In: Accounting
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:
2021 | 2022 | 2023 | |||||||
Cost incurred during the year | $ | 2,550,000 | $ | 4,250,000 | $ | 1,870,000 | |||
Estimated costs to complete as of year-end | 5,950,000 | 1,700,000 | 0 | ||||||
Billings during the year | 2,050,000 | 4,750,000 | 3,200,000 | ||||||
Cash collections during the year | 1,825,000 | 4,100,000 | 4,075,000 | ||||||
Westgate recognizes revenue over time according to percentage of completion.
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.
2021 2022 2023
Revenue ______ _______ ________
Gross P _______ _______ ________
2-a. In the journal below, complete the
necessary journal entries for the year 2021 (credit "Various
accounts" for construction costs incurred).
2-b. In the journal below, complete the necessary
journal entries for the year 2022 (credit "Various accounts" for
construction costs incurred).
2-c. In the journal below, complete the necessary
journal entries for the year 2023 (credit "Various accounts" for
construction costs incurred).
3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract.
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.
2021 | 2022 | 2023 | |||||||
Costs incurred during the year | $ | 2,550,000 | $ | 3,825,000 | $ | 3,225,000 | |||
Estimated costs to complete as of year-end | 5,950,000 | 3,125,000 | 0 | ||||||
2021 2022 2023
Revenue ______ _______ ________
Gross P _______ _______ ________
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.
2021 | 2022 | 2023 | |||||||
Costs incurred during the year | $ | 2,550,000 | $ | 3,825,000 | $ | 3,975,000 | |||
Estimated costs to complete as of year-end | 5,950,000 | 4,150,000 | 0 | ||||||
2021 2022 2023
Revenue ______ _______ ________
Gross P _______ _______ ________
Answer :
Particulars | 2021 | 2022 | 2023 | ||||||
Cost incurred during the year | $ | 2,550,000 | $ | 4,250,000 | $ | 1,870,000 | |||
Estimated costs to complete as of year-end | 5,950,000 | 1,700,000 | 0 | ||||||
Billings during the year | 2,050,000 | 4,750,000 | 3,200,000 | ||||||
Cash collections during the year | 1,825,000 | 4,100,000 | 4,075,000 |
Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.
2021 2022 2023
Answer :
Particulars | 2021 | 2022 | 2023 |
% of completion |
=25,50,000 / 59,50,000 =42.86% |
=42,50,000 / 59,50,000 = 71.42% |
=18,70,000 /59,50,000 = 31.43% To be considered for current year = (100 - 71.42) = 28.58% (this adjustment is done because total value exceeded 100%) |
Revenue to be recognized for the year |
=100,00,000*42.86% =4,28,60,000 |
=100,00,000*71.42% =7,14,20,000 |
=100,00,000*28.58% =2,85,80,000 |
Journal Entries :
2021
Construction in progress Dr. 25,50,000
Bank a/c Cr. 25,50,000
(Cost incurred for the contract in the year)
Accounts receivable Dr. 20,50,000
To Billings on construction contract Cr. 20,50,000
(Billimgs during the year)
Bank A/c Dr 18,25,500
Accounts receivable Cr 18,25,000
(Cash collections during the year)
Accounts receivable a/c Dr 18,25,000
Unbilled contracts receivable a/c Dr 4,10,35,000
Contract revenue earned a/c Cr. 4,28,60,000
(Revenue recognized for the year)
Journal Entries :
2022
Construction in progress Dr. 42,50,000
Bank a/c Cr. 42,50,000
(Cost incurred for the contract in the year)
Accounts receivable Dr. 47,50,000
To Billings on construction contract Cr. 47,50,000
(Billimgs during the year)
Bank A/c Dr 41,00,000
Accounts receivable Cr 41,00,000
(Cash collections during the year)
Accounts receivable a/c Dr 47,50,000
Unbilled contracts receivable a/c Dr 6,66,70,000
Contract revenue earned a/c Cr. 7,14,20,000
(Revenue recognized for the year)
Journal Entries :
2023
Construction in progress Dr. 18,70,000
Bank a/c Cr. 18,70,000
(Cost incurred for the contract in the year)
Accounts receivable Dr. 32,00,000
To Billings on construction contract Cr. 32,00,000
(Billimgs during the year)
Bank A/c Dr 40,75,500
Accounts receivable Cr 4075,000
(Cash collections during the year)
Accounts receivable a/c Dr 4075,000
Unbilled contracts receivable a/c Dr 2,45,05,000
Contract revenue earned a/c Cr. 2,85,80,000
(Revenue recognized for the year)