In: Finance
Question:
Your company is trying to decide which one of two projects it should accept. Both projects have the same start-up costs. Project 1 will produce annual cash flows of $52 000 at the end of each year for six years. Project 2 will produce cash flows of $39 000 at the beginning of each year for eight years. The company requires a 15% return. Required:
a. Which project should the company select and why?
Solution:
NPV of Project 1:
Here:
Cash Flows = $ 52,000 per year at the end of each year.
Discount Rate = 15 %
Number of Years = 6 Years
Tabulation of Calculation of Net Present Value of Project 1:
Years |
Cash Flows |
Present Value of Net Cash Flow = Net Cash Flow / (1 + Discount Rate / 100) ^Number of Year |
0 |
$ 52,000 |
(52,000) / (1+0.15) ^0 = $ 52,000.00 |
1 |
$ 52,000 |
(52,000) / (1+0.15) ^1 = $ 45,217.39 |
2 |
$ 52,000 |
(52,000) / (1+0.15) ^2 = $ 39,319.47 |
3 |
$ 52,000 |
(52,000) / (1+0.15) ^3 = $ 34,190.84 |
4 |
$ 52,000 |
(52,000) / (1+0.15) ^4 = $ 29,731.17 |
5 |
$ 52,000 |
(52,000) / (1+0.15) ^5 = $ 25,853.19 |
Total |
Net Present Value of Project 1= $ 226,313.00 |
Net Present Value of Project 2:
Here:
Cash Flows = $ 39,000 per year at the beginning of each year.
Discount Rate = 15 %
Number of Years = 8 Years
Tabulation of Calculation of Net Present Value of Project 2:
Years |
Cash Flows |
Present Value of Cash Flow = Cash Flow / (1 + Discount Rate / 100) ^Number of Years |
1 |
$ 39,000 |
(39,000) / (1+0.15) ^1 = $ 33913.04 |
2 |
$ 39,000 |
(39,000) / (1+0.15) ^2 = $ 29489.60 |
3 |
$ 39,000 |
(39,000) / (1+0.15) ^3 = $ 25643.13 |
4 |
$ 39,000 |
(39,000) / (1+0.15) ^4 = $ 22298.38 |
5 |
$ 39,000 |
(39,000) / (1+0.15) ^5 = $ 19389.89 |
6 |
$ 39,000 |
(39,000) / (1+0.15) ^6 = $ 16860.78 |
7 |
$ 39,000 |
(39,000) / (1+0.15) ^7 = $ 14661.54 |
8 |
$ 39,000 |
(39,000) / (1+0.15) ^8 = $ 12749.17 |
Total |
Net Present Value of Project 2= $ 175,006.00 |
Ans: Company should select Project 1 because the NPV of Project 1 is higher than that of Project 2
NPV of Project 1 = $ 226,313.00 > NPV of Project 2 = $ 175,006.00
b. Which project should the company select if the interest rate is 12% at the
cash flows in Project 2 is also at the end of each year?
Solution:
NPV of Project 2 with New Data:
Here:
Cash Flows = $ 39,000 per year at the end of each year.
Discount Rate = 12 %
Number of Years = 8 Years
Tabulation of Calculation of Net Present Value of Project 2:
Years |
Cash Flows |
Present Value of Cash Flow = Cash Flow / (1 + Discount Rate / 100) ^Number of Years |
0 |
$ 39,000 |
(39,000) / (1+0.12) ^0 = $ 39,000.00 |
1 |
$ 39,000 |
(39,000) / (1+0.12) ^1 = $ 34,821.43 |
2 |
$ 39,000 |
(39,000) / (1+0.12) ^2 = $ 31,090.56 |
3 |
$ 39,000 |
(39,000) / (1+0.12) ^3 = $ 27,759.43 |
4 |
$ 39,000 |
(39,000) / (1+0.12) ^4 = $ 24,785.21 |
5 |
$ 39,000 |
(39,000) / (1+0.12) ^5 = $ 22,129.65 |
6 |
$ 39,000 |
(39,000) / (1+0.12) ^6 = $ 19,758.61 |
7 |
$ 39,000 |
(39,000) / (1+0.12) ^7 = $ 17,641.62 |
Total |
Net Present Value of Project 2= $ 216,987.00 |
Ans: In this case also, Company should select Project 1 because the NPV of Project 1 is higher than that of Project 2
NPV of Project 1 = $ 226,313.00 > NPV of Project 2 = $ 216,987.00