Question

In: Accounting

QUESTION 1: CONSTRUCTION/CIVIL FRAUD A major infrastructure company, Mega Construction Corp. had been awarded a road...

QUESTION 1: CONSTRUCTION/CIVIL FRAUD

A major infrastructure company, Mega Construction Corp. had been awarded a road construction contract by the government. For execution of the project, the company had sub-divided the geographies and execution areas and invited bids for the sub-contracting. The company had publicized a whistle-blower policy and received a complaint from one of the bidders about possible collusion between certain bidders. The matter was sought to be investigated by the management of the company.

As the company’s fraud expert, you are investigating this possible fraud and are preparing to take necessary actions to complete a thorough investigation.

REQUIRED:

(a) Determine the possible type of schemes being perpetrated and red flag indicators of the said conduct.

(b) What are the steps taken to complete the investigation and the evidence sought for prosecution of perpetrators?

Solutions

Expert Solution

Answer a

The most common schemes considered while collusion are as follows:

  • Market division- Market division occurs when the bidding members agree to divide their market (e.g., geographical territories and client segments) thereby restricting competition
  • Bid rotation- Bid rotation refers to an agreement among bidders to take turns in winning contracts.
  • Price fixing- Price fixing refers to an agreement among competitors to fix prices at which goods and services are sold in a specific market.

The various red flags related to the above schemes are as follows:

Bid prices are unusually high- Bid prices would be relatively high compared the industry standards

Bidders loose on purpose- To favour one company the other bidders loose on purpose without even trying for genuine bid. They withdraw the bids in the last moment even without proper justification

Bids would be similar- The unit prices and bid prices would be identical and very close. This gives a clue that all the bidders have quoted the amount post discussion

Bidders take turns in winning- When there are group of 10 bidders for examples one bidder would give the best quote and other bidders quote in such a way that would lose by default

Lack of competition- Well know companies would not bid even after purchasing the bidding documents. Fewer bids would be received compared to the earlier tender.

Answer b

To proceed with the investigation necessary conversations and discussion should be carried out with industry representatives. The discussions could help identify the operation of collusive arrangements among bidders. The past contract awards and earlier bids and bidding documents could be verified as a part of investigation. The bids given can be compared with the industry standards and if the variation is quite abnormal it gives adequate evidence. There are possibilities of shadow bids to give appearance of competition. If the shadow bids could be identified it could serve as a evidence for prosecution. When the bids show unusual similarities like same contact details, letter head and errors it could even serve as a evidence for prosecution.


Related Solutions

Construction Engineering question: Produce a environmental management plan Company has been awarded the contract for a...
Construction Engineering question: Produce a environmental management plan Company has been awarded the contract for a bridge replacement, including 2km approach resurfacing on each side and has placed you and your team in charge. Produce a environmental management plan. Thanks!!
The Scenario: A construction company has been awarded the contract to build a pipeline in Alaska....
The Scenario: A construction company has been awarded the contract to build a pipeline in Alaska. The project timeline is of the highest priority because work can only be completed during summer months due to adverse weather conditions. One of the suppliers of a key component has longer lead time than is required to complete the pipeline, but may be able to deliver if the construction company will pay fees to expedite. There are other suppliers, but these suppliers are...
A building company has been awarded the contract to undertake the construction works for a multi-storey...
A building company has been awarded the contract to undertake the construction works for a multi-storey office project in a city centre location. A deep basement is to be installed under one half of the building, within a layer of dense gravel. The site is surrounded by public roads and buildings on all sides and it is expected that the water table is extremely close to the ground surface on a year-round basis. You have been asked by the contractor...
QUESTION 1 Garrett has been an employee of Construction Company for seven years.   His manager notices...
QUESTION 1 Garrett has been an employee of Construction Company for seven years.   His manager notices that he has been working late making sure that the shop equipment is properly stored and locked up at the end of each workday. The manager tells Garrett that he has appreciated his hard work, that Garrett should not feel obligated to stay late to lock up the equipment anymore, and that Garrett can expect a $250 bonus in his next paycheck because of...
You have been hired by Patterson Planning Corp., an events planning company that recently had a...
You have been hired by Patterson Planning Corp., an events planning company that recently had a fire in which some of the accounting records were damaged. In reviewing the fixed asset records, you find three depreciation schedules that are not labeled. They are listed in the following table. One of the assets has a depreciation rate of $4.30 per hour. Year Schedule A Schedule B Schedule C 1 $8,000.00 $10,125.00 $8,600.00 2 4,800.00 13,500.00 6,450.00 3 2,880.00 13,500.00 7,310.00 4...
You have been hired by Patterson Planning Corp., an events planning company that recently had a...
You have been hired by Patterson Planning Corp., an events planning company that recently had a fire in which some of the accounting records were damaged. In reviewing the fixed asset records, you find three depreciation schedules that are not labeled. They are listed in the following table. One of the assets has a depreciation rate of $4.40 per hour. Year Schedule A Schedule B Schedule C 1 $6,000.00 $10,125.00 $8,800.00 2 3,600.00 13,500.00 6,600.00 3 2,160.00 13,500.00 7,480.00 4...
Question 8 Queens Construction Company commences construction of a harbour on 1 July 2020. It signs...
Question 8 Queens Construction Company commences construction of a harbour on 1 July 2020. It signs a fixed-price contract for total revenue of $400 million. The project is expected to be completed by the end of June 2023. The expected cost at the commencement of construction was $300 million. The expected costs to complete a construction project can change throughout the project. The following data relates to the project: 2021 2022 2023 ($ M) ($ M) ($ M) Costs for...
Question # 1 You have been hired by Yew Corp. to advise them on how to...
Question # 1 You have been hired by Yew Corp. to advise them on how to reflect the events below in their financial statements for the year ended December 31, 2017 under ASPE. Event 1: The Division A employees union has been negotiating a new contract with Yew Corp. The union is requesting a 5% wage increase retroactive for two years. Yew’s management has offered the union a 2% wage increase retroactive for one year. While the negotiations are still...
Question 1. a) Modern Methods of Construction (MMC) is a term which has been commonly applied...
Question 1. a) Modern Methods of Construction (MMC) is a term which has been commonly applied to construction activities. Using your own words supported by references, provide an explanation of MMC and detail the technical construction procedures classified as MMC and explain how these differ from traditional construction
Question text Company began construction of a machine on 1/1/2021. Company borrowed $700,000 at 10% on...
Question text Company began construction of a machine on 1/1/2021. Company borrowed $700,000 at 10% on 1/1/2021 for this project. The project was under construction during the entire calendar year. Expenditures were made on the project during the year: Expenditure || Date            100,000 1/1/2021            300,000 3/1/2021            600,000 7/1/2021            400,000 10/1/2021 Company also had $1,000,000 outstanding at 12% during the entire year. Required: Calculate Avoidable and Actual Interest. Show work to receive credit.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT