In: Accounting
The Company P produces doors and windows. The company produces 4 windows per door. In each window the company uses half an hour of direct labor and for each door uses one hour. The prime costs of making doors are $ 20 and $ 16 for the windows. Labor represents 60% of the prime costs. The indirect costs estimated for this production total $ 330,000. The company distributes indirect costs through the use of machine hours. The labor cost used in the production of the windows is $ 240,000. A door requires 2 hours of machinery and sales need one hour. Required determine the cost per unit and total of doors and windows under premise a and answer the required b: a. The company distributes the indirect costs using machine hours b. If the actual indirect costs are $ 210,000 determine the effect of this on the cost per unit of each product
Hi,
I have answered both parts of the question along with the requisite calculations. In the question it is mentioned "A door requires 2 hours of machinery and sales need one hour." I am assuming window require one hour as the hours for windows are not referenced anywhere and sales does not require machine hours.
Answer Summary | Doors | Windows | ||
Production | 12,500 | 50,000 | ||
Case a - indirect costs $330,000 | $ 40.80 | $ 25.20 | ||
Case b - indirect costs $210,000 | $ 37.60 | $ 23.60 | ||
a. Cost per unit and number of doors: The company distributes the indirect costs using machine hours | ||||
Window | ||||
Prime Cost | 16 | |||
Labor Cost per hour (60% of Prime cost) (a) | 9.6 | |||
Hours per window (b) | 0.5 | |||
Labor cost per unit (a)/(b) | 4.8 | |||
Labor cost incurred in production of windows | 240,000 | |||
Therefore, total windows produced ($240,000/4.8) | 50,000 | |||
Doors are produced in the ratio 1:4 (50,000/4) | 12,500 | |||
Door | Window | |||
Units produced | 12,500 | 50,000 | ||
Machine hours | 2 | 1 | ||
Total machine hours | 25,000 | 50,000 | 75,000 | |
Indirect Cost | $330,000 | |||
Allocation of cost per hour ($330,000/75,000 hours) | $ 4.40 | |||
Cost of production: | ||||
Door | Window | |||
Prime Cost (a) | $ 20 | $ 16 | ||
Labor Cost per hour (60% of Prime cost) | $ 12 | $ 9.6 | ||
Hours (1 for door and 0.5 for window) | 1 | 0.5 | ||
Labor cost per unit (b) | $ 12 | $ 4.8 | ||
Direct cost (a)+(b) | $ 32.0 | $ 20.8 | ||
Indirect costs ($4.40/hour * 2hours/1 hour) | $ 8.8 | $ 4.4 | ||
Cost of production: per unit | $ 40.80 | $ 25.20 | ||
b) Cost per unit: If the actual indirect cost is $210,000 | ||||
Indirect Cost | $210,000 | |||
Allocation of cost per hour ($210,000/75,000 hours) | $ 2.80 | |||
Cost of production: | ||||
Door | Window | |||
Prime Cost (a) | $ 20 | $ 16 | ||
Labor Cost per hour (60% of Prime cost) | $ 12 | $ 9.60 | ||
Hours (1 for door and 0.5 for 4 windows) | 1 | 0.5 | ||
Labor cost per unit (b) | $ 12 | $ 4.8 | ||
Direct cost (a)+(b) | $ 32.0 | $ 20.80 | ||
Indirect costs ($2.80/hour * 2hours/1 hour) | $ 5.6 | $ 2.8 | ||
Cost of production: per unit | $ 37.60 | $ 23.60 |
Please do rate my answer and good luck!
Regards
D