Question

In: Finance

A new highway is to be constructed. Design A calls for a concrete pavement costing​$90 per...

A new highway is to be constructed. Design A calls for a concrete pavement costing​$90 per foot with a 20​-year​  life;four paved ditches costing ​$5 per foot​ each; and four box culverts every​ mile, each costing ​$9,000 and having a 20​-year life. Annual maintenance will cost ​$1,700 per​ mile; the culverts must be cleaned every five years at a cost of​$350 each per mile. Design B calls for a bituminous pavement costing ​$45 per foot with a 10-year ​life;four sodded ditches costing ​$1.65 per foot​ each; and three pipe culverts every​ mile, each costing ​$2,100 and having a 10​-year life. The replacement culverts will cost ​$2,400 each. Annual maintenance will cost ​$2,600 per​ mile; the culverts must be cleaned yearly at a cost of ​$225 each per​ mile; and the annual ditch maintenance will cost ​$1.45 per foot per ditch. Compare the two designs on the basis of equivalent worth per mile for a 20​-year period. Find the most economical design on the basis of AW and PW if the MARR is 6​%per year.

Solutions

Expert Solution

1 mile=5280 feet

Design A

Total construction cost per mile=(90+5)*5280= $501600

Culvert Cost for each mile= 9000*4=$36000

Annual Maintenance Cost of highway= $1700 per mile for 20 year i.e. $19498.87 of Present Value.Calculation is given below:

The cleaning cost of culvert is $350 every five year. Present Value is $603.02

Year Culvert Cleaning Cost Present Value (i.e. Cost/1.06^year)
5 $                       350.00 $                                                261.54
10 $                       350.00 $                                                195.44
15 $                       350.00 $                                                146.04
Total $                                                603.02

So, Present Value for total cost of design A for 20 year per mile= 603.02+19498.87+501600+36000=$557701.9

Design B

Construction cost oh highway per mile=(45+1.65)*5280=$246312

Culvert making cost per mile=2100*3=$6300

Annual maintenance for highway and ditch per mile= 2600+1.45*5280=$10256

Annual Culvert cleaning cost per mile is= 225*3=$675

So, total annual maintenance cost for design B= (10256+675)=$10931 for each of the 10 year i.e. $80453.11

PMT 10931
rate 6%
nper 10
PV ($80,453.11)

Total present Value of cost for Design B per mile for 10 year= (246312+6300+80453.11)=$333065.1

Now, after 10 year you need another $33065.1 to last for another 10 year ignoring inflation

So, for 20 present value of 20 year equivalent cost for design B= 333065.1+333065.1/1.06^10=$519046.9

As the present value of 20 year equivalent cost for Design B is lower than design A, design B should be accepted.

The AW for Design A and Design B is $557701.9/20=$27885.1 and 519046/20=25952.35 respectively

Design B is most economical.


Related Solutions

A new highway is to be constructed with two alternative designs. Design A calls for a...
A new highway is to be constructed with two alternative designs. Design A calls for a concrete pavement costing $90 per foot with a 20-year life; two paved ditches costing $3 per foot each; and three box culverts every mile, each costing $9,000 and having a 20-year life. Annual maintenance will cost $1,800 per mile; the culverts must be cleaned every five years at a cost of $450 each per mile. Design B calls for a bituminous pavement costing $45...
Pavement Design: New pavement design is to be constructed in 2026. The new average daily traffic...
Pavement Design: New pavement design is to be constructed in 2026. The new average daily traffic for commercial vehicles on the opening day will be 1700. Use: Growth rate = 6% Subgrade CBR = 3% Design life = 20 years
Insight on: a) Highway drainage and Slope protection Design b) Highway Pavement Design, Materials and Construction...
Insight on: a) Highway drainage and Slope protection Design b) Highway Pavement Design, Materials and Construction & Equipment Utilization
How the pavement rigid design will be affected if the modulus of elasticity of concrete increased?
How the pavement rigid design will be affected if the modulus of elasticity of concrete increased?
Design a plain concrete mix required for 400mm deep RCC beam to be constructed in New...
Design a plain concrete mix required for 400mm deep RCC beam to be constructed in New Girls Hostel at GIK Institute (you can assume workability). The specified compressive strength is 32 MPa at 28 days. The standard deviation of the concrete producer is 3.0 MPa. Select nominal maximum-size coarse aggregate from following data Min. distance b/w two reinforcing bar is 40mm Min. distance b/w reinforcing bar and concrete surface (clear cover) is 42mm Thick of slab is 120mm Concrete is...
Design the concrete mix according to the following conditions: Design Environment Pavement slab, Bozeman, Montana (cold...
Design the concrete mix according to the following conditions: Design Environment Pavement slab, Bozeman, Montana (cold climate) Required design strength = 3000 psi Slab thickness = 12 in Statistical data indicate a standard deviation of compressive strength of 250 psi is expected (more than 30 samples) Only air entrainer is allowed. Available materials Air entrainer: Manufacture specification is 0.15 fl oz/1% air/100lb cement Coarse aggregate: 2in. nominal maximum size, crushed stone Bulk oven dry specific gravity = 2.573, absorption =...
You have to a design a flexible highway pavement with soaked CBR value of soil subgrade...
You have to a design a flexible highway pavement with soaked CBR value of soil subgrade equal to 4%. Draw a typical cross-section of the pavement as considered currently worldwide.  
A Portland Cement Concrete (rigid) pavement is to be designed using AASHTO empirical design method. The...
A Portland Cement Concrete (rigid) pavement is to be designed using AASHTO empirical design method. The pavement should have an 8" granular sub-base having elastic modulus (Esb) of 50x103 psi. The resilient modulus of the subgrade is 5000 psi, and lying just 5 feet above rock strata (bed rock). (a) Determine the design k value, assuming loss of support factor (LSF) of 2. (b) Use the k value obtained from (a) to determine the thickness of the rigid pavement.   Assume...
A concrete mix design is needed for a residential street paving project in Detroit, Michigan. Pavement...
A concrete mix design is needed for a residential street paving project in Detroit, Michigan. Pavement thickness is 8”, unreinforced, subjected to freezing and thawing and deicing agents are anticipated. The specified compressive strength is 4000 psi. Assume both Fine Aggregate (FA) and Coarse Aggregate (CA) are in saturated surface dry condition. Specific Gravity of Fine Aggregate (FA) = 2.71 Fineness Modulus (FM) of Fine Aggregate (FA) = 2.70 Specific Gravity of Coarse Aggregate (CA) = 2.65 Bulk Density of...
Design of Rigid pavement for new construction - USING AASHTO METHOD
Design of Rigid pavement for new construction - USING AASHTO METHOD
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT