In: Economics
A new highway is to be constructed with two alternative designs. Design A calls for a concrete pavement costing $90 per foot with a 20-year life; two paved ditches costing $3 per foot each; and three box culverts every mile, each costing $9,000 and having a 20-year life. Annual maintenance will cost $1,800 per mile; the culverts must be cleaned every five years at a cost of $450 each per mile. Design B calls for a bituminous pavement costing $45 per foot with a 10-year life, two sodded ditches costing $1.50 per foot each; and three pipe culverts every mile, each costing $2,250 and having a 10-year life. The replacement culverts will cost $2,400 each. Annual maintenance will cost $2,700 per mile; the culverts must be cleaned yearly at a cost of $225 each per mile; and the annual ditch maintenance will cost $1.50 per foot per ditch. Compare the two designs using equivalent worth per mile for a 20-year period. Find the most economical design if the MARR is 6% per year.
Answer:
Given that:
A new highway is to constructed with two alternative designs .
Start design A in which all components have a life of 20 years . Now the capital investment for this design will be
Concrete pavement = ($90 / ft)(5,280 ft / min)
= $475,200 / mile
Paved ditches = 2($3 / ft)(5,280 ft / min)
= $31,680 / mile
Box culverts = (3 culverts / mile)($9,000 / min)
= $27,000 / mile
Therefore the total capital investment will become,
Total capital investment = $475,200 +$31,680+$27,000
= $533,880 / mile
The design maintenance cost is given as $1,800.
With this periodic cleaning of culverts will become :
(3 culverts / mile)($450 / culverts) = $1,350 / mile
Now apply the AW formula:
AW (i%) = R -E -CR(i%)
The annual worth in this case will become,
AW(6%)=-$533,880(A /P ,6%,20)-$1,800-$1,350(A / F ,6%, 5)
= -$48,594 / mile
Now calculate the present worth of design A
PW(6%)=-$533,880-[$1,800+$1,350(A /F ,6%,5)](P / A ,6%, 20)
= -$557,273 / mile
Consider design B in which all components have life of 0 years.Now the capital investment for this design in zero year will be
Bituminous pavement = ($45 / ft)(5,280 ft / min)
=$237,600
Sodded ditches = 2($150 / ft)(5,280 ft / min)
=$15,840 / mile
Pipe culverts = (3 culverts / mile)($2,250 / culverts)
=$6,750 / mile
Therefore the total capital investment will become
Total capital investment = $237,600+$15,840+$6.750
=$260,190 / mile
Consider design B in which all components have end of years 10 years.Now the capital investment for this design in zero year will be
Bituminous pavement = ($45 / ft)(5,280 ft / min)
=$237,600
Sodded ditches = 2($150 / ft)(5,280 ft / min)
=$15,840 / mile
Pipe culverts = (3 culverts / mile)($5,280 / culverts)
=$7,200 / mile
Therefore the total capital investment will become
Total capital investment = $237,600+$15,840+$7.200
=$260,640 / mile
Calculate maintenance cost for design B
Annual cleaning of culvert = (3 culverts / mile)($225 / culvert)
=$675 / mile
Annual ditch maintenance = 2($150 / ft)($5,280 ft / min)
=$15,840 / mile
The annual pavement maintenance is given as $2,700 / mile.
Now calculate annual worth and its relation as shown below:
AW (i%) = R -E -CR(i%)
The annual worth in this case will become,
AW(6%)=-[$260,190+$260,640(P /F ,6%,10)](A/P , 6% ,20)-$9,215
= -$54,595 / mile
Now present worth will become
PW(6%)=-$260,190-$260,640(P /F ,6%,10)]-$19,215(P / A ,6%, 20)
= -$626,126 / mile