Question

In: Finance

Two projects being considered are mutually exclusive and have the following cash flows: Year Project A...

  1. Two projects being considered are mutually exclusive and have the following cash flows:

Year

Project A

Project B

0

-$50,000

-$50,000

1

   15,000

0

2

   15,000

0

3

   15,000

0

4

   15,000

0

5

   15,000

90,000

1) Calculate NPV of each project if the required rate of return on these projects is 8 percent.

2) which would be chosen and why?

Solutions

Expert Solution


Related Solutions

Two mutually exclusive projects are being considered which have the following projected cash flows:                          &nbs
Two mutually exclusive projects are being considered which have the following projected cash flows:                                 Year                       Project A               Project B                                    0                           ($50,000)              ($50,000)                                    1                           $15,625                                $         0                                    2                           $16,000                                $         0                                    3                           $15,000                                $         0                                    4                           $16,000                                $         0                                    5                           $15,500                                $99,500 a. Calculate the NPV for each of these projects using a 10% rate of return. Also, indicate which project should be chosen based on the NPV...
Two projects being considered by a firm are mutually exclusive and have the following projected cash...
Two projects being considered by a firm are mutually exclusive and have the following projected cash flows: Year Project A Project B 0 ($100,000) ($100,000) 1 39,500 0 2 39,500 0 3 39,500 133,000 Based only on the information given, which of the two projects would be preferred, and why? Project A, because it has an even cash inflow stream. Project B, because it has a higher IRR. Indifferent, because the projects have equal IRRs. Include both in the capital...
Two projects being considered by a firm are mutually exclusive and have the following projected cash...
Two projects being considered by a firm are mutually exclusive and have the following projected cash flows: Project A Project B Year Cash Flow Cash Flow Proj A Project B 0 -$300,000 -$300,000 1 145,500 $150,000 2 145,500 -$ 40,000 3 145,500 $370,000 The firm’s cost of capital is 10 percent. Based only on the information given, What are the NPV for Project A and B? Which project do you choose based on the NPV? What are the payback periods...
A company is considering two mutually exclusive projects that have the following cash flows: Year                       Project...
A company is considering two mutually exclusive projects that have the following cash flows: Year                       Project A Cash Flow                      Project B Cash Flow 0                              -$10,000                                             -$8,000 1                                   1000                                                7000 2                                   2000                                                1000             3                                   6000                                                1000 4                                   6000                                                1000 If the company’s required rate of return is 10%, find the project’s NPV, IRR, PI, and payback period. Which project they should invest in?
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,200 -7,800 1 1,325 1,325 2 2,148 2,148 3 3,640 7,360 The required return for both projects is 8%. 1. What is the IRR for project A? 2. What is the IRR for project B? 3. Which project seems better according to the IRR method? 4. What is the NPV for project A? 5. What is the NPV for project B?...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,700 -8,550 1 1,325 1,325 2 2,148 2,148 3 4,325 8,384 The required return for both projects is 8%. What is the IRR for project A? What is the IRR for project B? Which project seems better according to the IRR method? Project A Project B What is the NPV for project A? What is the NPV for project B? Which...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0   –$ 68,000   –$ 83,000 1 48,000 47,000 2 43,000 56,000 3 38,000 59,000 The cash flows of Project A are expressed in real terms, whereas those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 11 percent and the inflation rate is 5 percent. Calculate the NPV for each project. (Do not round intermediate calculations and round your answers...
Mutually exclusive investments. The following are cash flows of two projects. Year  Project A Project B 0...
Mutually exclusive investments. The following are cash flows of two projects. Year  Project A Project B 0 $ (200) $ (200) 1 80 100 2 80 100 3 80 100 4 80 Calculate the NPV for both projects if the discount rate is 11%(Do not intermediate calculations.Round your answer to 2 decimal places) Suppose that you can only choose one of the these projects. Which would you choose ? project A Project B Neither
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0 67000 82000 1 47000 46000 2 42000 55000 3 37000 58000 The cash flows of Project A are expressed in real terms while those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 10 percent and the inflation rate is 2 percent.    Calculate the NPV for each project. (Do not round intermediate calculations and round your answers to...
Two mutually exclusive projects have the following forecasted cash flows:
Two mutually exclusive projects have the following forecasted cash flows: Year           A                      B 0                -20,000             -20,000 1                10,000                          0 2                10,000                          0 3                10,000                          0 4                10,000                60,000 Compute the internal rate of return for each project. Compute the NPV for each project if the required rate is 10%. Which project should be accepted, and why?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT