Question

In: Accounting

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,072,000 $ 2,738,000 $ 2,849,000 Estimated costs to complete as of year-end 5,328,000 2,590,000 0 Billings during the year 2,160,000 2,650,000 5,190,000 Cash collections during the year 1,880,000 2,700,000 5,420,000 Westgate recognizes revenue over time according to percentage of completion. 3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.)

Solutions

Expert Solution

Answer:

Balance Sheet (Partial) 2021 2022
Current Assets:
Accounts Receivable 280,000 230,000
Construction in progress 2,800,000 6,500,000
Less: Billings 2,160,000 4,810,000
Costs and profit in excess of billings 640,000 1,690,000
Current Liabilities:
Billing in excess of cost and profit

Workings:

2021 2022
Cost incurred (cummulative) 2,072,000 4,810,000
Estimated costs to complete 5,328,000 2,590,000
Total Cost 7,400,000 7,400,000
Contract price 10,000,000 10,000,000
Profit 2,600,000 2,600,000
Percentage of completion 28% 65%
Profit to be recognized 728,000 962,000
Balance Sheet (Partial) 2021 2022
Current Assets:
Accounts Receivable 2,160,000-1,880,000 2,160,000-1,880,000+2,650,000-2,700,000
Construction in progress 2,072,000+728,000 2,738,000+962,000+(2,072,000+728,000)
Less: Billings 2,160,000 2,160,000+2,650,000

Please rate positively if this helped you,

All the best !


Related Solutions

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to complete as of year-end 5,616,000 2,376,000 0 Billings during the year 1,200,000 3,624,000 5,176,000 Cash collections during the year 1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,100,000 $ 3,150,000 $ 2,475,000 Estimated costs to complete as of year-end 5,400,000 2,250,000 0 Billings during the year 2,150,000 3,100,000 4,750,000 Cash collections during the year 1,875,000 3,100,000 5,025,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,471,000 $ 4,005,000 $ 1,566,400 Estimated costs to complete as of year-end 5,429,000 1,424,000 0 Billings during the year 2,900,000 4,576,000 2,524,000 Cash collections during the year 2,700,000 4,500,000 2,800,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows. 2018 2019 2020 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0 Billings during the year 2,170,000 2,502,000 5,328,000 Cash collections during the year 1,885,000 2,600,000 5,515,000 5. Calculate the amount of revenue and...
In 2021, the Westgate Construction company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows. 2018 2019 2020 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0 Billings during the year 2,170,000 2,502,000 5,328,000 Cash collections during the year 1,885,000 2,600,000 5,515,000 3. Complete the information required below to...
in 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
in 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0 Billings during the year 2,170,000 2,502,000 5,328,000 Cash collections during the year 1,885,000 2,600,000 5,515,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the year 1,815,000 3,900,000 4,285,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,072,000 $ 2,738,000 $ 2,849,000 Estimated costs to complete as of year-end 5,328,000 2,590,000 0 Billings during the year 2,160,000 2,650,000 5,190,000 Cash collections during the year 1,880,000 2,700,000 5,420,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,072,000 $ 2,738,000 $ 2,849,000 Estimated costs to complete as of year-end 5,328,000 2,590,000 0 Billings during the year 2,160,000 2,650,000 5,190,000 Cash collections during the year 1,880,000 2,700,000 5,420,000 Westgate recognizes revenue over time according to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT