Question

In: Finance

A company is considering two mutually exclusive projects that have the following cash flows: Year                       Project...

A company is considering two mutually exclusive projects that have the following cash flows:

Year                       Project A Cash Flow                      Project B Cash Flow

0                              -$10,000                                             -$8,000

1                                   1000                                                7000

2                                   2000                                                1000            

3                                   6000                                                1000

4                                   6000                                                1000

If the company’s required rate of return is 10%, find the project’s NPV, IRR, PI, and payback period. Which project they should invest in?

Solutions

Expert Solution

Firstly we will calculate the NPV of both projects

Projects A NPV = (10,000) + 1000 / 1.101 + 2000 / 1.102 + 6000 / 1.103 + 6000 / 1.104

= $ 1,167.95

Projects B NPV = (8000) + 7000 / 1.101 + 1000 / 1.102 + 1000 / 1.103 + 1000 / 1.104

= $ 624.41

In order to compute the IRR the NPV of the projects shall be equal to zero.

IRR of project A:

Lets calculate the project NPV by taking a hypotheticaly rate of 12%

= (10,000) + 1000 / 1.121 + 2000 / 1.122 + 6000 / 1.123 + 6000 / 1.124

= $ 571.03

Now lets calculate the project NPV by taking a hypotheticaly rate of 15%

= (10,000) + 1000 / 1.151 + 2000 / 1.152 + 6000 / 1.153 + 6000 / 1.154

= ($ 242.53)

Now we can see that the IRR shall be in between these two rates since the projects NPV is zero between these two rates and we shall use the below formula in order to compute IRR.

= Lower Rate + Lower Rate NPV / ( Lower Rate NPV - Higher Rate NPV ) x (Higher Rate - Lower Rate)

By plugging the figures computed above in the formula we shall get:

= 12% + 571.03 / ( 571.03 - (242.53) ) x (15 -12)

= 12% + (571.03 / 813.56) x 3

= 14.10% Approximately

IRR of project B:

Lets calculate the project NPV by taking a hypotheticaly rate of 12%

= (8000) + 7000 / 1.121 + 1000 / 1.122 + 1000 / 1.123 + 1000 / 1.124

= $ 394.49

Now lets calculate the project NPV by taking a hypotheticaly rate of 16%

= (8000) + 7000 / 1.161 + 1000 / 1.162 + 1000 / 1.163 + 1000 / 1.164

= ($ 29.41)

Now we can see that the IRR shall be in between these two rates since the projects NPV is zero between these two rates and we shall use the below formula in order to compute IRR.

= Lower Rate + Lower Rate NPV / ( Lower Rate NPV - Higher Rate NPV ) x (Higher Rate - Lower Rate)

By plugging the figures computed above in the formula we shall get:

= 12% + 394.49 / ( 394.49 - (29.41) ) x (16 -12)

= 12% + (394.49 / 423.90) x 4

= 15.72% Approximately

PI of project A shall be computed by using the below formula

= Present Value of future cash flows / Initial Investment

= $ 11,167.95 / $ 10,000

= 1.17 Approximately

PI of project B shall be computed by using the below formula

= Present Value of future cash flows / Initial Investment

= $ 8,624.41 / $ 8,000

= 1.08 Approximately

Payback period of Project A can be computed as follows:

Year Cash Flow Cumulative Cash Flow
0 (10,000) (10,000)
1 1000 (9000)
2 2000 (7000)
3 6000 (1000)

As we can see that at the end of year 3 in order to recover our initial investment we need $ 1000 more. So our payback period shall be

= 3 years + Balance amount to be recovered for our initial investment / Year 4 cash inflow

= 3 years + 1000 / 6000

= 3.17 years Approximately

Payback period of Project B can be computed as follows:

Year Cash Flow Cumulative Cash Flow
0 (8,000) (8,000)
1 7000 (1000)
2 1000 0

As we can see that at the end of year 2, we have recovered our initial investment of $ 8,000 so our payback period shall be 2 years.

Since these two projects are mutually exclusive, we shall select only one project out of these on the basis of NPV criteria. So the project A shall be chosen since the NPV of project A is greater than the NPV of project B

Feel free to ask in case of any query relating to this question.


Related Solutions

Anderson Associates is considering two mutually exclusive projects that have the following cash flows: Project A...
Anderson Associates is considering two mutually exclusive projects that have the following cash flows: Project A Project B Year Cash Flow Cash Flow 0 -$10,000 -$8,000 1 4,000 7,000 2 2,000 3,000 3 6,000 1,000 4 8,000 3,000 At what cost of capital do the two projects have the same net present value? (That is, what is the crossover rate?) Enter your answer rounded to two decimal places. Do not enter % in the answer box. For example, if your...
Anderson Associates is considering two mutually exclusive projects that have the following cash flows: Project A...
Anderson Associates is considering two mutually exclusive projects that have the following cash flows: Project A Project B Year Cash Flow Cash Flow 0 -$11,000 -$9,000 1 3,500 6,000 2 3,000 4,000 3 5,000 3,000 4 9,000 2,000 At what cost of capital do the two projects have the same net present value? (That is, what is the crossover rate?) Enter your answer rounded to two decimal places. Do not enter % in the answer box. For example, if your...
Anderson Associates is considering two mutually exclusive projects that have the following cash flows: Project A...
Anderson Associates is considering two mutually exclusive projects that have the following cash flows: Project A Project B Year Cash Flow Cash Flow 0 -$11,000 -$9,000 1 3,500 6,000 2 3,000 4,000 3 5,000 3,000 4 9,000 2,000 At what cost of capital do the two projects have the same net present value? (That is, what is the crossover rate?) Enter your answer rounded to two decimal places. Do not enter % in the answer box. For example, if your...
Anderson Associates is considering two mutually exclusive projects that have the following cash flows: Project A...
Anderson Associates is considering two mutually exclusive projects that have the following cash flows: Project A Project B Year Cash Flow Cash Flow 0 -$11,000 -$9,000 1 4,500 6,000 2 3,000 4,000 3 5,000 3,000 4 9,000 2,000 At what cost of capital do the two projects have the same net present value? (That is, what is the crossover rate?) Enter your answer rounded to two decimal places. Do not enter % in the answer box. For example, if your...
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A...
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A Project B 0 -$50,000 -$50,000 1    15,000 0 2    15,000 0 3    15,000 0 4    15,000 0 5    15,000 90,000 1) Calculate NPV of each project if the required rate of return on these projects is 8 percent. 2) which would be chosen and why?
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,200 -7,800 1 1,325 1,325 2 2,148 2,148 3 3,640 7,360 The required return for both projects is 8%. 1. What is the IRR for project A? 2. What is the IRR for project B? 3. Which project seems better according to the IRR method? 4. What is the NPV for project A? 5. What is the NPV for project B?...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,700 -8,550 1 1,325 1,325 2 2,148 2,148 3 4,325 8,384 The required return for both projects is 8%. What is the IRR for project A? What is the IRR for project B? Which project seems better according to the IRR method? Project A Project B What is the NPV for project A? What is the NPV for project B? Which...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0   –$ 68,000   –$ 83,000 1 48,000 47,000 2 43,000 56,000 3 38,000 59,000 The cash flows of Project A are expressed in real terms, whereas those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 11 percent and the inflation rate is 5 percent. Calculate the NPV for each project. (Do not round intermediate calculations and round your answers...
Mutually exclusive investments. The following are cash flows of two projects. Year  Project A Project B 0...
Mutually exclusive investments. The following are cash flows of two projects. Year  Project A Project B 0 $ (200) $ (200) 1 80 100 2 80 100 3 80 100 4 80 Calculate the NPV for both projects if the discount rate is 11%(Do not intermediate calculations.Round your answer to 2 decimal places) Suppose that you can only choose one of the these projects. Which would you choose ? project A Project B Neither
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0 67000 82000 1 47000 46000 2 42000 55000 3 37000 58000 The cash flows of Project A are expressed in real terms while those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 10 percent and the inflation rate is 2 percent.    Calculate the NPV for each project. (Do not round intermediate calculations and round your answers to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT