Question

In: Civil Engineering

ABC Construct Bina Sdn Bhd. is awarded a contract to construct 100 single storey houses. The...

ABC Construct Bina Sdn Bhd. is awarded a contract to construct 100 single storey houses. The construction method is using conventional method or in-situ construction. Concrete is the main material used in that construction project.

a) Demonstrate the roles of parties involved in ensuring good quality of work is delivered during the construction project.

b) Explain the assessment involved in ensuring the quality of the reinforced concrete structural elements.

c) Discuss the possible problems related to poor quality control that may arise at construction site.

Solutions

Expert Solution

a)

  • Client:
  • The client should clearly mention the all required specifications at the time agreement itself.
  • The specifications of material for each work should be given to the contractor for every work.
  • And frequent inspection of the work , and checking the specifications is the most necessary in the conventional construction. As itself includes the highest cost to complete the project.

         Contractor:

  • The contractor should clearly read all the specifications and maintain the Work break down structure as per the give schedule.
  • Naturally contractor will give the work to subcontractor so he will scrutinize the work at all stages.
  • If one mistake done at the ending stage which oversees will become the biggest mistake of the project.
  • And the material is the most important in the construction industry.
  • The contractor should test the required material properties at the every time the batch arrives. And third party testing will also help the most.
  • And making the perfect schedule he should complete the work within the timeline.

  1. When it comes to the concrete , because it’s a in-situ project the batching plant will be at the site itself.
  • Reinforced concrete structures are subjected to a series of actions throughout their lifespan which can be the cause of deterioration.
  • In proper strength of the concrete will lead to the failure of the structure. So the concrete will be checked for workability and strength at the time use.
  • And improper pumping and mixing will lead to the segregation of the aggregates from the mix.
  • And excess final setting time of concrete will lead to the cracks.
  • Improper placing of the formwork leads to the concrete bulging.
  • If the reinforced bars in the concrete are affected by corrosion then the concrete life will be deteriorated.
  • So , to avoid all this the basic tests for the concrete should be done. And care should be taken while placing the concrete.
  1. The main problems arrive at site because of pure quality control mainly related to the materials only.
  • Because of the poor quality of cement the concrete did not have enough strength and issues related to setting time also.
  • Which leads to the bulging of the concrete , deterioration and cracking of the concrete.
  • Steel is the main structural element in the construction. Which should be checked properly placed properly to avoid collapse and corrosion.
  • Because of the corrosion both concrete and steel will affected which leads to the structure collapse.
  • If we maintain the quality check properly this will not happen.


Related Solutions

A building company has been awarded the contract to undertake the construction works for a multi-storey...
A building company has been awarded the contract to undertake the construction works for a multi-storey office project in a city centre location. A deep basement is to be installed under one half of the building, within a layer of dense gravel. The site is surrounded by public roads and buildings on all sides and it is expected that the water table is extremely close to the ground surface on a year-round basis. You have been asked by the contractor...
a) Based on the information below, prepared a financial position of company ABC Sdn Bhd. as...
a) Based on the information below, prepared a financial position of company ABC Sdn Bhd. as at 31.12.2019.          Items   RM Inventories 600,000 Retained earnings 270,000 Long-term loan 60,000 Tax payables 180,000 Trade receivables 780,000 Share capital 240,000 Overdraft 400,000 Furniture & Fittings 270,000 Trade payables 420,000 Other payables 80,000                                                                                                                                              b) You are required to calculate and comments on the following:    (i) Non-current asset (ii) Current asset    (iii) Current liabilities    (iv)...
Question 3 Barbie Sdn Bhd (BSB) manufactures and sells a single product which is a barbie...
Question 3 Barbie Sdn Bhd (BSB) manufactures and sells a single product which is a barbie doll. Following information are provided below: RM Manufacturing costs: Direct materials cost per unit 55 Direct labor cost per unit 45 Variable overhead cost per unit 36 Fixed overhead cost in total 51,000 Selling expenses: Variable selling expenses per unit 14 Fixed selling expenses in total 18,000 The selling price for each unit of barbie doll is RM220.00. Required: a) Differentiate between variable cost...
You and your team are awarded a 1 year contract to supply/deliver, construct, test and commissioning...
You and your team are awarded a 1 year contract to supply/deliver, construct, test and commissioning of a 20 units 2-storey shophouse near your hometown. Construct a financial plan to illustrate your preparation of material and manpower delivery plan comprehensively. Assuming the total budget will be $20,000,000
ABC Construction Co. signed a $2,000,000 contract to construct an office building for the State of...
ABC Construction Co. signed a $2,000,000 contract to construct an office building for the State of Arizona. The project will begin in 2017 and be completed in 2018. The cost of construction is expected to be $1,875,000. Below is a summary of events for 2017 and 2018: 2017 2018 Costs incurred during the year $ 712,500 $1,138,250 Estimated costs to complete 1,037,500 0 Billings during the year 850,000 1,150,000 Cash collections during the year 750,000 1,000,000 ABC Construction Co. recognizes...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT