Question

In: Civil Engineering

A truck will haul an average load of 15 cy, heaped capacity, and loose measure per...

A truck will haul an average load of 15 cy, heaped capacity, and loose measure per load. Use average values of swell factors in Table 7.3 on p. 131 of your textbook to determine the volume of the truck in bank measure when the material is sand, ordinary earth, dense clay, and well-blasted rock.

Then, using an Excel spreadsheet, determine the number of trucks required to move material in the following scenario:

A project requires 40,000 cy of compacted fill that must be completed in 32 working days. The fill material will be hauled to the site in 21 cy loose measure trucks. The cycle time for a truck is 40 min. per trip. The swell factor for the earth is 25% and the shrinkage factor is 10%. Assume 8 hours per day and a 45-min. effective hour. Determine the number of required trucks to complete the project in 32 days.

Deliverable:
Upon completion of this project, you will deliver an excel spreadsheet to include:

  • Tables of all information (data) given in the problem
  • Formulas that reference cells thus creating dynamic formulas that will change if information in the tables changes
  • The final answer highlighted in yellow.

Solutions

Expert Solution

Given data:
Haul an average load of Track = L = 15 cy
Sand, Sw = 10% − 15%:
Assume Avg. swell factor = Sw = 12%
Volume in truck, B = L / (1 + Sw)
B= 13.39 cy
Ordinary earth, Sw = 20% − 30%:
Assume Avg. swell factor = Sw = 25%
Volume in truck, B = L / (1 + Sw)
B= 12.0 cy
Dense clay, Sw = 25% − 40%:
Assume Avg. swell factor = Sw = 35%
Volume in truck, B = L / (1 + Sw)
B= 11.1 cy
Well-blasted rock, Sw = 50% − 80%:
Assume Avg. swell factor = Sw = 55%
Volume in truck, B = L / (1 + Sw)
B= 9.7 cy
Required production ratefor compacted measure
Given,
Volume for compacted measure = L1 = 40000 cy
Completion time = T = 32 days
Production rate = L1 / T = 1250 cy/day
Production rate of one truck:
Given,
Swell factor for the earth = Sw = 25%
Loose measure payload in truck, L2 = 21 cy
Bank measure payload in truck, B = L2/ (1 + Sw)
B= 16.8 cy
Shrinkage factor = 10%
Compacted measure payload in truck, C = (1 − Sh) B
C= 15.12 cy/day
The cycle time for a truck is =   T     = 40 min. per trip.
8 hours per day and a 45 min. effective hour.
Total effective hour = te = 6 hour / day
Daily production rate = P = (C/T)x te x 60 min. / hour
for compacted measure P = 136.08 cy/day,
Number of required trucks:
Required trucks = (Required production rate) / (production rate of one truck)
Required trucks = P/C
= 9 tracks
                                                                                                  Given data:                                             Haul an average load of Track = L =                             15      cy                                                      Sand, Sw = 10% − 15%:                                           Assume swell factor =                   12%                     Volume in truck, B = L / (1 + Sw)                                                       B=      13.39   cy                                                                      Ordinary earth, Sw = 20% − 30%:                                                 Assume swell factor =                   25%                     Volume in truck, B = L / (1 + Sw)                                                       B=      12.0    cy                                                                      Dense clay, Sw = 25% − 40%:                                             Assume swell factor =                   35%                     Volume in truck, B = L / (1 + Sw)                                                       B=      11.1    cy                                                                      Well-blasted rock, Sw = 50% − 80%:                                              Assume swell factor =                   55%                     Volume in truck, B = L / (1 + Sw)                                                       B=      9.7     cy                                                                                                                                                                                                                                                                                                                      Required production ratefor compacted measure                                           Given,                                          Volume for compacted measure = L1 =                             40000   cy      Completion time = T =                           32      days                                                    Production rate = L1 / T =                      1250    cy/day                                                          Production rate of one truck:                                           Given,                                          Swell factor for the earth = Sw =                               25%             Loose measure payload in truck, L2 =                            21      cy                                                      Bank measure payload in truck, B = L2/ (1 + Sw)                                                                 B=      16.8    cy                                                              shrinkage factor =              10%                             Compacted measure payload in truck, C = (1 − Sh) B                                                              C=      15.12   cy/day                                                          The cycle time for a truck is = T =                             40       min. per trip.         8       hours per day and a             45       min. effective hour.           Total effective hour = te =                     6       hour / day              Daily production rate = P = (C/T)x te x 60 min. / hour                                          for compacted measure           P =     136.08  cy/day,                                                                 Number of required trucks:                                              Required trucks = (Required production rate) / (production rate of one truck)                                           Required trucks =               P/C                                      =      9       tracks           

Related Solutions

A shovel with a 3-cy heaped capacity bucket is loading well blasted rock on a highway...
A shovel with a 3-cy heaped capacity bucket is loading well blasted rock on a highway project. The average face height is 22 ft. The shovel has a maximum rated digging height of 30 ft. Most of the cut will require a 140-degree swing of the shovel to load the haul units. Use efficiency factor 45-minues per hour. What is an aggressive production estimate in bank cubic yards? Show all the calculations
A dump truck with a heaped capacity of 10 yd3 is used to dispose of excavated...
A dump truck with a heaped capacity of 10 yd3 is used to dispose of excavated material at a dump site 3.5 mile away from the job site. The average velocity of the dump truck is 40 kph. The dump time is 30 seconds, load time is 40 seconds. Assume a 50 minutes/hour efficiency, determine the production of the dump truck to complete the 12’ deep excavation of 100’x200’ size building footprint?
The average clothes washer uses 15 gallons of water per load, with a standard deviation of...
The average clothes washer uses 15 gallons of water per load, with a standard deviation of 3.0 gallons. What is the probability that a random sample of 30 loads will provide a sample mean within one half gallon of the population mean?
The average clothes washer uses 15 gallons of water per load, with a standard deviation of...
The average clothes washer uses 15 gallons of water per load, with a standard deviation of 3.0 gallons. What is the probability that a random sample of 30 loads will provide a sample mean within one half gallon of the population mean?
Suppose that a truck has a legal load carrying capacity of 10,000 lbs. We want to...
Suppose that a truck has a legal load carrying capacity of 10,000 lbs. We want to load product, with an average weight of 21 lbs. and a standard deviation of 4 lbs. onto the truck. If we have 473 of these units, how many can we load on the truck if we only want to have a 1% risk chance of “overloading” the truck? a. 473 b. 472 c. 471 d. 470 e. 463
Suppose that a truck has a legal load carrying capacity of 10,000 lbs. We want to...
Suppose that a truck has a legal load carrying capacity of 10,000 lbs. We want to load product, with an average weight of 21 lbs. and a standard deviation of 4 lbs. onto the truck. If we have 473 of these units, how many can we load on the truck if we only want to have a 1% risk chance of “overloading” the truck? a. 473 b. 472 c. 471 d. 470 e. 463
Consider a log splitter with a load capacity of 15 ton which is run by a...
Consider a log splitter with a load capacity of 15 ton which is run by a 10 GPM hydraulic pump. The bore and rod diameter of the log splitter cylinder are 4 in. and 2 in., respectively, whereas the stroke length is 24 in. Determine the following: a) Maximum pressure generated in the extension stroke b)Extension velocity of the cylinder c)Power (HP) generated in the extension stroke when pushing the maximum load d) Retraction velocity of the cylinder e) Power...
The National Association of Truck Drivers claims that the average truck driver travels 60000 miles per...
The National Association of Truck Drivers claims that the average truck driver travels 60000 miles per year. The population standard deviation of the mileage is 5000 miles. The Connecticut Valley Trucking Corporation surveyed 48 Truck Drivers and found the mean mileage for its Truck Drivers was 59500 miles driven per year. Is Connecticut Valley’s mileage different from that claimed by the National Association of Truck Drivers at the .05 significance level?
Question 1 (25 marks) A measure of average annual income in a country. GDP per capita...
Question 1 A measure of average annual income in a country. GDP per capita as a measure of material wellbeing is a widely used summary measure of incomes in a country. It is calculated by dividing Gross Domestic Product (GDP)—the total value of all the goods and services produced in a country in a given period, such as a year—by the population of the country. GDP per capita is therefore a measure of average annual income in a country. •...
On Time Airlines claims their average delay is less than 15 minutes per flight. A random...
On Time Airlines claims their average delay is less than 15 minutes per flight. A random sample of 35 flights has a sample mean of 14 minutes and standard deviation of 7 minutes. You will need to test the claim that the average delay is less than 15 minutes per flight using a 2.5% level of significance. a) State the hypotheses b) Find the rejection region. c) Will you reject or retain the null hypothesis? Show all work to support...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT