Question

In: Civil Engineering

i: A hydraulic shovel with a bottom-dump bucket with a heaped bucket volume of 5 m3...

i: A hydraulic shovel with a bottom-dump bucket with a heaped bucket volume of 5 m3 is excavating tough clay. The swing angle is 47 degrees and the job efficiency is 0.86. Calculate the shovel production in BCM

ii: Estimate the time required to load 452 m3 of gravel from a stockpile into trucks using a clamshell having a heaped bucket capacity of 0.57 m3. The estimated cycle time is 20s. Swing depth factor = 1.0. Job efficiency is estimated to be 51min/h.

iii: A small hydraulic excavator will be used to dig a trench in hard clay. The trench size is 0.76 m wide by 1.52m deep. The excavator bucket available is 0.76 m wide and has a heaped capacity of 0.51m3. The maximum digging depth of the excavator is 4.90 m. The average swing angle is expected to be 75° and the job efficiency is 71 %. Estimate the hourly trench production in BCM and in linear meters of a trench.

Solutions

Expert Solution

Ans i) We know,  

Shovel produuction (BCM/hr) = C x S x V x B x E x L

where, C = cycle per hour

S = swing factor

V = heaped bucked volume = 5

B = bucket fill factor

E = job efficiency = 0.86

L = Load factor = 0.77 for clay

According to table 3-6, for tough clay and bottom dump shovel, cycle per hour (C) = 140

For swing angle 47 degree, S = 1.14

For clays, fill factor (B) = 0.95

Putting values,

=> Production = 140 x 1.14 x 5 x 0.95 x 0.86 x 0.77

=> Production = 502 BCM/hr

.

Ans ii) We know,

Produuction (LCM/hr) = C x S x V x B x E

where, C = cycle per hour = 3600 sec / 20 sec = 180

S = swing factor = 1

V = heaped bucked volume = 0.57

B = bucket fill factor = 0.70 for gravel

E = job efficiency = 0.51 min/hr or 51 min/60 min = 0.85

Putting values,

  Production (LCM/hr) = 180 x 1 x 0.57 x 0.70 x 0.85

=>  Production (LCM/hr) = 61.05 LCM/hr

Given volume to be excavated = 452

=> Time required = 452 / 61.05 = 7.40 hr

.

Ans iii) We know,

Production (BCM/hr) = C x S x V x B x E x L

where, C = cycle per hour = 3600 sec / 20 sec = 180

S = swing factor = 1.21

V = heaped bucked volume = 0.51

B = bucket fill factor = 0.95

E = job efficiency = 0.71

L = Load factor = 0.77 for clay

According to table 3-3, for small excavator , cycle per hour (C) = 160

For swing angle 75 degree, S = 1.21

For clays, fill factor (B) = 0.95

Putting values,

Production (BCM/hr) = 180 x 1.21 x 0.51 x 0.95 x 0.71 x 0.77

=>  Production (BCM/hr) = 57.7 BCM/hr

Also, production per linear meter = Production in BCM/hr / (excavator width x depth)

=> Production per linear meter = 57.7/ (0.76 x 1.52)

=> Production per linear meter = 49.93 linear meter/hr  


Related Solutions

1) A hydraulic shovel with a bottom-dump bucket with a heaped bucket volume of 10 m3...
1) A hydraulic shovel with a bottom-dump bucket with a heaped bucket volume of 10 m3 is excavating tough clay. The swing angle is 103 degrees and the job efficiency is 0.85 + (8/100). Calculate the shovel production in BCM. 2) Estimate the time required to load 408 m3 of gravel from a stockpile into trucks using a clamshell having a heaped bucket capacity of 0.57 m3. Estimated cycle time is 20s. Swing depth factor = 1.0. Job efficiency is...
A shovel with a 3-cy heaped capacity bucket is loading well blasted rock on a highway...
A shovel with a 3-cy heaped capacity bucket is loading well blasted rock on a highway project. The average face height is 22 ft. The shovel has a maximum rated digging height of 30 ft. Most of the cut will require a 140-degree swing of the shovel to load the haul units. Use efficiency factor 45-minues per hour. What is an aggressive production estimate in bank cubic yards? Show all the calculations
Given the following: Bucket volume of loader: 3.6 L m3 (loose cubic meters) Loader cycle: 0.42...
Given the following: Bucket volume of loader: 3.6 L m3 (loose cubic meters) Loader cycle: 0.42 min Truck capacity: 11.5 L m3 Truck traveling time with load 2.28 min Truck maneuvering for tipping and tipping time 0.65 min Truck return time 1.18 min Truck maneuvering for loading 0.40 min Planned activities (lunch, breaks etc…) 0.64 min Waiting time at loader (per cycle) 0.50 min Conversation with supervisor (per cycle) 0.25 min Other cycle time affecting machine performance 0.75 min Swell...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT