at that Rate / Change in NPV due to 1% inc in disc rate ] * 1%
If IRR > Cost of Capital - Project can be accepted
IRR = Cost of Capital - Indifferebce Point - Project will be
accepted / Rejected
IRR < Cost of Capital - Project will be erejected
Year | CF | PVF @0% | Disc CF | PVF @1% | Disc CF |
0 | $ -8,600.00 | 1.0000 | $ -8,600.00 | 1.0000 | $ -8,600.00 |
1 | $ 1,080.00 | 1.0000 | $ 1,080.00 | 0.9901 | $ 1,069.31 |
2 | $ 2,280.00 | 1.0000 | $ 2,280.00 | 0.9803 | $ 2,235.07 |
3 | $ 1,480.00 | 1.0000 | $ 1,480.00 | 0.9706 | $ 1,436.47 |
4 | $ 1,480.00 | 1.0000 | $ 1,480.00 | 0.9610 | $ 1,422.25 |
5 | $ 1,280.00 | 1.0000 | $ 1,280.00 | 0.9515 | $ 1,217.88 |
6 | $ 1,080.00 | 1.0000 | $ 1,080.00 | 0.9420 | $ 1,017.41 |
NPV | $ 80.00 | $ -201.61 |
IRR = Rate at which least +ve NPV + [ NPV at that rate / Change in NPV due to Inc of 1% in Int Rate ] * 1% |
= 0.00 + [80.00 / 281.61] * 1% |
= 0.00 + [0.28 ] * 1% |
= 0.00 + [0.0028] |
= 0.0028 i.e 0.28% |
As IRR(0.28%) < Cost of Capital ( 8%), Project is Rejected.
Pls do rate, if the answer is correct and comment, if any further assistance is required.