Question

In: Civil Engineering

QUESTION 1 (30%). Concrete is required for a reinforced concrete building. The 28-day target mean (cube)...

QUESTION 1 (30%). Concrete is required for a reinforced concrete building. The 28-day target mean (cube) compressive strength should be 40 N/mm2. Use the BRE method to determine the concrete mix proportions for 0.05 m3 concrete (BRE tables and figures are attached below for each stage). (30%) The properties of materials and site conditions are as follows: - Cement strength class: 42.5 - Slump required: 50 mm - Coarse aggregate: crushed 20 mm (use 1:2 proportions for 10 mm and 20 mm combination); Fine aggregate: uncrushed (40% passes 600 micron sieve) - Minimum allowable cement content: 300 kg/m3; Maximum allowable cement content: 450 kg/m3 - Maximum allowable free w/c ratio: 0.55 - Relative density of aggregates (SSD): 2.65 - Free Moisture content for Coarse Aggregate: +1.0% - Free moisture content for Fine Aggregate: +1.0%

1.1 characterisitic compressive strength (MPa) and age (days): Proportion defective (%)

Solutions

Expert Solution

Complete mix design using BRE method for given specifications is shown below.

Mix quantities for 1m3 and trial mix is tabulated at the end.


Related Solutions

A concrete mix was designed for thin core walls in a tall building. A 28-day strength...
A concrete mix was designed for thin core walls in a tall building. A 28-day strength of 32 MPa is required. The exposure classification for durability purposes is for B2 and C. One hundred laboratory test results on the controlling mix show a standard deviation of 5.3 MPa (k=1.65). The density of uncrushed coarse aggregate is 2850 kg/m3 and its dry rodded density is 1600 kg/m3 and the maximum size to be used is 10 mm. The density of fine...
Describe 2 advantages and 2 disadvantages for masonry building,reinforced concrete building and steel structural building,respectively
Describe 2 advantages and 2 disadvantages for masonry building,reinforced concrete building and steel structural building,respectively
A concrete mix is required for reinforced concrete wave breaker at seashore where frequent mild freezing...
A concrete mix is required for reinforced concrete wave breaker at seashore where frequent mild freezing and thawing is dominant. A specified compressive strength of 25 MPa is required at the age of 28 days, and the size of the section and reinforcement dictate using a maximum aggregate size of 19 mm. The company had no history of testing concrete used. The coarse aggregate meets the ASTM grading requirements. It has absorption of 2%, a BSG (D) of 2.70 and...
A concrete mix is required for reinforced concrete wave breaker at seashore where frequent mild freezing...
A concrete mix is required for reinforced concrete wave breaker at seashore where frequent mild freezing and thawing is dominant. A specified compressive strength of 25 MPa is required at the age of 28 days, and the size of the section and reinforcement dictate using a maximum aggregate size of 19 mm. The company had no history of testing concrete used. The coarse aggregate meets the ASTM grading requirements. It has absorption of 2%, a BSG (D) of 2.70 and...
A concrete mix is required for reinforced concrete wave breaker at seashore where frequent mild freezing...
A concrete mix is required for reinforced concrete wave breaker at seashore where frequent mild freezing and thawing is dominant. A specified compressive strength of 25 MPa is required at the age of 28 days, and the size of the section and reinforcement dictate using a maximum aggregate size of 19 mm. The company had no history of testing concrete used. The coarse aggregate meets the ASTM grading requirements. It has absorption of 2%, a BSG (D) of 2.70 and...
A concrete mix is required for reinforced concrete wave breaker at seashore where frequent mild freezing...
A concrete mix is required for reinforced concrete wave breaker at seashore where frequent mild freezing and thawing is dominant. A specified compressive strength of 25 MPa is required at the age of 28 days, and the size of the section and reinforcement dictate using a maximum aggregate size of 19 mm. The company had no history of testing concrete used. The coarse aggregate meets the ASTM grading requirements. It has absorption of 2%, a BSG (D) of 2.70 and...
A concrete mix was designed for a concrete road pavement (i.e. heavy mass concrete). A 28-day...
A concrete mix was designed for a concrete road pavement (i.e. heavy mass concrete). A 28-day strength of 26 MPa is required. The exposure classification for durability purposes is C. One hundred laboratory test results on the controlling mix show a standard deviation of 5.3 MPa (k=1.65). The density of crushed coarse aggregate is 2850 kg/m3 and its dry rodded density is 1600 kg/m3 and the maximum size to be used is 10 mm. The specific gravity of fine aggregate...
Question 1) In the Reinforced concrete answer all of these: a) what the main difference between...
Question 1) In the Reinforced concrete answer all of these: a) what the main difference between simply support slab and continuous (fixed) slab and which one is the better? b) what the difference between one-way and two- way slab and which of them better to use? c) why we use small L for the slab in Mu formula (Mu= Wu * L^2 / 8)? d) how the load transfer from the slab to foundation? e) is the beam ductile member...
The involves building a 80 feet highX80X100 foot in dimension reinforced concrete structure with 3 -...
The involves building a 80 feet highX80X100 foot in dimension reinforced concrete structure with 3 - foot thick walls in the river that extends to twenty feet below river bottom in soft clay. Water depth at the location is 30 feet. The structure starts at 200 feet from the river edge where land is about 5 feet above the river level.The project needs to be completed in 800 days. Determine the amount and types of equipment you feel should be...
I received a model of a reinforced concrete office building design in Revit from a coworker,...
I received a model of a reinforced concrete office building design in Revit from a coworker, and I’d like to get started on some of the sheets that will make up the document sets for the project. What are some elements I should consider including in my sheets?