Question

In: Civil Engineering

1) A hydraulic shovel with a bottom-dump bucket with a heaped bucket volume of 10 m3...

1) A hydraulic shovel with a bottom-dump bucket with a heaped bucket volume of 10 m3 is excavating tough clay. The swing angle is 103 degrees and the job efficiency is 0.85 + (8/100). Calculate the shovel production in BCM.

2) Estimate the time required to load 408 m3 of gravel from a stockpile into trucks using a clamshell having a heaped bucket capacity of 0.57 m3. Estimated cycle time is 20s. Swing depth factor = 1.0. Job efficiency is estimated to be 58 min/h.

3) A small hydraulic excavator will be used to dig a trench in hard clay. The trench size is 0.76 m wide by 1.50 + (58/100) m deep. The excavator bucket available is 0.76 m wide and has a heaped capacity of 0.50 + (8/100) m3. The maximum digging depth of the excavator is 4.90 m. The average swing angle is expected to be 75° and the job efficiency is 78 %.  Estimate the hourly trench production in BCM and in linear meters of trench.

Solutions

Expert Solution


Related Solutions

i: A hydraulic shovel with a bottom-dump bucket with a heaped bucket volume of 5 m3...
i: A hydraulic shovel with a bottom-dump bucket with a heaped bucket volume of 5 m3 is excavating tough clay. The swing angle is 47 degrees and the job efficiency is 0.86. Calculate the shovel production in BCM ii: Estimate the time required to load 452 m3 of gravel from a stockpile into trucks using a clamshell having a heaped bucket capacity of 0.57 m3. The estimated cycle time is 20s. Swing depth factor = 1.0. Job efficiency is estimated...
A shovel with a 3-cy heaped capacity bucket is loading well blasted rock on a highway...
A shovel with a 3-cy heaped capacity bucket is loading well blasted rock on a highway project. The average face height is 22 ft. The shovel has a maximum rated digging height of 30 ft. Most of the cut will require a 140-degree swing of the shovel to load the haul units. Use efficiency factor 45-minues per hour. What is an aggressive production estimate in bank cubic yards? Show all the calculations
A dump truck with a heaped capacity of 10 yd3 is used to dispose of excavated...
A dump truck with a heaped capacity of 10 yd3 is used to dispose of excavated material at a dump site 3.5 mile away from the job site. The average velocity of the dump truck is 40 kph. The dump time is 30 seconds, load time is 40 seconds. Assume a 50 minutes/hour efficiency, determine the production of the dump truck to complete the 12’ deep excavation of 100’x200’ size building footprint?
Given the following: Bucket volume of loader: 3.6 L m3 (loose cubic meters) Loader cycle: 0.42...
Given the following: Bucket volume of loader: 3.6 L m3 (loose cubic meters) Loader cycle: 0.42 min Truck capacity: 11.5 L m3 Truck traveling time with load 2.28 min Truck maneuvering for tipping and tipping time 0.65 min Truck return time 1.18 min Truck maneuvering for loading 0.40 min Planned activities (lunch, breaks etc…) 0.64 min Waiting time at loader (per cycle) 0.50 min Conversation with supervisor (per cycle) 0.25 min Other cycle time affecting machine performance 0.75 min Swell...
Question 1 Calculate the Hydraulic Radius for a trapezoidal channel that has a bottom width of...
Question 1 Calculate the Hydraulic Radius for a trapezoidal channel that has a bottom width of 4 feet, side slopes, s = 20, a Manning’s n value of 0.012, and bottom slope of 1.5%, and a depth of flow of 1 foot. a. 0.54 ft b. 1.3 ft c. 2.1 ft d. 2.9 ft e. 3.7 ft 2 points Question 2 A trapezoidal channel that has a bottom width of 4 feet, side slopes 2:1 (H:V) and bottom slope of...
A rectangular storage container with an open top is to have a volume of 10 m3....
A rectangular storage container with an open top is to have a volume of 10 m3. The length of this base is twice the width. Material for the base costs $10 per square meter. Material for the sides costs $6 per square meter. Find the cost of materials for the cheapest such container. (Round your answer to the nearest cent.)
A CM basin with a volume of 475 m3 receives a flow of 2000 m3 d−1....
A CM basin with a volume of 475 m3 receives a flow of 2000 m3 d−1. The basin has a dead volume of 42 m3. Find the effluent tracer curve if a mass of 5 g of tracer is added instantaneously to the influent. Also plot the effluent tracer curve for the reactor without dead volume.
1a. A container of volume 3.2 × 10-6 m3 is filled with helium gas at a...
1a. A container of volume 3.2 × 10-6 m3 is filled with helium gas at a pressure of 5.1 × 105 Pa and temperature 320 K. Assume that this sample of helium gas behaves as an ideal gas. The molar mass of helium is 4.0 g mol-1. Show that the mass of a helium atom is 6.6 × 10-27 kg. 1b. Estimate the average speed of the helium atoms in the container. 1c. Show that the number of helium atoms...
Ammonia is initially at a temperature of -10° C and a specific volume of 0.07 m3/kg....
Ammonia is initially at a temperature of -10° C and a specific volume of 0.07 m3/kg. The ammonia undergoes an isobaric expansion to a final specific volume of 0.22 m3/kg. Evaluate the specific work done on the ammonia in kJ/kg and the specific heat transfer to the ammonia in kJ/kg. Neglect changes in kinetic energy and potential energy. Carbon dioxide is contained in a piston-cylinder assembly with an initial pressure and temperature of 8 lbf/in2 and 100° F, respectively. The...
10 kg of air occupying a cylinder volume of 0.28 m3 is allowed to expand isentropically...
10 kg of air occupying a cylinder volume of 0.28 m3 is allowed to expand isentropically behind a piston to a pressure of 30 bar. The air is then heated at a constant volume. Finally, the air is cooled at a constant pressure back to its initial conditions. The initial pressure is 60 bar. Calculate the change in entropy, the net work done and the net heat flow. Sketch the cycle on the p‐v and T‐s diagrams.