Question

In: Operations Management

Eastern Engineering Company is trying to decide which of 6 projects to perform during the next...

  1. Eastern Engineering Company is trying to decide which of 6 projects to perform during the next quarter. The net present value, the estimated cost, and the number of engineers and staff personnel required for each project are given in the following table.

Project

Net Present Value ($1000’s)

Cost ($1000’s)

Engineers Required

Staff Required

1

100

35

5

2

2

145

65

8

3

3

200

95

11

2

4

250

180

4

2

5

500

250

16

7

6

695

475

19

11

Eastern has a $550,000 budget and 30 engineers and 15 staff available. Which projects should Eastern perform during the quarter?

Solutions

Expert Solution

The project table is:

Project

Net Present Value ($1000s)

Cost ($1000s)

Engineers Required

Staff Required

1

100

35

5

2

2

145

65

8

3

3

200

95

11

2

4

250

180

4

2

5

500

250

16

7

6

695

475

19

11

Budget available = $550,000 = $550*1000

Engineers available = 30

Staff Available = 15

We have to find the projects should be performed.

We have to select the projects such as to maximize the Net Present Value.

Let Project 1 = x1

Project 2 = x2

Project 3 = x3

Project 4 = x4

Project 5 = x5

Project 6 = x6

If value of xi = 1, then the project will be chosen

If value of xi = 0, then the project wont be chosen

Objective:

We have to maximize the Net Present Value.

Maximize 100*x1 + 145*x2 + 200*x3 + 250*x4 + 500*x5 + 695*x6

Constraints:

The total cost used should not exceed the budget.

35*x1 + 65*x2 + 95*x3 + 180*x4 + 250*x5 + 475*x6 <= 550

Total engineers used should not exceed engineers available. Total staff used should not exceed the total staff available.

5*x1 + 8*x2 + 11*x3 + 4*x4 + 16*x5 + 19*x6 <=30 (for engineers)

2*x1 + 3*x2 + 2*x3 + 2*x4 + 7*x5 + 11*x6 <= 15 (for staff)

The project can be either be selected or rejected. Hence another constraint is the decision variables being binary.

x1:x6 : binary

Putting everything in excel:

Solver Parameters:

Optimal Solution:

Hence,

The projects that Eastern should perform during the quarter: Project 2, Project 4 and Project 5

The Net Present Value is: $895000

The total cost of all the projects is: $495000

Engineers Used: 28

Staffs Used: 12

.

IF YOU HAVE ANY DOUBT, KINDLY COMMENT. I WOULD LOVE TO HELP YOU!!!

IF YOU LIKE THE ANSWER, PLEASE GIVE AN UP-VOTE OR THUMB UP. THIS WILL ENCOURAGE ME TO ANSWER MORE!!


Related Solutions

Your company is trying to decide which one of two projects it should accept. Both projects...
Your company is trying to decide which one of two projects it should accept. Both projects have the same start-up costs. Project 1 will produce annual cash flows of $52 000 at the end of each year for six years. Project 2 will produce cash flows of $39 000 at the beginning of each year for eight years. The company requires a 15% return. Required: a. Whichprojectshouldthecompanyselectandwhy? b. Whichprojectshouldthecompanyselectiftheinterestrateis12%atthe cash flows in Project 2 is also at the end of...
A television network is trying to decide during the summer which of the following three football...
A television network is trying to decide during the summer which of the following three football games to televise on the Saturday following Thanksgiving Day: Alabama versus Auburn, Georgia versus Georgia Tech, or Army versus Navy. The estimated viewer ratings for the games depend on the win–loss records of the six teams, as shown in the following payoff table:                 Number of Viewers (1,000,000s)                              One Team Has Both Teams       Winning Record; One      Both Teams Have Winning      Team Has Losing...
A company is trying to decide between TWO projects that would provide the same necessary service...
A company is trying to decide between TWO projects that would provide the same necessary service and each project can be repeated indefinitely at the same cost and same cash flows. The first project costs $7,000 and is expected to generate cash flows of $4,250 for NINE years. The second project cost $10,000 and is expected to generate cash flows of $4,400 for ELEVEN years While the replacement chain approach is a valid option, you currently cannot use a spreadsheet...
when a company is trying to decide on which capitalization option is best for the company...
when a company is trying to decide on which capitalization option is best for the company why are the following three important? Company’s capital structure, Company’s working capital and Asset performance of the company. ​
Chandler Tire Co. is trying to decide which one of two projects it should accept. Both...
Chandler Tire Co. is trying to decide which one of two projects it should accept. Both projects have the same start-up costs. Project 1 will produce annual cash flows of $52,000 a year for six years. Project 2 will produce cash flows of $48,000 a year for eight years. The company requires a 15 percent rate of return. Which project should the company select and why? Project 1, because the annual cash flows are greater by $4,000 than those of...
4) The company you work for is trying to decide between two projects. Project 1 costs...
4) The company you work for is trying to decide between two projects. Project 1 costs $160,000 up front, and has an expected life of 4 years, over which it will return $52,000 each of the four years. Project 2 would last for 20 years, costs $1.5 million up front, and returns $170,000 at the end of each of the 20 years. Assuming a real discount rate of 6%, which project has the higher equivalent annual net benefit?
Brazen, Ltd. has $75,000 to invest. The company is trying to decide between two different projects.  The...
Brazen, Ltd. has $75,000 to invest. The company is trying to decide between two different projects.  The alternatives are: Project A Project B Cost of equipment required $ 75,000 $ - Working capital investment required $ - $ 75,000 Annual cash inflows $ 18,000 $ 11,000 Salvage value of equipment in six years $ 22,000 $ - Life of the project 6 years 6 years The working capital needed for project B will be released at the end of six years...
An enterprise has to decide between two investment projects from which the next information is known:...
An enterprise has to decide between two investment projects from which the next information is known: The investment X requires an initial investment of 150 million euros, generating annual cash flow (also in million euros) of 30 the first year, 56 the second year and 150 the third one. Meanwhile, the investment “Y” also requires an initial investment of 150 million euros, but it generates annual cash flow (also in million euros) of 40 the first year, 50 the second...
Tower Engineering Corporation is considering undertaking several proposed projects for the next fiscal year. The projects,...
Tower Engineering Corporation is considering undertaking several proposed projects for the next fiscal year. The projects, the number of engineers and the number of support personnel required for each project, and the expected profits for each project are summarized in the following table: Project 1 2 3 4 5 6 Engineers Required 20 55 47 38 90 63 Support Personnel Required 15 45 50 40 70 70 Profit ($1,000,000s) 1.0 1.8 2.0 1.5 3.6 2.2 Formulate an integer program that...
1) You own a mining company and are trying to decide which of three mines to...
1) You own a mining company and are trying to decide which of three mines to lease to extract ore from. For mine A you pay a leasing fee of $1,040 in period 0, and then earn net profits of $400 per year for years 1-8; in year 9 you have to pay a fee of $2,500 to rehabilitate the mining site. For mine B you pay a fee of $240 in period 0 to lease the mine and then...