Question

In: Economics

A new highway is to be constructed with two alternative designs. Design A calls for a...

A new highway is to be constructed with two alternative designs. Design A calls for a concrete pavement costing $90 per foot with a 20-year life; two paved ditches costing $3 per foot each; and three box culverts every mile, each costing $9,000 and having a 20-year life. Annual maintenance will cost $1,800 per mile; the culverts must be cleaned every five years at a cost of $450 each per mile. Design B calls for a bituminous pavement costing $45 per foot with a 10-year life, two sodded ditches costing $1.50 per foot each; and three pipe culverts every mile, each costing $2,250 and having a 10-year life. The replacement culverts will cost $2,400 each. Annual maintenance will cost $2,700 per mile; the culverts must be cleaned yearly at a cost of $225 each per mile; and the annual ditch maintenance will cost $1.50 per foot per ditch. Compare the two designs using equivalent worth per mile for a 20-year period. Find the most economical design if the MARR is 6% per year.

Solutions

Expert Solution

Answer:

Given that:

A new highway is to constructed with two alternative designs .

Start design A in which all components have a life of 20 years . Now the capital investment for this design will be

Concrete pavement = ($90 / ft)(5,280 ft / min)

= $475,200 / mile

Paved ditches = 2($3 / ft)(5,280 ft / min)

= $31,680 / mile

Box culverts = (3 culverts / mile)($9,000 / min)

= $27,000 / mile

Therefore the total capital investment will become,

Total capital investment = $475,200 +$31,680+$27,000

= $533,880 / mile

The design maintenance cost is given as $1,800.

With this periodic cleaning of culverts will become :

(3 culverts / mile)($450 / culverts) = $1,350 / mile

Now apply the AW formula:

AW (i%) = R -E -CR(i%)

The annual worth in this case will become,

AW(6%)=-$533,880(A /P ,6%,20)-$1,800-$1,350(A / F ,6%, 5)

= -$48,594 / mile

Now calculate the present worth of design A

PW(6%)=-$533,880-[$1,800+$1,350(A /F ,6%,5)](P / A ,6%, 20)

= -$557,273 / mile

Consider design B in which all components have life of 0 years.Now the capital investment for this design in zero year will be

Bituminous pavement = ($45 / ft)(5,280 ft / min)

=$237,600

Sodded ditches = 2($150 / ft)(5,280 ft / min)

=$15,840 / mile

Pipe culverts = (3 culverts / mile)($2,250 / culverts)

=$6,750 / mile

Therefore the total capital investment will become

Total capital investment = $237,600+$15,840+$6.750

=$260,190 / mile

Consider design B in which all components have end of  years 10 years.Now the capital investment for this design in zero year will be

Bituminous pavement = ($45 / ft)(5,280 ft / min)

=$237,600

Sodded ditches = 2($150 / ft)(5,280 ft / min)

=$15,840 / mile

Pipe culverts = (3 culverts / mile)($5,280 / culverts)

=$7,200 / mile

Therefore the total capital investment will become

Total capital investment = $237,600+$15,840+$7.200

=$260,640 / mile

Calculate maintenance cost for design B

Annual cleaning of culvert = (3 culverts / mile)($225 / culvert)

=$675 / mile

Annual ditch maintenance = 2($150 / ft)($5,280 ft / min)

=$15,840 / mile

The annual pavement maintenance is given as $2,700 / mile.

Now calculate annual worth and its relation as shown below:

AW (i%) = R -E -CR(i%)

The annual worth in this case will become,

AW(6%)=-[$260,190+$260,640(P /F ,6%,10)](A/P , 6% ,20)-$9,215

= -$54,595 / mile

Now present worth will become

PW(6%)=-$260,190-$260,640(P /F ,6%,10)]-$19,215(P / A ,6%, 20)

= -$626,126 / mile


Related Solutions

A new highway is to be constructed. Design A calls for a concrete pavement costing​$90 per...
A new highway is to be constructed. Design A calls for a concrete pavement costing​$90 per foot with a 20​-year​  life;four paved ditches costing ​$5 per foot​ each; and four box culverts every​ mile, each costing ​$9,000 and having a 20​-year life. Annual maintenance will cost ​$1,700 per​ mile; the culverts must be cleaned every five years at a cost of​$350 each per mile. Design B calls for a bituminous pavement costing ​$45 per foot with a 10-year ​life;four sodded ditches...
Pavement Design: New pavement design is to be constructed in 2026. The new average daily traffic...
Pavement Design: New pavement design is to be constructed in 2026. The new average daily traffic for commercial vehicles on the opening day will be 1700. Use: Growth rate = 6% Subgrade CBR = 3% Design life = 20 years
Insight on: a) Highway drainage and Slope protection Design b) Highway Pavement Design, Materials and Construction...
Insight on: a) Highway drainage and Slope protection Design b) Highway Pavement Design, Materials and Construction & Equipment Utilization
The Dept. of Transportation is comparing two alternative pavement designs with the following cost characteristics. Determine...
The Dept. of Transportation is comparing two alternative pavement designs with the following cost characteristics. Determine the least expensive alternative with a method of your choice. i=5% per year compounded annually.   Construction Cost at year 0 Maintenance Cost from years 1-20 Year A B 0 $450,000 $700,000 1 2 3 $40,000 4 5 $50,000 6 $40,000 7 8 9 $40,000 10 $50,000 11 12 End of Service 13 14 15 $500,000 16 17 18 19 20 End of Service
Design a plain concrete mix required for 400mm deep RCC beam to be constructed in New...
Design a plain concrete mix required for 400mm deep RCC beam to be constructed in New Girls Hostel at GIK Institute (you can assume workability). The specified compressive strength is 32 MPa at 28 days. The standard deviation of the concrete producer is 3.0 MPa. Select nominal maximum-size coarse aggregate from following data Min. distance b/w two reinforcing bar is 40mm Min. distance b/w reinforcing bar and concrete surface (clear cover) is 42mm Thick of slab is 120mm Concrete is...
A bridge design firm is performing an economic analysis of two mutually exclusive designs for a...
A bridge design firm is performing an economic analysis of two mutually exclusive designs for a highway overpass. The steel girder option has an initial cost of $2.03 million, and the concrete option has an initial cost of $2.42 million. Every 25 years, the steel bridge must be painted at a cost of $420,000, and all other maintenance costs are the same for both options. The steel bridge is expected to last 50 years, and concrete bridge is expected to...
Contact Manufacturing, Inc is considering two alternative investment proposals. The first proposal Calls for a major...
Contact Manufacturing, Inc is considering two alternative investment proposals. The first proposal Calls for a major renovation of the company's manufacturing facility. The second involves replacing just a few obsolete pieces of equipment in the facility. The company will choose one project or the other this year, but it will not do both. The cash flows associated with each project appear below and the firm discounts project cash flows at 15%. Year Renovate Replace 0 -9,000,000 -2,400,000 1 3,000,000 2,000,000...
Cummins Engines, Inc. is considering two alternative investment proposals. The first proposal calls for investment in...
Cummins Engines, Inc. is considering two alternative investment proposals. The first proposal calls for investment in plant and equipment to produce a new alternative fuel engine. The second proposal calls for investment in plant and equipment to expand production of a current, successful diesel engine. Cummins will choose only of these project since they are for similar markets. Year New Line Expand Line 0 ($65,000,000) ($20,000,000) 1 $20,000,000 $11,000,000 2 $20,000,000 $10,000,000 3 $20,000,000 $8,000,000 4 $20,000,000 $0 5 $20,000,000...
Contract Manufacturing, Inc., is considering two alternative investment proposals. The first proposal calls for a major...
Contract Manufacturing, Inc., is considering two alternative investment proposals. The first proposal calls for a major renovation of the company’s manufacturing facility. The second involves replacing just a few obsolete pieces of equipment in the facility. The company will choose one project or the other but not both. The cash flows associated with each project appear below and the firm discounts project cash flow at 15%: Year: 0 ; 1 ; 2 ; 3 ; 4 ; 5 Renovate :...
Industrial Designs has been awarded a contract to design a label for a new wine produced...
Industrial Designs has been awarded a contract to design a label for a new wine produced by Lake View Winery. The company estimates that 150 hours will be required to complete the project. The firm’s three graphic designers available for assignment to this project are Lisa, a senior designer and team leader; David, a senior designer; and Sarah, a junior designer. Because Lisa has worked on several projects for Lake View Winery, management specified that Lisa must be assigned at...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT