Question

In: Operations Management

1. Five samples of table legs produced in an automated cutting process were taken each hour...

1. Five samples of table legs produced in an automated cutting process were taken each hour for 20 hours. The length of a table leg in centimeters was measured, and yielded averages and ranges show in the below table. Assume the sample size (n) is 5.

Sample

Avg Length ()

Range (R)

1

95.72

1.0

2

95.24

0.9

3

95.18

0.8

4

95.44

0.4

5

95.46

0.5

6

95.32

1.1

7

95.40

0.9

8

95.44

0.3

9

95.08

0.2

10

95.50

0.6

11

95.80

0.6

12

95.22

0.2

13

95.56

1.3

14

95.22

0.5

15

95.04

0.8

16

95.72

1.1

17

94.82

0.6

18

95.46

0.5

19

95.60

0.4

20

95.74

0.6

    1. Use the data to construct an chart and an R chart. Show all steps and all your work, including: Overall Mean and Overall Average Range; Calculations for Center Line, Upper Control Limit, and Lower Contol Limit, Visual representation of the control chart (either plotted in Excel or drawn to scale on graph paper). You must show all work for full credit.
    2. Is the process in control or out of control? Explain why thoroughly.
  1. A fast-food franchise tracked the number of errors that occurred in customers’ orders. These included wrong menu item, wrong drink size, lack of condiments, wrong price total, etc. Some orders may have had more than one error. In one week, 1250 orders were filled, and a total of 30 errors were discovered. Find the Midline (, and the Upper and Lower Control Limits for a c chart. Show all your work for full credit.

Solutions

Expert Solution

(Please like the answer it will encourage me.)


Related Solutions

Twelve samples, each containing five parts, were taken from a process that produces steel rods. The...
Twelve samples, each containing five parts, were taken from a process that produces steel rods. The length of each rod in the samples was determined. The results were tabulated and sample means and ranges were computed. The results were: Sample Sample Mean (in.) Range (in.) 1 10.002 0.011 2 10.002 0.014 3 9.991 0.007 4 10.006 0.022 5 9.997 0.013 6 9.999 0.012 7 10.001 0.008 8 10.005 0.013 9 9.995 0.004 10 10.001 0.011 11 10.001 0.014 12 10.006...
Five samples of size 4 were taken from a process. A range chart was developed that...
Five samples of size 4 were taken from a process. A range chart was developed that had LCLr = 0 and UCLr = 2.50. Similarly, an average chart was developed with the average range from the five samples, with LCLx = 15.0 and UCLX = 24.0. The ranges for each of the five samples were 1.75, 2.42, 2.75, 2.04, and 2.80, respectively. The values of the sample average for each sample were 19.5, 22.3, 17.4, 20.1, and 18.9, respectively. What...
Five samples of size 4 were taken from a process. Summary statistics are shown below: Sample...
Five samples of size 4 were taken from a process. Summary statistics are shown below: Sample Range Mean 1 1.75 10.5 2 2.42 22.3 3 2.75 17.4 4 2.04 20.1 5 2.80 18.9 What is the lower control limit for a range chart?
Ten samples of 15 parts each were taken from an ongoing process to establish a p...
Ten samples of 15 parts each were taken from an ongoing process to establish a p chart for control. The samples and the number of defectives in each are shown in the following table: Sample n Number of defects in Sample Sample n Number of defects in Sample 1 15 3 6 15 2 2 15 1 7 15 0 3 15 0 8 15 4 4 15 2 9 15 1 5 15 0 10 15 0 Develop a...
Samples of n = 5 units are taken from a process every hour. The x-bar and...
Samples of n = 5 units are taken from a process every hour. The x-bar and R-bar values for a particular quality characteristic are determined. After 25 samples have been collected, we calculate x-bar = 20 and R-bar = 4.56. a) What are the three-sigma control limits for x-bar and R? b) Both charts exhibit control. Estimate the process standard deviation. c) Assume that the process output is normally distributed. If the specifications are 19 ± 5, what are your...
Ten samples of 15 parts each were taken from an ongoing process to establish a p-chart...
Ten samples of 15 parts each were taken from an ongoing process to establish a p-chart for control. The samples and the number of defectives in each are shown in the following table: SAMPLE n NUMBER OF DEFECTIVE ITEMS IN THE SAMPLE 1 15 0 2 15 2 3 15 0 4 15 3 5 15 1 6 15 3 7 15 1 8 15 0 9 15 0 10 15 0 Determine the p−p− , Sp, UCL and LCL...
Twenty-five samples of 100 items each were inspected when a process was considered to be operating...
Twenty-five samples of 100 items each were inspected when a process was considered to be operating satisfactorily. In the 25 samples, a total of 155 items were found to be defective. (a)What is an estimate of the proportion defective when the process is in control? ____?___ (b)What is the standard error of the proportion if samples of size 100 will be used for statistical process control? (Round your answer to four decimal places.) ____?____ (c)Compute the upper and lower control...
Problem 10-23 Ten samples of 15 parts each were taken from an ongoing process to establish...
Problem 10-23 Ten samples of 15 parts each were taken from an ongoing process to establish a p-chart for control. The samples and the number of defectives in each are shown in the following table: SAMPLE n NUMBER OF DEFECTIVE ITEMS IN THE SAMPLE 1 15 2 2 15 1 3 15 1 4 15 1 5 15 3 6 15 1 7 15 0 8 15 2 9 15 1 10 15 0 a. Determine the p−p−, Sp, UCL...
Twenty samples with 100 units each were taken; with the following number of defectives in each...
Twenty samples with 100 units each were taken; with the following number of defectives in each respective sample: 11, 2, 7, 5, 6, 7, 8, 5, 3, 6, 4, 3, 5, 6, 2, 5, 0, 9, 10, and 8. Calculate the center line, upper control limit, and lower control limit for a 3s p-chart. (RE: As your starting point, recall that p-charts represent percentages of defects for samples.) Plot the points on the chart. Comment on whether the process is...
Table 1 The following table shows output per hour produced by the different units of labor....
Table 1 The following table shows output per hour produced by the different units of labor. Table 1 Number of Workers Output per Hour Price of the Product 0 0 $3 1 7 $3 2 12 $3 3 15 $3 4 17 $3 5 18 $3 The marginal revenue product of a resource is equal to the product of the marginal product of an input and marginal revenue.      8.   According to Table 1, if the wage rate is $9 per hour,...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT