Question

In: Economics

Toll lanes on a section of the​ I-40 freeway are being considered in order to reduce...

Toll lanes on a section of the​ I-40 freeway are being considered in order to reduce traffic congestion and travel times. Since this is a government​ project, the​ B-C ratio method must be applied in the evaluation. The following are cost and other​ estimates:

Construction costs​ = ​$17,300,000

Operating and maintenance costs​ = ​$532,000 per year

Projected service life​ = 30 years

Savings in travel times and revenues generated from the tolls​ = ​$5,244,000 in the first year of operation and projected to increase by 2.75​% per year due to the projected annual increase in traffic. In​ addition, environmental analysis estimates that the project will result in increased noise and air pollution that will cause an additional societal health cost of ​$644,000 the first year and is also projected to increase at 2.75​% per year.

Assuming zero market​ (salvage) value at the end of 30 years and a MARR of 10​%per​ year, should the toll lanes be​constructed?

The conventional​ benefit-cost ratio of the project with PW is______​(Round to two decimal​ places.)

According to the​ B-C ratio​ method, the toll lanes should

A.not be constructed

B. be constructed

Solutions

Expert Solution

Initial costs​ = ​$17,300,000

Operating and maintenance costs​ = ​$532,000 per year

Projected service life​ = 30 years

Savings = ​$5,244,000 in the first year and increase by 2.75​% per year

Additional societal health cost of ​$644,000 the first year increase at 2.75​% per year.

MARR = 10%

Calculating the conventional benefit cost ratio using Present Worth.

Conventional Benefit cost ratio = PW of Benefits ÷ Initial Cost + PW of all costs

Step 1 – PW of Benefits

PW = A1 [1 – (1+g) N (1+i) –N ÷ i – g]

PW = ​$5,244,000 [1 – (1 + 0.0275) 30 (1 + 0.10) –30 ÷ 0.10 – 0.0275]

PW = $62,976,998.47

Step 2 – PW of all cost

Initial Cost = ​$17,300,000

PW of annual maintenance cost = ​$532,000 (P/A, 10%, 30)

PW of annual maintenance cost = ​$532,000 (9.42691) = $5,015,116.12

PW of Additional societal health cost

PW = A1 [1 – (1+g) N (1+i) –N ÷ i – g]

PW = ​$644,000 [1 – (1 + 0.0275) 30 (1 + 0.10) –30 ÷ 0.10 – 0.0275]

PW = $7,734,017.36

Total Cost = ​$17,300,000 + $5,015,116.12 + $7,734,017.36 = $30,049,133.48

Step 3 – Calculate B/C Ratio

B/C ratio = PW of all Benefits ÷ PW of all Costs

B/C ratio = $62,976,998.47 ÷ $30,049,133.48

B/C Ratio = 2.09

The conventional​ benefit-cost ratio of the project with PW is 2.09.

According to the​ Benefit Cost ratio​ method, the toll lanes should

As the B/C Ratio is more than ONE

B. be constructed


Related Solutions

#1 Toll lanes on a section of the​ I-40 freeway are being considered in order to...
#1 Toll lanes on a section of the​ I-40 freeway are being considered in order to reduce traffic congestion and travel times. Since this is a government​ project, the​ B-C ratio method must be applied in the evaluation. The following are cost and other​ estimates: -Construction costs​=​$17,200,000 Operating and maintenance costs​ =​$521,000 per year Projected service life​ =24 years Savings in travel times and revenues generated from the tolls​ =​$5,152,000 in the first year of operation and projected to increase...
An existing four lane section of urban freeway (3 lanes each way) is located in rolling...
An existing four lane section of urban freeway (3 lanes each way) is located in rolling terrain and has 10’ travel lanes, no lateral obstructions within 5’ of the pavement edge. The roadway has 8 ramps upstream and 4 ramps downstream of the midpoint of the six mile analysis segment. The traffic stream contains 10% trucks and buses, and 4% RV’s. The peak hour directional volume is 3200 vehicles with the heaviest 15 minute volume of 800 vehicles. What is...
A westbound section of freeway currently has three 12-ft wide lanes, a 6-ft right shoulder, and...
A westbound section of freeway currently has three 12-ft wide lanes, a 6-ft right shoulder, and no ramps within 3 miles upstream and downstream of the segment midpoint. It is on rolling terrain with 10% heavy vehicles and is operating at capacity with a peak-hour factor of 0.9. If the road is expanded to four 11-foot lanes with a 2-foot right shoulder, and traffic after the expansion is projected to increase by 10% with the same heavy vehicle percentage and...
3-lane freeway reduces to 2 lanes total flow in section = 5000 veh/hr lane saturation flow...
3-lane freeway reduces to 2 lanes total flow in section = 5000 veh/hr lane saturation flow rate= 2400 veh/hr traffic density at A: 10veh/km/ln shockwabe speed Wab between A nad B = -10km/hr Find traffic density at B (immediately upstream of the lane reduction) and the stream flows at locations A (far upstream from lane reduction), B, and C (within the lane reduction)
A grade S450 steel universal column section with designation 254x254x132 is being considered for a column...
A grade S450 steel universal column section with designation 254x254x132 is being considered for a column for a office building. Classify the section. Based on the classification, discuss the suitability of the section as a column.
a. An unsymmetrical I section prestressed concrete beam of top flange (350 X 40 mm) in...
a. An unsymmetrical I section prestressed concrete beam of top flange (350 X 40 mm) in size, bottom flange of (200 X 40 mm), 30mm thickness of web and overall depth of 400 mm is prestressed with 19 numbers straight steel wires of 7 mm diameter located at a distance of 15 mm from the bottom of the soffit and 9 numbers of straight steel wires of 6 mm diameter located at a distance of 15 mm from the top...
a. An unsymmetrical I section prestressed concrete beam of top flange (350 X 40 mm) in...
a. An unsymmetrical I section prestressed concrete beam of top flange (350 X 40 mm) in size, bottom flange of (200 X 40 mm), 30mm thickness of web and overall depth of 400 mm is prestressed with 19 numbers straight steel wires of 7 mm diameter located at a distance of 15 mm from the bottom of the soffit and 9 numbers of straight steel wires of 6 mm diameter located at a distance of 15 mm from the top...
An unsymmetrical I section prestressed concrete beam of top flange (350 X 40 mm) in size,...
An unsymmetrical I section prestressed concrete beam of top flange (350 X 40 mm) in size, bottom flange of (200 X 40 mm), 30mm thickness of web and overall depth of 400 mm is prestressed with 19 numbers straight steel wires of 7 mm diameter located at a distance of 15 mm from the bottom of the soffit and 9 numbers of straight steel wires of 6 mm diameter located at a distance of 15 mm from the top of...
a. What is hypothesis testing in statistics? Discuss b. Does Type I error being considered more...
a. What is hypothesis testing in statistics? Discuss b. Does Type I error being considered more serious than Type II error? Explain c. What is the p-value of a test? Give an example
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT