Question

In: Civil Engineering

A shovel with a 3-cy heaped capacity bucket is loading well blasted rock on a highway...

A shovel with a 3-cy heaped capacity bucket is loading well blasted rock on a highway project. The
average face height is 22 ft. The shovel has a maximum rated digging height of 30 ft. Most of the cut will
require a 140-degree swing of the shovel to load the haul units. Use efficiency factor 45-minues per hour.
What is an aggressive production estimate in bank cubic yards? Show all the calculations

Solutions

Expert Solution

Given :- • Capacity of shovel bucket = 3- cy;

• The average face height = 22 ft;

• Maximum rated digging height of shovel = 30 ft ;

• Swing of the shovel = 140° ;

• Efficiency factor = 45 min per hour;

• Shovel bucket is loaded with well-blasted rock of highway project.

To find :- Production of shovel in bank cubic yards (bcy)

Solution:- The whole solution is shown in below images. The following steps are followed to calculate required production in (bcy per hour).

1. Step 1: Calculate optimum height = 0.5 times the maximum rated digging height = 0.5 × 30 = 15 ft

2. Step 2: Find Fill factors for front shovel buckets according to the material type given which is loaded into the bucket. Here, well-blasted rock material is used, for which fill factor is between 100 to 110%. Take Fill factor = 100%.

3. Step 3: Find Cycle Time according to the 3-cy capacity bucket of shovel. Cycle time is calculated by the equation given as:- Cycle time = Load + Swing loaded + Dump load + Swing empty.

For 3-cy capacity bucket, Load bucket = 9sec; swing loaded = 4 sec; Dump load = 4sec; Swing empty = 4sec

Cycle time = 9+4+4+4 = 21 sec = 0.35 min.

4. Step 4: Calculate ideal production (lcy/hr) which is equal to multiplication of fill factor with the capacity of shovel bucket (lcy) which is divided by the cycle time(hr).

Ideal production = (60/0.35) × 3 × 1.0 = 514 lcy/hr

5. Step 5: Calculate Percent Optimum height which is found out by dividing average face height by the optimum height calculated in step 1.

Percent optimum height = 22/15 = 1.47 = 147%

6. Step 6: Calculate height swing factor by interpolation which is shown in below images. Height swing factor is dependent on angle of swing and percent optimum height (%). The obtained height swing factor for 140° swing angle and at percent optimum height of 147% is 0.735.

7. Step 7: Calculate adjusted Ideal production by multiplying the height swing factor with the ideal production calculated in step 4.

Adjusted Ideal Production = 514 × 0.735 = 377.79 lcy/hr

8. Step 8: Calculate percent swell which depends on the material type used to load the shovel bucket. For well-blasted rock, the value of percent swell = 60% = 0.6

9. Step 9: Estimate the production in (bcy/hr) calculated by dividing the Adjusted Ideal production (obtained in step 7) by the ( 1 + percent swell).

Production = 377.79 / (1 + 0.6) = 236.12 bcy/hr.

10. Step 10: Given efficiency factor = 45min per hour.

Final production is calculated by multiplying the efficiency factor with the production (obtained in step 9).

Production (bcy) = (45/60) × 236.12 = 177.09 bcy/hr

The required value of production in bank cubic yards in 177.09 bcy/hr.


Related Solutions

1) A hydraulic shovel with a bottom-dump bucket with a heaped bucket volume of 10 m3...
1) A hydraulic shovel with a bottom-dump bucket with a heaped bucket volume of 10 m3 is excavating tough clay. The swing angle is 103 degrees and the job efficiency is 0.85 + (8/100). Calculate the shovel production in BCM. 2) Estimate the time required to load 408 m3 of gravel from a stockpile into trucks using a clamshell having a heaped bucket capacity of 0.57 m3. Estimated cycle time is 20s. Swing depth factor = 1.0. Job efficiency is...
i: A hydraulic shovel with a bottom-dump bucket with a heaped bucket volume of 5 m3...
i: A hydraulic shovel with a bottom-dump bucket with a heaped bucket volume of 5 m3 is excavating tough clay. The swing angle is 47 degrees and the job efficiency is 0.86. Calculate the shovel production in BCM ii: Estimate the time required to load 452 m3 of gravel from a stockpile into trucks using a clamshell having a heaped bucket capacity of 0.57 m3. The estimated cycle time is 20s. Swing depth factor = 1.0. Job efficiency is estimated...
A truck will haul an average load of 15 cy, heaped capacity, and loose measure per...
A truck will haul an average load of 15 cy, heaped capacity, and loose measure per load. Use average values of swell factors in Table 7.3 on p. 131 of your textbook to determine the volume of the truck in bank measure when the material is sand, ordinary earth, dense clay, and well-blasted rock. Then, using an Excel spreadsheet, determine the number of trucks required to move material in the following scenario: A project requires 40,000 cy of compacted fill...
A load trucks is using a hoe equipped with a special 3½ cy light weight bucket....
A load trucks is using a hoe equipped with a special 3½ cy light weight bucket. Working efficiency is a 45 min-hr efficiency. The material is a sandy clay, 2,600 lb./lcy. The digging face will have an average height of 60% of max. digging depth and the angle of swing will always be less than 60º. The round-trip time of either truck, exclusive of load time, is 5 minutes Consider 2 truck sizes • 18 lcy and 26 lcy. •...
capacity of a 1-km section of northbound Highway 3 located on a 3.5% upgrade. The highway...
capacity of a 1-km section of northbound Highway 3 located on a 3.5% upgrade. The highway has three 3.5m-wide lanes in one direction with no lateral obstruction within 5m of the pavement edges. The ideal (base) free-flow speed is 100 km/hour. You observed that percentages of cars and truck are 90% and 10%, respectively (no RVs). A weekday peak hour volume is 4320 vehicles, with 1200 vehicles arriving in the most congested 15-minute period. Since a majority of drivers are...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT