In: Operations Management
Item LLC Leadtime Lot Sizing Rule
Skate |
1 |
1 |
Lot for Lot |
Lace |
1 |
1 |
FOQ = 500 |
Box |
1 |
2 |
FOQ = 500 |
Board |
1 |
2 |
Lot for Lot |
Wheel Assembly |
2 |
1 |
FOQ = 800 |
Body |
2 |
2 |
Lot for Lot |
Axle |
2 |
1 |
Lot for Lot |
Hardware |
2 |
3 |
FOQ = 1500 |
BOM Draw Product Structures Here
Boxed Skates
Skates (2)
Body
Axle (2)
Hardware
Wheel Assembly (2)
Laces (2)
Box
Skateboard
Board
Wheel Assembly (4)
Axle (2)
Hardware
On each transaction file, comment on
any action that should be taken. Fill in
the charts below using this information.
MPS |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
Boxed Skates |
90 |
90 |
90 |
||||||
Skateboards |
200 |
100 |
100 |
Skate Leadtime = 1 Week Lot for Lot Safety Stock = 0
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
|
Gross Requirements |
|||||||||
Scheduled Receipts |
|||||||||
On Hand 150 |
|||||||||
Planned Order Release |
Laces Leadtime = 1 Week FOQ = 500 Safety Stock = 50
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
|
Gross Requirements |
|||||||||
Scheduled Receipts |
|||||||||
On Hand 300 |
|||||||||
Planned Order Release |
Box Leadtime = 2 Weeks FOQ = 500 Safety Stock = 0
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
|
Gross Requirements |
|||||||||
Scheduled Receipts |
|||||||||
On Hand 15 |
|||||||||
Planned Order Release |
MPS |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
Skates boxed |
90 |
90 |
90 |
||||||
Skateboards |
200 |
100 |
100 |
Board Leadtime = 2 Weeks Lot for Lot Safety Stock = 0
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
|
Gross Requirements |
|||||||||
Scheduled Receipts |
|||||||||
On Hand 10 |
|||||||||
Planned Order Release |
Wheel Assembly Leadtime = 1 Week FOQ = 800 Safety Stock = 0
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
|
Gross Requirements |
|||||||||
Scheduled Receipts |
|||||||||
On Hand 500 |
|||||||||
Planned Order Release |
Body Leadtime = 2 Weeks Lot for Lot Safety Stock = 0
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
|
Gross Requirements |
|||||||||
Scheduled Receipts |
|||||||||
On Hand 10 |
|||||||||
Planned Order Release |
MPS |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
Skates boxed |
90 |
90 |
90 |
||||||
Skateboards |
200 |
100 |
100 |
Axle Leadtime = 1 Week Lot for Lot Safety Stock = 0
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
|
Gross Requirements |
|||||||||
Scheduled Receipts |
|||||||||
On Hand 150 |
|||||||||
Planned Order Release |
Hardware Leadtime = 3 Weeks FOQ = 1500 Safety Stock = 150
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
|
Gross Requirements |
|||||||||
Scheduled Receipts |
|||||||||
On Hand 700 |
|||||||||
Planned Order Release |