Question

In: Accounting

Dalton Construction Co. contracted to build a bridge for $8,000,000. Construction began in 2018 and was...

Dalton Construction Co. contracted to build a bridge for $8,000,000. Construction began in 2018 and was completed in 2019. Data relating to the construction are: 2018 2019 Costs incurred during the year $2,105,600 $2,408,400 Estimated costs to complete 2,374,400 ― Dalton uses the percentage-of-completion method.

Part 1 How much revenue should be reported for 2018?

Part 2 Make the entry to record progress billings of $2,905,600 during 2018. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.)

Account Titles and Explanation

Debit

Credit

Part 3 Make the entry to record the revenue and gross profit for 2018. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.)

Account Titles and Explanation

Debit

Credit

Part 4 How much gross profit should be reported for 2019?

Gross profit $

Solutions

Expert Solution

Solution

Dalton Construction Co

  1. Determination of the amount of revenue to be reported for 2018:

contract amount x [cost incurred/(cost incurred + estimated costs to complete]

contract amount = $8,000,000

cost incurred = $2,105,600

Estimated costs to complete = $2,374,400

Revenue to be reported for 2018 = $8,000,000 x [2,105,600/(2,105,600 + 2,374,400)] = $3,760,000

Gross profit = 3,760,000 – 2,105,600 = $1,654,400

  1. Entry to record progress billings of $2,105,600:

Date

Account Titles and Explanation

Ref. No.

Debit

Credit

Accounts Receivable

$2,105,600

Billing on Construction in Process

$2,105,600

  1. Entry to record the revenue and gross profit for 2018:

Date

Account Titles and Explanation

Ref. No.

Debit

Credit

Construction Expenses

$2,105,600

Construction in Process

$1,654,400

Revenue from Long-Term Contracts

$3,760,000

  1. How much gross profit to be reported in 2019:

Gross profit in 2019 = $1,831,600

Revenue

$8,000,000

costs incurred

$4,514,000

Gross Profit

$3,486,000

Recognized in 2018

$1,654,400

Recognized in 2019

$1,831,600

Alternatively,

Total revenue

$8,000,000

Recognzied in 20`18

$3,760,000

Recognized in 2019

$4,249,000

Costs in 2019

$2,408,400

Gross profit in 2019

$1,831,600


Related Solutions

Rajbir Construction Co. contracted to build a bridge for $10,000,000. Construction began in 2018 and was...
Rajbir Construction Co. contracted to build a bridge for $10,000,000. Construction began in 2018 and was completed in 2019. Data relating to the construction are: 2018 2019 Costs incurred during the year $3,300,000 $2,750,000 Estimated costs to complete 2,700,000 — Raj uses the percentage-of-completion method. Instructions (a) How much revenue should be reported for 2018? Show your computation. (b) Make the entry to record progress billings of $4,100,000 during 2018. (c) Make the entry to record the revenue and gross...
Chapter 18 Howard Construction Co. contracted to build a bridge for $3,000,000. Construction began in 2012...
Chapter 18 Howard Construction Co. contracted to build a bridge for $3,000,000. Construction began in 2012 and was completed in 2013. Data relating to the construction are:                                                                                                  2012              2013             Costs incurred                                                     $990,000       $825,000             Estimated costs to complete                                810,000                — Howard uses the percentage-of-completion method. Instructions:         (a)           How much revenue should be reported for 2012?         (b)          Make the entry to record progress billings of $1,000,000 during 2012.         (c)            Make the entry...
Brady Construction Company contracted to build an apartment complex for a price of $5,800,000. Construction began...
Brady Construction Company contracted to build an apartment complex for a price of $5,800,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2021 2022 2023 2021 2022 2023 1 1,580 2,370 1,140 3,510 1,140 — 2 1,580...
Brady Construction Company contracted to build an apartment complex for a price of $5,200,000. Construction began...
Brady Construction Company contracted to build an apartment complex for a price of $5,200,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2018 2019 2020 2018 2019 2020 1 1,520 2,190 960 3,150 960 — 2 1,520...
Brady Construction Company contracted to build an apartment complex for a price of $6,000,000. Construction began...
Brady Construction Company contracted to build an apartment complex for a price of $6,000,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2018 2019 2020 2018 2019 2020 1 1,600 2,430 1,200 3,630 1,200 — 2 1,600...
Brady Construction Company contracted to build an apartment complex for a price of $5,200,000. Construction began...
Brady Construction Company contracted to build an apartment complex for a price of $5,200,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2021 2022 2023 2021 2022 2023 1 1,520 2,190 960 3,150 960 — 2 1,520...
Brady Construction Company contracted to build an apartment complex for a price of $5,200,000. Construction began...
Brady Construction Company contracted to build an apartment complex for a price of $5,200,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2021 2022 2023 2021 2022 2023 1 1,520 2,190 960 3,150 960 — 2 1,520...
Brady Construction Company contracted to build an apartment complex for a price of $6,800,000. Construction began...
Brady Construction Company contracted to build an apartment complex for a price of $6,800,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2018 2019 2020 2018 2019 2020 1 1,680 2,670 1,440 4,110 1,440 — 2 1,680...
Brady Construction Company contracted to build an apartment complex for a price of $6,900,000. Construction began...
Brady Construction Company contracted to build an apartment complex for a price of $6,900,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2018 2019 2020 2018 2019 2020 1 1,690 2,700 1,470 4,170 1,470 — 2 1,690...
Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began...
Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2018 2019 2020 2018 2019 2020 1 1,630 2,520 1,290 3,810 1,290 — 2 1,630...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT