Question

In: Accounting

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:

2021 2022 2023
Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000
Estimated costs to complete as of year-end 5,600,000 2,000,000 0
Billings during the year 2,000,000 4,000,000 4,000,000
Cash collections during the year 1,800,000 3,600,000 4,600,000


Assume that Westgate Construction’s contract with Santa Clara County does not qualify for revenue recognition over time.

Required:
1.
Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.
2-a.In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred).
2-b.In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs incurred).
3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract.
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.

2021 2022 2023
Cost incurred during the year $ 2,400,000 $ 3,800,000 $ 3,200,000
Estimated costs to complete as of year-end 5,600,000 3,100,000 0


5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.

2021 2022 2023
Cost incurred during the year $ 2,400,000 $ 3,800,000 $ 3,900,000
Estimated costs to complete as of year-end 5,600,000 4,100,000 0

Solutions

Expert Solution

1)

Year Revenue Recognized Gross Profit Recognised
2021 3000000 600000
2022 4500000 900000
2023 2500000 300000

2a) Journal Entries for 2021:

Date General Journal Debit Credit
2021 Construction In progress 2400000
Materials, Cash, Payables 2400000
2021 Accounts Receivables 2000000
Billings on Construction Contract 2000000
2021 Cash 1800000
Accounts Receivables 1800000
2021 Construction In Progress 600000
Construction Exp. 2400000
Revenue from Contract 3000000


2b) Journal Entries for 2022:

Date General Journal Debit Credit
2022 Construction In progress 3600000
Materials, Cash, Payables 3600000
2022 Accounts Receivables 4000000
Billings on Construction Contract 4000000
2022 Cash 3600000
Accounts Receivables 3600000
2022 Construction In Progress 900000
Construction Exp. 3600000
Revenue from Contract 4500000

2c) Journal Entries for 2023:

Date General Journal Debit Credit
2023 Construction In progress 2200000
Materials, Cash, Payables 2200000
2023 Accounts Receivables 4000000
Billings on Construction Contract 4000000
2023 Cash 4600000
Accounts Receivables 4600000
2023 Construction In Progress 300000
Construction Exp. 2200000
Revenue from Contract 2500000

3) Partial Balance sheet for 2020 and 2021:

Balance Sheet Partial 2021 2022
Current Assets:
Accounts Receivables 200000 600000
Construction in Progress 3000000 7500000
Less: Billings -2000000 -6000000
Costs and Profits in excess of billings 1000000 1500000
Current Liabilities:
Working for Accounts Receivables: 2021 2022
Beginning Balance 0 200000
Billings 2000000 4000000
Less: Collections -1800000 -3600000
Closing Balance 200000 600000

4)

Year Revenue Recognized Gross Profit Recognised
2021 3000000 600000
2022 3666667 -133333
2023 3333333 133333

Working Note:

% of Completion
Actual Costs to date / Total Estimated costs = % of completion
Actual Costs to date Estimated total costs
2021 2400000 8000000 30%
2022 6200000 9300000 67%
2023 9400000 9400000 100%

5)

Year Revenue Recognized Gross Profit Recognised
2021 3000000 600000
2022 3019417 -780583
2023 3980583 80583

Working Note:

% of Completion
Actual Costs to date / Total Estimated costs = % of completion
Actual Costs to date Estimated total costs
2021 2400000 8000000 30%
2022 6200000 10300000 60%
2023 10100000 10100000 100%

Related Solutions

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to complete as of year-end 5,616,000 2,376,000 0 Billings during the year 1,200,000 3,624,000 5,176,000 Cash collections during the year 1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,100,000 $ 3,150,000 $ 2,475,000 Estimated costs to complete as of year-end 5,400,000 2,250,000 0 Billings during the year 2,150,000 3,100,000 4,750,000 Cash collections during the year 1,875,000 3,100,000 5,025,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,471,000 $ 4,005,000 $ 1,566,400 Estimated costs to complete as of year-end 5,429,000 1,424,000 0 Billings during the year 2,900,000 4,576,000 2,524,000 Cash collections during the year 2,700,000 4,500,000 2,800,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows. 2018 2019 2020 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0 Billings during the year 2,170,000 2,502,000 5,328,000 Cash collections during the year 1,885,000 2,600,000 5,515,000 5. Calculate the amount of revenue and...
In 2021, the Westgate Construction company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows. 2018 2019 2020 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0 Billings during the year 2,170,000 2,502,000 5,328,000 Cash collections during the year 1,885,000 2,600,000 5,515,000 3. Complete the information required below to...
in 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
in 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0 Billings during the year 2,170,000 2,502,000 5,328,000 Cash collections during the year 1,885,000 2,600,000 5,515,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the year 1,815,000 3,900,000 4,285,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,072,000 $ 2,738,000 $ 2,849,000 Estimated costs to complete as of year-end 5,328,000 2,590,000 0 Billings during the year 2,160,000 2,650,000 5,190,000 Cash collections during the year 1,880,000 2,700,000 5,420,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,072,000 $ 2,738,000 $ 2,849,000 Estimated costs to complete as of year-end 5,328,000 2,590,000 0 Billings during the year 2,160,000 2,650,000 5,190,000 Cash collections during the year 1,880,000 2,700,000 5,420,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,072,000 $ 2,738,000 $ 2,849,000 Estimated costs to complete as of year-end 5,328,000 2,590,000 0 Billings during the year 2,160,000 2,650,000 5,190,000 Cash collections during the year 1,880,000 2,700,000 5,420,000 Westgate recognizes revenue over time according to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT